Progres saat ini untuk kapal LCS pertama (photo: Lunas shipyard)
KUALA LUMPUR - Status pembinaan kapal tempur pesisir (LCS) kedua ketika ini mencapai kemajuan 64.66 peratus, kata Menteri Pertahanan, Datuk Seri Mohamed Khaled Nordin.
Beliau berkata, jumlah bayaran yang dibuat bagi pembinaan kapal LCS kedua itu adalah berdasarkan kontrak yang telah ditandatangani, dan bukannya mengikut kemajuan setiap kapal secara individu.
"Bayaran dilaksanakan mengikut kemajuan keseluruhan projek LCS sebagaimana pandangan pihak Suruhanjaya Pencegahan Rasuah Malaysia (SPRM) dan Jawatankuasa Siasatan Tadbir Urus, Perolehan dan Kewangan Kerajaan (JKSTUPKK).
"Selaras dengan perkara itu kerajaan telah membayar RM7.15 bilion iaitu bersamaan 63.69 peratus, berbanding perancangan asal pembayaran iaitu 68.43 peratus berdasarkan kontrak mengikut kemajuan semasa perolehan LCS kelima-lima kapal secara keseluruhannya,” katanya.
Beliau berkata demikian bagi menjawab soalan Datuk Seri Ikmal Hisham Abdul Aziz (PN-Tanah Merah) yang bertanyakan peratus terkini pembinaan kapal LCS kedua serta jumlah bayaran yang telah diselesaikan Kementerian Pertahanan kepada Lumut Naval Shipyard (LUNAS).
Mohamed Khaled berkata, status terkini bagi kapal LCS ketiga pula berada pada tahap 56.48 peratus, manakala LCS keempat 51.10 peratus, dan kapal LCS kelima 42.33 peratus.
Beliau berkata, kementerian menaruh keyakinan bahawa projek pembinaan lima kapal LCS itu dapat diserahkan kepada Tentera Laut Diraja Malaysia (TLDM) mengikut tempoh masa yang telah dirancangkan secara berperingkat mulai Ogos 2026.
Fregat Australia HMAS Ancac
Menjawab soalan tambahan Ikmal Hisham yang ingin tahu sama ada kerajaan berminat untuk mendapatkan kapal HMAS Anzac dari Australia yang baru dilucutkan tauliah pada Mei lepas bagi penggunaan sementara TLDM, beliau berkata, kapal itu tidak bersesuaian untuk kegunaan sementara.
"Setelah diteliti TLDM merumuskan kapal yang dimaksudkan itu... ia tidak bersesuaian. Ia adalah berdasarkan perkara seperti isu commonality peralatan selain kos perolehan yang tidak menguntungkan kepada kerajaan, lebih-lebih lagi jika kita lakukan perolehan terhadap kapal HMAS Anzac.
"Proses perolehan itu dijangka mengambil masa yang lama, sehingga 2027 dan pada tahun itu kita sudah dibekalkan dengan dua kapal LCS. Kapal itu akan diserah kepada TLDM dan mula beroperasi dalam tahun 2027,” katanya.
Selain itu, Mohamed Khaled berkata, kerajaan baru-baru ini juga telah membuat perolehan bagi mendapatkan tiga kapal misi pesisir (LMS) dari Turkiye yang dijangka siap menjelang akhir 2027.
"Jadi lima kapal akan mula berkhidmat dengan TLDM dan oleh kerana hampir keseluruhan kapal HMAS Anzac ini menggunakan peralatan yang berbeza, maka kita membuat keputusan ia tidak sesuai dan bukan untuk kepentingan kerajaan serta rakyat Malaysia,” katanya.
(Bernama)
real contract and delivery five units C130J Hercules
BalasHapusreal contract and delivery two unit Frankethal class Countermine vessels (Pulau Fani class)
real contract and delivery four units KCR 60 Fast missiles boats PT PAL
real contract and delivery 9 units Bell 412 EPI
real contract and delivery 8 additional H225 M
real contract and delivery 2 units Bell 429 Global Ranger
real contract and delivery 18 Medium weight tank Harimau
real contract and delivery 22 Pandur II IFV
real contract and delivery two unit Hospital Ships
real contract and delivery one unit Command and control variant C295
real contract and delivery one unit CN235 MPA
real contract and delivery 7 Badak FSV, 26 Anoa apc and 10 additional Komodo recce vehicles in 2022
real contract and delivery 4 AS 550 Fennec and 8 AS565 MBE, in 2024
real contract and delivery five NC212i in 2023
real contract and delivery one Leonardo RAT 31 DL/M
real contract and delivery five C130H ordered from Australia in 2013 (finished in 2020) after received Grant of 4 C130H
real contract and delivery 9 Teluk Bintuni class LST
real contract and delivery six CH4B UCAV ordered in 2019
real contract t and process building of Abeking & Rasmussen design ocean Hydrography ship
real contract and process building two AH140 AAW Frigate
real contract and process building two OPV 90 ASW patrol vessels
real contract and process building 42 Dassault Rafale F4 fighter
real contract and process building two A400M heavy cargo aircraft
real contract and delivery M3 Amphibious bridging system
real contract and delivery 3 KT1 Wong Bee ordered in 2018 along with radar and spares for T/A50
real contract and process building 13 GM 403 GCI radar from Thales
real contract and process building 12 ANKA S UCAV
real contract and process building additional CH4B UCAV
real contract and delivery Slingshot Satcom system
real contract and delivery Falcon 8X aircraft
real contract and process Thales Alenia earth observation satelite
real contract and process 22 S70M Blackhawk
real contract and process 6 N219 aircraft
real contract and process 3 CN235 for Army
real contract and process 2 PPA patrol Frigate
real contract and process 2 Scorpene Subs
real contract and process Khan Short Range ballistic missiles from Turki
real contract and process Trisula Air defense system
real contract and process 6 T50i aircraft
real contract and delivery Oiler and replenishment ship
real contract and delivery several Tug Harbor ships
real contract and process Submarine rescue vessels and system
real contract and delivery two Large LCU for army
real contract and process 45 Atmaca
===============
barter sawit 10 LCA 8 FLIT
akan 2 Leonardo P-72M
akan 3 anka ISR ompong
LOA LMS B2 Ada-Class DOWNGRADE
Dibayar PBB/UN = 4x4 Ejder Yalçin
LCS dibayar 6 jadi NOL
OPV dibayar 3 jadi 1
πBEDA KASTA BEDA LEVELπ
Did you know...?
