30 Juni 2026

TNI AU Juga Lakukan Uji Performa Roket WAFAR RD-702

30 Juni 2026

Uji performa roket WAFAR RD-702 kaliber 70mm buatan PT DI (photos: TNI AU)

TNI AU. Dinas Penelitian dan Pengembangan TNI Angkatan Udara (Dislitbangau) berhasil mendemonstrasikan penembakan roket Wrap Around Fin Aerial Rocket (WAFAR) RD-702 Practice kaliber 70 mm produksi PT Dirgantara Indonesia di Lapangan Tembak Nanggala, Pacitan, Jawa Timur, Kamis (18/6/2026). Pengujian tersebut menjadi bagian dari upaya memastikan performa dan keandalan alutsista produksi dalam negeri sekaligus mendukung proses sertifikasi dan pengembangan roket nasional.


Roket WAFAR RD-702 Practice kaliber 70 mm merupakan salah satu produk PT Dirgantara Indonesia yang memiliki fleksibilitas tinggi dan dapat diintegrasikan pada berbagai platform udara, termasuk helikopter dan pesawat tempur.


Kadislitbangau Kolonel Tek Rachmadi Anggoro, S.E., M.Sc., M.S.S., yang diwakili Sesdislitbangau Kolonel Tek Sapta Jengkar P., M.Sc., M.I.Pol. menyampaikan bahwa demonstrasi tersebut merupakan bagian dari tugas Dislitbangau untuk memastikan setiap alutsista hasil produksi dalam negeri memiliki performa dan keandalan yang teruji sebagai wujud nyata dukungan terhadap kemandirian industri pertahanan nasional.


Pengujian dilakukan untuk mengamati performa roket yang meliputi aspek keandalan peluncuran, karakteristik terbang, serta efektivitas sistem secara keseluruhan sebagai bagian dari pelaksanaan tugas pokok Dislitbangau. Keberhasilan uji tembak tersebut menjadi tolok ukur penting dalam proses sertifikasi dan pengembangan roket nasional, sementara hasil pengujian akan menjadi bahan evaluasi bagi penyempurnaan sistem pada tahap berikutnya.


Kadislitbangau juga menekankan kepada seluruh personel pelaksana agar senantiasa mengutamakan keselamatan terbang dan kerja, melaksanakan seluruh prosedur sesuai ketentuan, serta mendokumentasikan hasil pengujian secara lengkap dan akurat.


Kegiatan demonstrasi penembakan roket WAFAR RD-702 Practice kaliber 70 mm berlangsung dengan aman dan lancar. Diharapkan hasil pengujian tersebut semakin memperkuat ekosistem industri roket nasional melalui sinergi antara industri pertahanan, pengguna, lembaga penelitian, dan mitra strategis nasional dalam mendukung terwujudnya TNI AU yang AMPUH.

13 komentar:

  1. NSM bataaallll haha!⛔️🤣😭

    BalasHapus
  2. Mabuhayyy
    SSV 3 PH sukses Seremoni Loncing di PT Pal
    Full Kembang Api & Laser cuy haha!🥳⚡️🤗

    Pasti Nambah lagi SSV 163 meter jugak donk..ntar ada yg NGAMUK🔥 dari negri banana fisank kl haha!🍌🤣😂


    ⬇️✅️⬇️✅️⬇️
    https://www.facebook.com/story.php?story_fbid=122313976628196909&id=61555907296700

    BalasHapus
    Balasan
    1. Netizens sipino berisiknya minta ampun om

      Hapus
    2. Sama seperti geng beruk malons

      Hapus
    3. Sama seperti netizen sini juga.🤣 Vietnam dan Thailand paling sama saja, tapi kita tidak bisa baca tulisan mereka.😶