BalasHapusBerapapun progressnya, itu kapal sudah mulai kerja 12 tahun lalu, dan hingga sekarang tak selesai satupon...
π€£π€£π€£π€£π€£π€£
ZONK a.k.a GHOIB om Ps πππππ€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£
HapusDid you know?.. I know lah..
Hapus... besi burok.. wkwkwkwkwk
Did you know ? We are know lah..
HapusAnd we are all people in SEA region...LOL
Dan drakor pun berlanjutπ₯π₯π₯π₯ππππππ€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺ
BalasHapusMasih kurang bayar alias NGUTANG..
BalasHapusπ€£π€£π€£π±
"...kerajaan telah membayar RM7.15 bilion iaitu bersamaan 63.69 peratus, berbanding perancangan asal pembayaran iaitu 68.43 peratus berdasarkan kontrak ..."
Gila...sdh bayar RM 7,15b tp 12th tak satupun jadi.....NGERRIIIHHHHHH!!!!πππππππππ€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺ
BalasHapusMungkin para insinyur malon terlalu jenius kali yah, jadi berfikirnya terlalu jauhhhhhhhhhh ke depan, sampai2 13th tak satupun jadiπππππππ€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺπ€ͺ
BalasHapusMohamed Khaled berkata, status terkini bagi kapal LCS ketiga pula berada pada tahap 56.48 peratus, manakala LCS keempat 51.10 peratus, dan kapal LCS kelima 42.33 peratus.
BalasHapusBeliau berkata, kementerian menaruh keyakinan bahawa projek pembinaan lima kapal LCS itu dapat diserahkan kepada Tentera Laut Diraja Malaysia (TLDM) mengikut tempoh masa yang telah dirancangkan secara berperingkat mulai Ogos 2026.
======================
2011 PENGADAAN LCS = Pengadaan enam LCS pada 2011 itu juga dilakukan tanpa tender terbuka. Kapal-kapal itu akan dibangun di Galangan Kapal Boustead dan unit pertama sedianya dikirim pada 2019.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
---
2019 LCS DIJANGKA = KD Maharaja Lela setelah ditugaskan, diluncurkan secara seremonial pada Agustus 2017. Seharusnya telah dikirim ke RMN pada April 2019
---
2022 LCS DIJANGKA = menurut jadual asal, setakat Ogos 2022 sepatutnya lima buah kapal LCS harus disiap dan diserahkan kepada TLDM.
---
2023 LCS DIJANGKA = Seharusnya telah dikirim ke RMN pada April 2019, dengan kapal terakhir dijadwalkan untuk serah terima pada Juni 2023. Namun, progres kapal pertama baru sekitar 60% selesai
---
2025 LCS DIJANGKA = Kapal pertama Littoral Combat Ship (LCS) TLDM itu dijangka hanya akan siap pada tahun 2025, iaitu 12 tahun selepas projek itu bermula pada Oktober 2013 dan kerajaan telah membayar RM6 bilion kepada kontraktor utama projek itu.
---
2026 LCS DIJANGKA = Lima kapal LCS akan diserahkan kepada TLDM secara berperingkat dengan kapal pertama dijangka diserahkan pada penghujung 2026
---
2029 LCS DIJANGKA = TLDM hanya akan dapat memperoleh kelima-lima LCS pada 2029 berbanding kontrak asal di mana 5 kapal LCS itu sepatutnya diserahkan pada 2022..
πDRAMA TIAP TAHUNπ
No gambar kapal ke-2 bual teros
BalasHapusSombong nolak ANZAC padahal ngarep d kasih gratisan tuhππππππ€£π€£π€£π€£π€£π€£πππππππππππππππππππ
BalasHapusSebener nya alibi mbah...jadi klo ngajuin trus dtolak ostrali...ga malu doi π€£π€£π€£π€£
HapusPasti d kasih kok ama Aus, masalahnya malon pengennya gratis..tis...tanpa keluar uang sepersenpun, mulai dr pemulihan sampai d kirim k malon om Elπππππ€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£
Hapuskapal KOSONG haha!π€£π€£π
BalasHapuspura2 tak mau Anzac, padahal maunya gratis apgred total diantar free ongkir pulak haha!πππ
BalasHapussementara warganyet kl diminta tunjuk kontrak epektip tak sanggup ehhh hilang haha!π₯Άπ₯Άπ₯Ά
Kebiasaan malon om Pal yg penting sembang bual padahal ngarep pppoooolllll!!!!π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£π€£
HapusBerkenaan hal ini saya pribadi sependapat dg argumen pihak kera_jian ttg potensi komonalitas perangkat yg rendah dg aset yg dimiliki kera_jian saat ini.
HapusUtamanya soalan CMS, radar, sinar dan senjata.....list terlampir π
https://youtu.be/IE3aCbh2SUM?si=GAP1AFhlVtTVjzC9
Terlebih pernah ada kasus dimana helikopter sea hawk milik RAN yg terbaik ketika parkir didalam hangar saat pelayaran menuju zona operasi di kawasan Mediterania....tampaknya case ini mencabar keinginan majelis high supreme mengingat heli Nuri yg sudah diujung masa kelapukannya
ahh sebla teori doank, gegara bejet ciput ngemenk komonalitas om smilikity, masa gak inget dolo mrk borong 4 pespur dobel enjin mana beda2 merek smua haha!π€£π€£π€£
HapusMasalah SEDAPKAN HATI malon slalu didepan ππ€£ππ€£ππ€£
BalasHapusPssstttt.. Semua kapal LCS sudah dibina ya dari awal..... 5 buah terus... ORANG KAYA.. πππ²πΎπ²πΎπ²πΎπ²πΎ
BalasHapusLCS KEDUA - 64.66 peratus
LCS KETIGA - 56.48 peratus
LCS keempat 51.10 peratus
LCS kelima 42.33 peratus.
Psssst kapal mangkrak bahan gelak sekawasan.Dah karatan cape didarat terus.
HapusLCS ke 6 dah terkubur di laut yah Pork?
HapusTa,i..! Sejak 7 thn yg lalu emang dah sgitu..ngajak PT PAL sekarang utk membenahi Salah Potongnya..! Memalukan..tiap kena batunya selalu ke Indonesia dah jadi Omong Besar binaan Tempatan..Ta'i Malon..Bakat Tipu2..!
Hapusgun boat.. π€ͺπ€ͺπ€ͺπ€ͺπ€ͺ
Hapusbuat latihan tembak kcr kita aja..
π€ͺπ€ͺπ€ͺ
Wkwkwkwkwk... than we can't hold anymore for.. LOL
Hapusπ€π€π€π€π€
HapusManakala INDON.... Kapal POHANG RONGSOK guys.. π€£π€£π€£
BalasHapusMALAYSIA... πππ²πΎπ²πΎπ²πΎ
BalasHapus5 BUAH LCS FRIGATE
3 BUAH LMS BATCH 2 KORVET
2024: hibah pohang emang uda disetujui dpr namun anggaran dana $105 jt uda dipindah buat akusisi FREMM haha!π€π€π€
BalasHapus2025: bs jadi gomen nanti kensel pohang, siapa tau ganti destroyer 052..yaa buat manas2 in warganyet kl bolel...duit kita banyakkk haha!πππ
Kapal POHANG versi TAK LAYAK DIPAKAI guys....
BalasHapusMURAH katanya... π€£π€£π€£
105 juta buat bayar FREMM ..? Harga FREMM apa tu ya semurah itu....? π€£π€£π€£
BalasHapusFREMM 105 JUTA..? woiiiii LAWAK apa ni...? π€£π€£π€£
BalasHapusPanda otak ompong gak bisa cerna berita.kasihan.
Hapuseitttt warganyet kl NGAMUkπ₯
BalasHapusPPA semakin dekat
FREMM semakin hampir
ARROWHEAD 140 uda pasti haha!π¦Ύπ¦Ύπ¦Ύ
menang banyak kita, seblah ktinggalan dengan kapal2 kecil2 tak beguna haha!π€£π€£π€£
POHANG yang tak layak dipakai tu pun sudah 35 JUTA.... Masa FREMM baru harga 105 juta...? π€£π€£π€£
BalasHapusHAHAHHAHHA.... Apa ARROWHEAD yang 2030 baru siap...? Itu pun kalau tiada masalah pembayaran seperti KFX.. π€£π€£π€£
BalasHapusKapal kecil tak berguna tu maksud kamu seperti BOT AYAM KFC..? π€£π€£π€£π€£
BalasHapusPssstttt..tahap pembinaan Semua kapal LCS sudah dibina ya dari awal..... 5 buah terus... ORANG KAYA.. πππ²πΎπ²πΎπ²πΎπ²πΎ
BalasHapusLCS KEDUA - 64.66 peratus
LCS KETIGA - 56.48 peratus
LCS keempat 51.10 peratus
LCS kelima 42.33 peratus.
Dan tak satupun selesai,,,ambyaΕr,,dunia pun sdh paham,,π€π₯΄
Hapus$105 juta ituw uang muka, harga $ 600 juta/satuan Wah MAHAL bingit, yaiyalah FREMM frigat Premium haha!π€π€π€
BalasHapuskelas duniya kita....seblah Mangkrak
Maklum beruk otak ompong gak bisa cerna berita guys. Cuma bual ngamok dan lawak saja.
HapusPasti GORILLA sangka LCS baru dibina hanya sebuah.. Lihat peratus pembinaan Semua kapal LCS ya... πππ
BalasHapusLCS KEDUA - 64.66 peratus
LCS KETIGA - 56.48 peratus
LCS keempat 51.10 peratus
LCS kelima 42.33 peratus.
Dari 6 rencana, puluhan tahun satupun belum ada yg diserahkan malah hilang satu persatu ...lawak kali Pork.
HapusPssssst kapal mangkrak yg bikin gelak dunia.
HapusWang muka 2 kapal FREMM 105 JUTA.....? serius la... π€£π€£π€£
BalasHapusDRAMA TIAP TAHUN = Mohamed Khaled berkata, status terkini bagi kapal LCS ketiga pula berada pada tahap 56.48 peratus, manakala LCS keempat 51.10 peratus, dan kapal LCS kelima 42.33 peratus.
HapusBeliau berkata, kementerian menaruh keyakinan bahawa projek pembinaan lima kapal LCS itu dapat diserahkan kepada Tentera Laut Diraja Malaysia (TLDM) mengikut tempoh masa yang telah dirancangkan secara berperingkat mulai Ogos 2026.
======================
2011 PENGADAAN LCS = Pengadaan enam LCS pada 2011 itu juga dilakukan tanpa tender terbuka. Kapal-kapal itu akan dibangun di Galangan Kapal Boustead dan unit pertama sedianya dikirim pada 2019.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
---
2019 LCS DIJANGKA = KD Maharaja Lela setelah ditugaskan, diluncurkan secara seremonial pada Agustus 2017. Seharusnya telah dikirim ke RMN pada April 2019
---
2022 LCS DIJANGKA = menurut jadual asal, setakat Ogos 2022 sepatutnya lima buah kapal LCS harus disiap dan diserahkan kepada TLDM.
---
2023 LCS DIJANGKA = Seharusnya telah dikirim ke RMN pada April 2019, dengan kapal terakhir dijadwalkan untuk serah terima pada Juni 2023. Namun, progres kapal pertama baru sekitar 60% selesai
---
2025 LCS DIJANGKA = Kapal pertama Littoral Combat Ship (LCS) TLDM itu dijangka hanya akan siap pada tahun 2025, iaitu 12 tahun selepas projek itu bermula pada Oktober 2013 dan kerajaan telah membayar RM6 bilion kepada kontraktor utama projek itu.