      Hapus
  3. stelah wafar? Bikin Rudal donk minimal yg 1000km haha!👌🚀😋

    BalasHapus
  4. LUNAS = 1 PROTOTIPE KF21
    LUNAS = 1 PROTOTIPE KF21
    LUNAS = 1 PROTOTIPE KF21
    https://defense-studies.blogspot.com/2026/06/indonesia-siap-terima-prototipe-jet.html?sc=1781141080257#c7962626431917344692
    ===================
    ===================
    LCS By LUNAS = TIDAK LUNAS
    -
    17 VENDOR TAGIH HUTANG LCS = 15 TAHUN
    PROTANK = TAGIH HUTANG
    MTU Services = TAGIH HUTANG
    Contraves Sdn Bhd = TAGIH HUTANG
    Axima Concept SA = TAGIH HUTANG
    Contraves Advanced Devices Sdn Bhd = TAGIH HUTANG
    Tyco Fire, Security & Services Malaydesh Sdn Bhd = TAGIH HUTANG
    iXblue SAS = TAGIH HUTANG
    iXblue Sdn Bhd = TAGIH HUTANG
    Bank Pembangunan Malaydesh Bhd = TAGIH HUTANG
    AmBank Islamic Bhd, AmBank (M) Bhd = TAGIH HUTANG
    MTU Services = TAGIH HUTANG
    Affin Hwang Investment Bank Bhd = TAGIH HUTANG
    Bank Muamalat Malaydesh Bhd = TAGIH HUTANG
    Affin Bank Bhd, Bank Kerjasama Rakyat Malaydesh Bhd = TAGIH HUTANG
    Malayan Banking Bhd (Maybank) = TAGIH HUTANG
    Kuwait Finance House (Malaydesh) Bhd = TAGIH HUTANG
    https://theedgemalaydesh.com/article/high-court-decide-boustead-naval-shipyard-restraining-order-against-creditors-june
    ----------------------------------
    5x Ganti RAJA = ZONK MRCA SPH LCS NSM
    5x Ganti PM = PRANK MRCA SPH LCS NSM
    6x Ganti Mindef = PRANK MRCA SPH LCS NSM
    -
    2011 Najib Razak Ahmad Zahid Hamidi
    2015 Najib Razak Hishammuddin Hussein
    2018 Mahathir Mohamad Mohamad Sabu
    2020 Muhyiddin Yassin Ismail Sabri
    2021 Ismail Sabri Hishammuddin Hussein
    2022 Anwar Ibrahim Mohamad Khaled Nordin
    ----------------------------------
    2026 MALONDESH = CUT DEFENSE BUDGET
    2026 MALONDESH = NSM BANNED - AMRAAM BLOKIR
    2026 MALONDESH = F18 BATAL - UH60A BATAL
    2026 MALONDESH = REWORK 4000 PIPA DAN KABEL LCS
    2026 MALONDESH = PHK MASSAL
    2026 MALONDESH = FREEZE PROCUREMENT
    2025 MALONDESH = SIPRI KOSONG
    2024 MALONDESH = SIPRI KOSONG
    2023 MALONDESH = CANCELLED PROCUREMENT
    --------------------------------------------
    😝KF 21 LUNAS versus LCS BY LUNAS : TIDAK LUNAS 15 TAHUN😝

    BalasHapus
  5. PT Pindad buat roket FFAR dan PT DI buat roket WAFAR ga ada yg minat bikin Rudal basis Roket RX..🤔

    BalasHapus
    Balasan
    1. PT DI bikin R-Han yg berbasis roket RX.

      Hapus
  6. Dulu ada roket namanya Taming Sariiiiii 🤣🤣🤣 sekarang dipakai pasukan asgard 😁😁😁