---
2026 LCS DIJANGKA = Lima kapal LCS akan diserahkan kepada TLDM secara berperingkat dengan kapal pertama dijangka diserahkan pada penghujung 2026
---
2029 LCS DIJANGKA = TLDM hanya akan dapat memperoleh kelima-lima LCS pada 2029 berbanding kontrak asal di mana 5 kapal LCS itu sepatutnya diserahkan pada 2022..
πDRAMA TIAP TAHUNπ
TOLOL ga hilang hilang dari Malaysia.... dasar tolol
BalasHapusNegara diisi bangsa TOLOL ya Malaysia
BalasHapus105 juta klaim GORILLA wang muka kapal FREMM...? .... Jadi kalau 2 kapal SEBUAH FREMM wang muka hanya semurah 53 juta..? Serius la woiiii... π€£π€£π€£
BalasHapusGORILLA KALAU MEMBUAL SESAMA GORILLA BOLEH LA... π€£π€£
Psstttt... GORILLA klaim wang muka sebuah kapal FREMM hanya USD53 Juta je guys.... π€£π€£π€£π€£
BalasHapusLAWAK LA.... π€ͺπ€ͺ
seblah SHOPPING LAMA dikit amat gak berasa...GHOIB gaeszπ»haha!πππ
BalasHapuskita donk aset BARUW MODEREN,
ADA CIWS, ADA SONAR, ADA TORPEDO
✅️Sigma PKR lagi ke Hawaii Rimpac
✅️AH 140 uda potong baja kapal kedua
✅️KCR 60M Palindo Marine-TAIS Turkiye
PPA semakin dekat
FREMM semakin hampir
wahhh SHOPPING SUPER MAHAL, yaa makloum
BEDA LEVEL, BEDA KASTA haha!πππ
No sonar, no torpedo= downgrade. Tapi beruk tak mengakui. Ha ha ha
BalasHapus2027 2 buah KAPAL LCS dan 3 Kapal LMS BATCH 2 diterima TLDM.. ππ
BalasHapuspada tahun itu kita sudah dibekalkan dengan dua kapal LCS. Kapal itu akan diserah kepada TLDM dan mula beroperasi dalam tahun 2027,” katanya.
Selain itu, Mohamed Khaled berkata, kerajaan baru-baru ini juga telah membuat perolehan bagi mendapatkan tiga kapal misi pesisir (LMS) dari Turkiye yang dijangka siap menjelang akhir 2027.
"Jadi lima kapal akan mula berkhidmat dengan TLDM
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
BalasHapus-----
DRAMA TIAP TAHUN = Mohamed Khaled berkata, status terkini bagi kapal LCS ketiga pula berada pada tahap 56.48 peratus, manakala LCS keempat 51.10 peratus, dan kapal LCS kelima 42.33 peratus.
Beliau berkata, kementerian menaruh keyakinan bahawa projek pembinaan lima kapal LCS itu dapat diserahkan kepada Tentera Laut Diraja Malaysia (TLDM) mengikut tempoh masa yang telah dirancangkan secara berperingkat mulai Ogos 2026.
======================
2011 PENGADAAN LCS = Pengadaan enam LCS pada 2011 itu juga dilakukan tanpa tender terbuka. Kapal-kapal itu akan dibangun di Galangan Kapal Boustead dan unit pertama sedianya dikirim pada 2019.---
2019 LCS DIJANGKA = KD Maharaja Lela setelah ditugaskan, diluncurkan secara seremonial pada Agustus 2017. Seharusnya telah dikirim ke RMN pada April 2019
---
2022 LCS DIJANGKA = menurut jadual asal, setakat Ogos 2022 sepatutnya lima buah kapal LCS harus disiap dan diserahkan kepada TLDM.
---
2023 LCS DIJANGKA = Seharusnya telah dikirim ke RMN pada April 2019, dengan kapal terakhir dijadwalkan untuk serah terima pada Juni 2023. Namun, progres kapal pertama baru sekitar 60% selesai
---
2025 LCS DIJANGKA = Kapal pertama Littoral Combat Ship (LCS) TLDM itu dijangka hanya akan siap pada tahun 2025, iaitu 12 tahun selepas projek itu bermula pada Oktober 2013 dan kerajaan telah membayar RM6 bilion kepada kontraktor utama projek itu.
---
2026 LCS DIJANGKA = Lima kapal LCS akan diserahkan kepada TLDM secara berperingkat dengan kapal pertama dijangka diserahkan pada penghujung 2026
---
2029 LCS DIJANGKA = TLDM hanya akan dapat memperoleh kelima-lima LCS pada 2029 berbanding kontrak asal di mana 5 kapal LCS itu sepatutnya diserahkan pada 2022..
πDRAMA TIAP TAHUNπ
2027....πππ
BalasHapus2 BUAH LCS
3 BUAH LMS BATCH 2
Setiap hari cuma bual dan ngamok yah Pork.
HapusWkwkwkwk kapal sampah dibanggakan
HapusLCS ver karatan, LMS ver Downgrade ππππ
BalasHapus2 buah FREMM.... Wang muka hanya semurah USD105 juta je... π€£π€£
BalasHapusIni beerti wang muka sebuah hanya senilai US D53 Juta je.... FREMM apa semurah itu woiiii.... π€£π€£π€£π€£
pengalihan anggaran $105 juta untuk pembelian kapal Fremm dari Italia.
BalasHapusHerindra menjelaskan anggaran itu dipakai untuk membeli dua buah kapal Fremm.
harganya 600 juta dolar satunya. Karena sudah perlengkapan dan sangat modern," kata Herindra di dalam rapat kerja dengan komisi I DPR, Kamis (6/6).
-‐----
wuiihhh 2 FREMM = $ 1, 2 miliar dolar, wow bisa dapat banyak si LeMeS yg MURAH tapi AKAN ituw haha!πππ
semakin FANAS semakin NGAMUkπ₯
FREMM makin hampir Njoosss haha!πππ
NO CONTRACT LMS = THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
BalasHapusThree of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2 RADAR 3D 30mm = STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
-----
DRAMA TIAP TAHUN = Mohamed Khaled berkata, status terkini bagi kapal LCS ketiga pula berada pada tahap 56.48 peratus, manakala LCS keempat 51.10 peratus, dan kapal LCS kelima 42.33 peratus.
Beliau berkata, kementerian menaruh keyakinan bahawa projek pembinaan lima kapal LCS itu dapat diserahkan kepada Tentera Laut Diraja Malaysia (TLDM) mengikut tempoh masa yang telah dirancangkan secara berperingkat mulai Ogos 2026.
======================
2011 PENGADAAN LCS = Pengadaan enam LCS pada 2011 itu juga dilakukan tanpa tender terbuka. Kapal-kapal itu akan dibangun di Galangan Kapal Boustead dan unit pertama sedianya dikirim pada 2019.---
2019 LCS DIJANGKA = KD Maharaja Lela setelah ditugaskan, diluncurkan secara seremonial pada Agustus 2017. Seharusnya telah dikirim ke RMN pada April 2019
---
2022 LCS DIJANGKA = menurut jadual asal, setakat Ogos 2022 sepatutnya lima buah kapal LCS harus disiap dan diserahkan kepada TLDM.
---
2023 LCS DIJANGKA = Seharusnya telah dikirim ke RMN pada April 2019, dengan kapal terakhir dijadwalkan untuk serah terima pada Juni 2023. Namun, progres kapal pertama baru sekitar 60% selesai
---
2025 LCS DIJANGKA = Kapal pertama Littoral Combat Ship (LCS) TLDM itu dijangka hanya akan siap pada tahun 2025, iaitu 12 tahun selepas projek itu bermula pada Oktober 2013 dan kerajaan telah membayar RM6 bilion kepada kontraktor utama projek itu.
---
2026 LCS DIJANGKA = Lima kapal LCS akan diserahkan kepada TLDM secara berperingkat dengan kapal pertama dijangka diserahkan pada penghujung 2026
---
2029 LCS DIJANGKA = TLDM hanya akan dapat memperoleh kelima-lima LCS pada 2029 berbanding kontrak asal di mana 5 kapal LCS itu sepatutnya diserahkan pada 2022..
πDRAMA TIAP TAHUN = NO CONTRACT ACTIVE π
Sedangkan servis kerangka kapal dan enjin kapal POHANG RONGSOK YANG TAK LAYAK DIPAKAI sudah memakan anggaran USD 35 JUTA...... π€£π€£π€£
BalasHapusAda KE patut SI GORILLA klaim wang muka sebuah kapal FREMM HANYA USD53 JUTA...
NO CONTRACT LMS = THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
HapusThree of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2 RADAR 3D 30mm = STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
-----
DRAMA TIAP TAHUN = Mohamed Khaled berkata, status terkini bagi kapal LCS ketiga pula berada pada tahap 56.48 peratus, manakala LCS keempat 51.10 peratus, dan kapal LCS kelima 42.33 peratus.
Beliau berkata, kementerian menaruh keyakinan bahawa projek pembinaan lima kapal LCS itu dapat diserahkan kepada Tentera Laut Diraja Malaysia (TLDM) mengikut tempoh masa yang telah dirancangkan secara berperingkat mulai Ogos 2026.
======================
2011 PENGADAAN LCS = Pengadaan enam LCS pada 2011 itu juga dilakukan tanpa tender terbuka. Kapal-kapal itu akan dibangun di Galangan Kapal Boustead dan unit pertama sedianya dikirim pada 2019.---
2019 LCS DIJANGKA = KD Maharaja Lela setelah ditugaskan, diluncurkan secara seremonial pada Agustus 2017. Seharusnya telah dikirim ke RMN pada April 2019
---
2022 LCS DIJANGKA = menurut jadual asal, setakat Ogos 2022 sepatutnya lima buah kapal LCS harus disiap dan diserahkan kepada TLDM.
---
2023 LCS DIJANGKA = Seharusnya telah dikirim ke RMN pada April 2019, dengan kapal terakhir dijadwalkan untuk serah terima pada Juni 2023. Namun, progres kapal pertama baru sekitar 60% selesai
---
2025 LCS DIJANGKA = Kapal pertama Littoral Combat Ship (LCS) TLDM itu dijangka hanya akan siap pada tahun 2025, iaitu 12 tahun selepas projek itu bermula pada Oktober 2013 dan kerajaan telah membayar RM6 bilion kepada kontraktor utama projek itu.
---
2026 LCS DIJANGKA = Lima kapal LCS akan diserahkan kepada TLDM secara berperingkat dengan kapal pertama dijangka diserahkan pada penghujung 2026
---
2029 LCS DIJANGKA = TLDM hanya akan dapat memperoleh kelima-lima LCS pada 2029 berbanding kontrak asal di mana 5 kapal LCS itu sepatutnya diserahkan pada 2022..
πDRAMA TIAP TAHUN = NO CONTRACT ACTIVE π
NO CONTRACT LMS = THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
BalasHapusThree of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2 RADAR 3D 30mm = STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
-----
DRAMA TIAP TAHUN = Mohamed Khaled berkata, status terkini bagi kapal LCS ketiga pula berada pada tahap 56.48 peratus, manakala LCS keempat 51.10 peratus, dan kapal LCS kelima 42.33 peratus.
Beliau berkata, kementerian menaruh keyakinan bahawa projek pembinaan lima kapal LCS itu dapat diserahkan kepada Tentera Laut Diraja Malaysia (TLDM) mengikut tempoh masa yang telah dirancangkan secara berperingkat mulai Ogos 2026.
======================
2011 PENGADAAN LCS = Pengadaan enam LCS pada 2011 itu juga dilakukan tanpa tender terbuka. Kapal-kapal itu akan dibangun di Galangan Kapal Boustead dan unit pertama sedianya dikirim pada 2019.---
2019 LCS DIJANGKA = KD Maharaja Lela setelah ditugaskan, diluncurkan secara seremonial pada Agustus 2017. Seharusnya telah dikirim ke RMN pada April 2019
---
2022 LCS DIJANGKA = menurut jadual asal, setakat Ogos 2022 sepatutnya lima buah kapal LCS harus disiap dan diserahkan kepada TLDM.