    BalasHapus
  7. 2016 EKSPOR SSV B1 versus LCS DELAY
    2026 LAUNCHING SSV B2 versus LCS DELAY
    ----------------------------------
    SSV Batch 1:
    BRP Tarlac (LD-601) & BRP Davao del Sur (LD-602)
    This initial $92 million contract marked Indonesia’s first major military warship export. The ships were modeled after the Indonesian Navy's Makassar-class.
    • June 2014: The Philippine Department of National Defense officially signs the contract with PT PAL Indonesia for two SSV units.
    • January 2015: First steel cutting and construction begins for the lead ship, SSV-1 (BRP Tarlac).
    • June 2015: Keel laying ceremony takes place for the sister ship, SSV-2 (BRP Davao del Sur).
    • January 17, 2016: BRP Tarlac (LD-601) is launched at the shipyard in Surabaya.
    • May 2016: BRP Tarlac (LD-601) is officially delivered and arrives in Manila, later commissioning on June 1, 2016.
    • September 2016: BRP Davao del Sur (LD-602) is launched in Surabaya.
    • May 10, 2017: BRP Davao del Sur (LD-602) is formally delivered and inducted into active service.
    ----------------------------------
    BSSV atch 2:
    Follow-On Upgraded SSVs (LD-603 & LD-604)
    Following satisfaction with Batch 1, the Philippines ordered a second batch under the Landing Docks Acquisition Project featuring improved troop lift capabilities and larger helicopter decks.
    • June 2022: The Philippines signs a follow-on repeat contract with PT PAL Indonesia for two additional upgraded SSV units.
    • August 10, 2023: First steel cutting ceremony takes place for the 3rd LPD overall (LD-603).
    • January 22, 2024: Keel laying for the 3rd LPD (LD-603) and simultaneous first steel cutting for the 4th LPD (LD-604).
    • May 29, 2024: Keel laying ceremony is completed for the 4th LPD (LD-604).
    • April 2025: Fleet maintenance milestone occurs as Batch 1 lead ship BRP Tarlac returns to PT PAL's Surabaya shipyard for an extensive Maintenance, Repair, and Overhaul (MRO) program.
    • June 30, 2026: The 3rd LPD, BRP Ilocos Norte (LD-603), is officially launched in Surabaya after accelerating its dock construction phase down to just six months.
    • Late 2026 (Projected): Scheduled delivery and final handover of BRP Ilocos Norte (LD-603) to the Philippine Navy following sea trials.
    • 2027 (Projected): Anticipated launch and delivery of the 4th upgraded SSV (LD-604), completing the total fleet of four Indonesian-built strategic sealift assets.
    ===================
    ===================
    LCS By LUNAS = TIDAK LUNAS 16 TAHUN
    -
    2011 (Pengadaan): Kontrak enam kapal LCS diberikan ke Galangan Boustead tanpa tender terbuka.
    2019 (Target Awal): Kapal pertama (KD Maharaja Lela) seharusnya dikirim ke TLDM pada April 2019.
    2022 (Target Asal): Jadwal asli mengharuskan lima kapal selesai dan diserahkan.
    2023 (Target Akhir Kontrak Asal): Kapal terakhir seharusnya diserahterimakan Juni 2023, namun kapal pertama baru selesai 60%.
    2025 (Estimasi Baru): Kapal pertama mundur hingga 2025, setelah proyek berjalan 12 tahun dan dibayar RM6 miliar.
    2026 (Revisi Pengiriman Pertama): Penyerahan lima kapal diubah bertahap, dengan kapal pertama dijadwalkan akhir 2026.
    2029 (Target Penyelesaian Baru): Kelima kapal LCS diperkirakan baru selesai sepenuhnya pada tahun 2029.
    ----------------------------------
    😝EKSPOR SSV VERSUS LCS 16 TAHUN DELAY😝