---
2023 LCS DIJANGKA = Seharusnya telah dikirim ke RMN pada April 2019, dengan kapal terakhir dijadwalkan untuk serah terima pada Juni 2023. Namun, progres kapal pertama baru sekitar 60% selesai
---
2025 LCS DIJANGKA = Kapal pertama Littoral Combat Ship (LCS) TLDM itu dijangka hanya akan siap pada tahun 2025, iaitu 12 tahun selepas projek itu bermula pada Oktober 2013 dan kerajaan telah membayar RM6 bilion kepada kontraktor utama projek itu.
---
2026 LCS DIJANGKA = Lima kapal LCS akan diserahkan kepada TLDM secara berperingkat dengan kapal pertama dijangka diserahkan pada penghujung 2026
---
2029 LCS DIJANGKA = TLDM hanya akan dapat memperoleh kelima-lima LCS pada 2029 berbanding kontrak asal di mana 5 kapal LCS itu sepatutnya diserahkan pada 2022..
πGHOIB DOWNGRADE = NO CONTRACT ACTIVEπ
aset BARUW MODEREN,
BalasHapusADA CIWS, ADA SONAR, ADA TORPEDO
✅️Sigma PKR lagi ke Hawaii Rimpac
✅️AH 140 uda potong baja kapal kedua
✅️KCR 60M Palindo Marine-TAIS Turkiye
✅️PPA semakin dekat
✅️FREMM semakin hampir
lah seblah tuch paling kasihan,uda lama...langsung jadi kapal Rongsokan tiada guna haha!πππ
Versi termurah ada class, tdk ada sonar, tak ada torpedo ππππ utk lawan kapal nelayan vietnam ok lah
BalasHapusNO CONTRACT LMS = THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
BalasHapusThree of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2 RADAR 3D 30mm = STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
-----
DRAMA TIAP TAHUN = Mohamed Khaled berkata, status terkini bagi kapal LCS ketiga pula berada pada tahap 56.48 peratus, manakala LCS keempat 51.10 peratus, dan kapal LCS kelima 42.33 peratus.
Beliau berkata, kementerian menaruh keyakinan bahawa projek pembinaan lima kapal LCS itu dapat diserahkan kepada Tentera Laut Diraja Malaysia (TLDM) mengikut tempoh masa yang telah dirancangkan secara berperingkat mulai Ogos 2026.
======================
2011 PENGADAAN LCS = Pengadaan enam LCS pada 2011 itu juga dilakukan tanpa tender terbuka. Kapal-kapal itu akan dibangun di Galangan Kapal Boustead dan unit pertama sedianya dikirim pada 2019.---
2019 LCS DIJANGKA = KD Maharaja Lela setelah ditugaskan, diluncurkan secara seremonial pada Agustus 2017. Seharusnya telah dikirim ke RMN pada April 2019
---
2022 LCS DIJANGKA = menurut jadual asal, setakat Ogos 2022 sepatutnya lima buah kapal LCS harus disiap dan diserahkan kepada TLDM.
---
2023 LCS DIJANGKA = Seharusnya telah dikirim ke RMN pada April 2019, dengan kapal terakhir dijadwalkan untuk serah terima pada Juni 2023. Namun, progres kapal pertama baru sekitar 60% selesai
---
2025 LCS DIJANGKA = Kapal pertama Littoral Combat Ship (LCS) TLDM itu dijangka hanya akan siap pada tahun 2025, iaitu 12 tahun selepas projek itu bermula pada Oktober 2013 dan kerajaan telah membayar RM6 bilion kepada kontraktor utama projek itu.
---
2026 LCS DIJANGKA = Lima kapal LCS akan diserahkan kepada TLDM secara berperingkat dengan kapal pertama dijangka diserahkan pada penghujung 2026
---
2029 LCS DIJANGKA = TLDM hanya akan dapat memperoleh kelima-lima LCS pada 2029 berbanding kontrak asal di mana 5 kapal LCS itu sepatutnya diserahkan pada 2022..
πGHOIB DOWNGRADE = DRAMA LCS TIAP TAHUNπ
LCS versi karatan ππππ
BalasHapusNO CONTRACT LMS = THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
BalasHapusThree of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2 RADAR 3D 30mm = STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
-----
DRAMA TIAP TAHUN = Mohamed Khaled berkata, status terkini bagi kapal LCS ketiga pula berada pada tahap 56.48 peratus, manakala LCS keempat 51.10 peratus, dan kapal LCS kelima 42.33 peratus.
Beliau berkata, kementerian menaruh keyakinan bahawa projek pembinaan lima kapal LCS itu dapat diserahkan kepada Tentera Laut Diraja Malaysia (TLDM) mengikut tempoh masa yang telah dirancangkan secara berperingkat mulai Ogos 2026.
======================
2011 PENGADAAN LCS = Pengadaan enam LCS pada 2011 itu juga dilakukan tanpa tender terbuka. Kapal-kapal itu akan dibangun di Galangan Kapal Boustead dan unit pertama sedianya dikirim pada 2019.---
2019 LCS DIJANGKA = KD Maharaja Lela setelah ditugaskan, diluncurkan secara seremonial pada Agustus 2017. Seharusnya telah dikirim ke RMN pada April 2019
---
2022 LCS DIJANGKA = menurut jadual asal, setakat Ogos 2022 sepatutnya lima buah kapal LCS harus disiap dan diserahkan kepada TLDM.
---
2023 LCS DIJANGKA = Seharusnya telah dikirim ke RMN pada April 2019, dengan kapal terakhir dijadwalkan untuk serah terima pada Juni 2023. Namun, progres kapal pertama baru sekitar 60% selesai
---
2025 LCS DIJANGKA = Kapal pertama Littoral Combat Ship (LCS) TLDM itu dijangka hanya akan siap pada tahun 2025, iaitu 12 tahun selepas projek itu bermula pada Oktober 2013 dan kerajaan telah membayar RM6 bilion kepada kontraktor utama projek itu.
---
2026 LCS DIJANGKA = Lima kapal LCS akan diserahkan kepada TLDM secara berperingkat dengan kapal pertama dijangka diserahkan pada penghujung 2026
---
2029 LCS DIJANGKA = TLDM hanya akan dapat memperoleh kelima-lima LCS pada 2029 berbanding kontrak asal di mana 5 kapal LCS itu sepatutnya diserahkan pada 2022..
πGHOIB LMS DOWNGRADE = DRAMA LCS TIAP TAHUNπ
Tak perlu banyak BUAL.. cukup Saya tunjuk ini... π€£π€£π€£
BalasHapusLMS BATCH 2.. πππ²πΎπ²πΎ
RADAR CENK AESA - 400KM
MERIAM KAPAL- 76MM
MERIAM SOKONGAN KAPAL - 30MM
Misil ATMACA - 220KM
Misil SAM K SAAM - 20KM
-----------------------------
KRI DIPONEGORO... Jarak radar hingga persenjataan masih dibawah LMS BATCH 2 .. π€£π€£
RADAR MW08 - 150KM
MERIAM UTAMA KAPAL - 76MM
MERIAM SOKONGAN KAPAL - 20MM
EXOCET MK3 - 200KM
MISTRAL SAM - 6KM
Lah... Kapal Putih merah yang makan masa 10 tahun baru siap sebuah...? π€£π€£π€£
BalasHapusada warganyet Halu, siapa tulis $53 juta haha!πππ
BalasHapusSALAM $ 105 juta milik 3 pohang dipindah buat tambah SHOPPING FREMM MAHAL uhuuyyyy haha!π€π€π€
eittt FDI/ Belhara minat juga tampaknya, sikaatttt...Bajet Besar Horang Kaya...Naik Terus Tiap Tahun haha!π°π°π°
warganyet jiran kl flonga flongo haha!π€π€π€
real contract and delivery five units C130J Hercules
BalasHapusreal contract and delivery two unit Frankethal class Countermine vessels (Pulau Fani class)
real contract and delivery four units KCR 60 Fast missiles boats PT PAL
real contract and delivery 9 units Bell 412 EPI
real contract and delivery 8 additional H225 M
real contract and delivery 2 units Bell 429 Global Ranger
real contract and delivery 18 Medium weight tank Harimau
real contract and delivery 22 Pandur II IFV
real contract and delivery two unit Hospital Ships
real contract and delivery one unit Command and control variant C295
real contract and delivery one unit CN235 MPA
real contract and delivery 7 Badak FSV, 26 Anoa apc and 10 additional Komodo recce vehicles in 2022
real contract and delivery 4 AS 550 Fennec and 8 AS565 MBE, in 2024
real contract and delivery five NC212i in 2023
real contract and delivery one Leonardo RAT 31 DL/M
real contract and delivery five C130H ordered from Australia in 2013 (finished in 2020) after received Grant of 4 C130H
real contract and delivery 9 Teluk Bintuni class LST
real contract and delivery six CH4B UCAV ordered in 2019
real contract t and process building of Abeking & Rasmussen design ocean Hydrography ship
real contract and process building two AH140 AAW Frigate
real contract and process building two OPV 90 ASW patrol vessels
real contract and process building 42 Dassault Rafale F4 fighter
real contract and process building two A400M heavy cargo aircraft
real contract and delivery M3 Amphibious bridging system
real contract and delivery 3 KT1 Wong Bee ordered in 2018 along with radar and spares for T/A50
real contract and process building 13 GM 403 GCI radar from Thales
real contract and process building 12 ANKA S UCAV
real contract and process building additional CH4B UCAV
real contract and delivery Slingshot Satcom system
real contract and delivery Falcon 8X aircraft
real contract and process Thales Alenia earth observation satelite
real contract and process 22 S70M Blackhawk
real contract and process 6 N219 aircraft
real contract and process 3 CN235 for Army
real contract and process 2 PPA patrol Frigate
real contract and process 2 Scorpene Subs
real contract and process Khan Short Range ballistic missiles from Turki
real contract and process Trisula Air defense system
real contract and process 6 T50i aircraft
real contract and delivery Oiler and replenishment ship
real contract and delivery several Tug Harbor ships
real contract and process Submarine rescue vessels and system
real contract and delivery two Large LCU for army
real contract and process 45 Atmaca
===============
barter sawit 10 LCA 8 FLIT
akan 2 Leonardo P-72M
akan 3 anka ISR ompong
LOA LMS B2 Ada-Class DOWNGRADE
Dibayar PBB/UN = 4x4 Ejder Yalçin
LCS dibayar 6 jadi NOL
OPV dibayar 3 jadi 1
πBEDA KASTA BEDA LEVEL = SHOPPING ELIT versus SHOPPING SULITπ
LMS Malon masih dibawah sigma KRI i Gusti Ngurah Rai. No sonar, no torpedo
BalasHapusternyata ADA sebelah
BalasHapusGAK ADA⛔️torpedo
GAK ADA⛔️ CIWS
GAK ADA⛔️sonar
fiks ADA versi Dongred Murah aja haha!π€£π€£π€£
makanan empuk kalsel sama akinci om @palu gada
BalasHapusHa ha ha ha ha. Versi utk negara miskin
BalasHapushttps://www.zonajakarta.com/nasional/67312979033/dikira-setara-diponegoro-class-korvet-ada-class-pesanan-malaysia-alami-downgrade
ADA warganyet tak brani sebut kata
BalasHapus⛔️sonar⛔️torpedo⛔️CIWS fik Kalah Total haha!πππ
anka sebelah cuma ISR y ompong om............