    BalasHapus
  8. LD-603 FILIPINA =
    SELESAI 6 BULAN DOCKING
    SELESAI 6 BULAN DOCKING
    SELESAI 6 BULAN DOCKING
    https://defense-studies.blogspot.com/2026/07/pt-pal-lakukan-launching-kapal-lpd-ke-3.html?sc=1782865796211#c5761900414098458099
    ----------------------------------
    LUNAS = 1 PROTOTIPE KF21
    LUNAS = 1 PROTOTIPE KF21
    LUNAS = 1 PROTOTIPE KF21
    https://defense-studies.blogspot.com/2026/06/indonesia-siap-terima-prototipe-jet.html?sc=1781141080257#c7962626431917344692
    ----------------------------------
    INDONESIA 48 KAAN
    INDONESIA 48 KAAN
    INDONESIA 48 KAAN
    https://www.tusas.com/medya-merkezi/haberler/turkiye-ile-endonezya-arasinda-atilan-imzalarla-turkiye-tarihinin-rekor-ihracat-sozlesmesi-gerceklestirildi-anlasma-tusas-tarafindan-milli-imkanlarla-uretilen-48-adet-milli-muharip-ucak-kaan-in-satisini-kapsiyor
    ----------------------------------
    2024 BUKTI 42 RAFALE RESMI DASSAULT =
    6 RAFALE SEPTEMBER 2022
    18 RAFALE AGUSTUS 2023
    18 RAFALE JANUARI 2024
    DASSAULT AVIATION = 42 RAFALE
    https://www.dassault-aviation.com/fr/groupe/presse/press-kits/entree-en-vigueur-de-la-derniere-tranche-de-18-rafale-pour-lindonesie/
    ----------------------------------
    RESMI : PROCUREMENT MRCA JULIET
    https://sirup.inaproc.id/sirup/rup/detailPaketPenyedia2020?idPaket=66843686
    ----------------------------------
    RESMI : PROCUREMENT MRCA SURABAYA
    https://sirup.inaproc.id/sirup/rup/detailPaketPenyedia2020?idPaket=66843682
    ----------------------------------
    WELCOME 24 J10CE - PL15E
    WELCOME 24 J10CE - PL15E
    WELCOME 24 J10CE - PL15E
    https://defense-studies.blogspot.com/2026/06/indonesia-dilaporkan-mencapai.html#comment-form
    -
    KAYA = KAAN - RAFALE - KF21 - J10CE - KIZILELMA –
    M364FA - GARIBALDI - FMP - PPA - ISTIF
    ===================
    ===================
    MISKIN = F18 BATAL - BLACKHAWK BATAL - NSM BATAL - CUT BUDGET
    -
    PULLED OUT (DIKELUARKAN) AUSTRALIA =
    Armidale class is a class of patrol boats built for the Royal Australian Navy (RAN). Planning for a class of vessels to replace the fifteen Fremantle-class patrol boats began in 1993 as a joint project with the Royal Malaydesh n Navy, but was cancelled when Malaydesh pulled out of the process. The project was reopened in 1999 under the designation SEA 1444, with the RAN as the sole participant.
    -
    17 VENDOR TAGIH HUTANG LCS = 16 TAHUN
    PROTANK = TAGIH HUTANG
    MTU Services = TAGIH HUTANG
    Contraves Sdn Bhd = TAGIH HUTANG
    Axima Concept SA = TAGIH HUTANG
    Contraves Advanced Devices Sdn Bhd = TAGIH HUTANG
    Tyco Fire, Security & Services Malaydesh Sdn Bhd = TAGIH HUTANG
    iXblue SAS = TAGIH HUTANG
    iXblue Sdn Bhd = TAGIH HUTANG
    Bank Pembangunan Malaydesh Bhd = TAGIH HUTANG
    AmBank Islamic Bhd, AmBank (M) Bhd = TAGIH HUTANG
    MTU Services = TAGIH HUTANG
    Affin Hwang Investment Bank Bhd = TAGIH HUTANG
    Bank Muamalat Malaydesh Bhd = TAGIH HUTANG
    Affin Bank Bhd, Bank Kerjasama Rakyat Malaydesh Bhd = TAGIH HUTANG
    Malayan Banking Bhd (Maybank) = TAGIH HUTANG
    Kuwait Finance House (Malaydesh) Bhd = TAGIH HUTANG
    https://theedgemalaydesh.com/article/high-court-decide-boustead-naval-shipyard-restraining-order-against-creditors-june
    ----------------------------------
    2011 (Pengadaan): Kontrak enam kapal LCS diberikan ke Galangan Boustead tanpa tender terbuka.
    2019 (Target Awal): Kapal pertama (KD Maharaja Lela) seharusnya dikirim ke TLDM pada April 2019.
    2022 (Target Asal): Jadwal asli mengharuskan lima kapal selesai dan diserahkan.
    2023 (Target Akhir Kontrak Asal): Kapal terakhir seharusnya diserahterimakan Juni 2023, namun kapal pertama baru selesai 60%.
    2025 (Estimasi Baru): Kapal pertama mundur hingga 2025, setelah proyek berjalan 12 tahun dan dibayar RM6 miliar.
    2026 (Revisi Pengiriman Pertama): Penyerahan lima kapal diubah bertahap, dengan kapal pertama dijadwalkan akhir 2026.
    2029 (Target Penyelesaian Baru): Kelima kapal LCS diperkirakan baru selesai sepenuhnya pada tahun 2029.
    ----------------------------------
    😝SELESAI 6 BULAN LD 603 VERSUS LCS16 TAHUN DELAY😝

    BalasHapus