HapusHAHAHAHHA.. 2 buah FREMM wang muka semurah USD53 Juta je sebuah...? Agak agak la kalau mau MEMBUAL.. π€ͺπ€ͺ
BalasHapusreal contract and delivery five units C130J Hercules
Hapusreal contract and delivery two unit Frankethal class Countermine vessels (Pulau Fani class)
real contract and delivery four units KCR 60 Fast missiles boats PT PAL
real contract and delivery 9 units Bell 412 EPI
real contract and delivery 8 additional H225 M
real contract and delivery 2 units Bell 429 Global Ranger
real contract and delivery 18 Medium weight tank Harimau
real contract and delivery 22 Pandur II IFV
real contract and delivery two unit Hospital Ships
real contract and delivery one unit Command and control variant C295
real contract and delivery one unit CN235 MPA
real contract and delivery 7 Badak FSV, 26 Anoa apc and 10 additional Komodo recce vehicles in 2022
real contract and delivery 4 AS 550 Fennec and 8 AS565 MBE, in 2024
real contract and delivery five NC212i in 2023
real contract and delivery one Leonardo RAT 31 DL/M
real contract and delivery five C130H ordered from Australia in 2013 (finished in 2020) after received Grant of 4 C130H
real contract and delivery 9 Teluk Bintuni class LST
real contract and delivery six CH4B UCAV ordered in 2019
real contract t and process building of Abeking & Rasmussen design ocean Hydrography ship
real contract and process building two AH140 AAW Frigate
real contract and process building two OPV 90 ASW patrol vessels
real contract and process building 42 Dassault Rafale F4 fighter
real contract and process building two A400M heavy cargo aircraft
real contract and delivery M3 Amphibious bridging system
real contract and delivery 3 KT1 Wong Bee ordered in 2018 along with radar and spares for T/A50
real contract and process building 13 GM 403 GCI radar from Thales
real contract and process building 12 ANKA S UCAV
real contract and process building additional CH4B UCAV
real contract and delivery Slingshot Satcom system
real contract and delivery Falcon 8X aircraft
real contract and process Thales Alenia earth observation satelite
real contract and process 22 S70M Blackhawk
real contract and process 6 N219 aircraft
real contract and process 3 CN235 for Army
real contract and process 2 PPA patrol Frigate
real contract and process 2 Scorpene Subs
real contract and process Khan Short Range ballistic missiles from Turki
real contract and process Trisula Air defense system
real contract and process 6 T50i aircraft
real contract and delivery Oiler and replenishment ship
real contract and delivery several Tug Harbor ships
real contract and process Submarine rescue vessels and system
real contract and delivery two Large LCU for army
real contract and process 45 Atmaca
===============
barter sawit 10 LCA 8 FLIT
akan 2 Leonardo P-72M
akan 3 anka ISR ompong
LOA LMS B2 Ada-Class DOWNGRADE
Dibayar PBB/UN = 4x4 Ejder Yalçin
LCS dibayar 6 jadi NOL
OPV dibayar 3 jadi 1
πBEDA KASTA BEDA LEVEL = SHOPPING ELIT versus SHOPPING SULITπ
Untuk menyesuaikan anggaran yang ada, Turki memodifikasi Ada class sesuai dengan apa yang dibayar oleh Malaysia.
BalasHapus"Ketiga korvet, yang desainnya telah disesuaikan oleh STM untuk memenuhi persyaratan Angkatan Laut Kerajaan Malaysia, akan dibangun di Turki dalam lingkup Proyek Kapal Misi Pesisir Batch-2 (LMS-B2)," jelas STM pada 10 Juni 2024.
Salah satu downgrade yang dialami Ada class Malaysia ialah tak adanya kemampuan peperangan bawah laut.
https://www.zonajakarta.com/nasional/67312979033/dikira-setara-diponegoro-class-korvet-ada-class-pesanan-malaysia-alami-downgrade
Beruk tak terima kenyataan. Ha ha ha ha ha
Hapusnyoiiihhh apalagi ama UUV proyek rahasia kite...siap2 klelep haha!π₯Άπ₯Άπ₯Ά
BalasHapuspengalihan anggaran $105 juta untuk pembelian kapal Fremm dari Italia.
BalasHapusHerindra menjelaskan anggaran itu dipakai untuk membeli dua buah kapal Fremm.
harganya 600 juta dolar satunya. Karena sudah perlengkapan dan sangat modern," kata Herindra di dalam rapat kerja dengan komisi I DPR, Kamis (6/6).
-‐----
wuiihhh 2 FREMM = $ 1, 2 miliar dolar, wow bisa dapat banyak si LeMeS yg MURAH tapi AKAN ituw haha!πππ
warganyet kl semakin FANAS semakin NGAMUkπ₯pertanda TAKUT
FREMM makin hampir Njoosss haha!ππ
kita mainnya frigat sebelah mainnya corvette downgrade ...........
Hapusnyoiihh bentar lagi destro...waks tambah MeWeK lagi para waragnyet kl om pemburu haha!πππ
HapusHa ha ha ha ha susah memang terima kenyataan kalau Malon sedang miskin dan memaksakan diri beli kapal perang.
BalasHapusUntuk menyesuaikan anggaran yang ada, Turki memodifikasi Ada class sesuai dengan apa yang dibayar oleh Malaysia.
"Ketiga korvet, yang desainnya telah disesuaikan oleh STM untuk memenuhi persyaratan Angkatan Laut Kerajaan Malaysia, akan dibangun di Turki dalam lingkup Proyek Kapal Misi Pesisir Batch-2 (LMS-B2)," jelas STM pada 10 Juni 2024.
Salah satu downgrade yang dialami Ada class Malaysia ialah tak adanya kemampuan peperangan bawah laut.
https://www.zonajakarta.com/nasional/67312979033/dikira-setara-diponegoro-class-korvet-ada-class-pesanan-malaysia-alami-downgrade
Hull sonar tak dee..Sasaran mudah torpedo kapal selam...
Hapusπ€£π€£π€£π€£
NO CONTRACT LMS
BalasHapusTHEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
πππππππππππ
MEMBUAL ADA CLASS MALON bla ... bla ... bla ..., ternyata kontrak belum ada
BalasHapusπ€£π€£π€£π€£π€£π€£π€£π€£
MEMBUAL LCS ON TRACK, ..... TERNYATA TELAT BERTAHUN2
BalasHapusπ€£π€£π€£π€£π€£π€£π€£π€£
MEMBUAL RADAR CENK 400 km ,....
BalasHapusTernyata mau pakai CENK S yang merupakan versi donwngrade dari CENK 400N yang dipakai Turki
π€£π€£π€£π€£π€£π€£π€£π€£
Tak ADA class a.k.a LeMeS-2 malon tak punya macam nii...
BalasHapusπ€£π€£π€£π€£
"....upgrade pada KRI Frans Kaisiepo 368 telah tuntas dilakukan oleh Thales.
Tidak hanya diperbaiki, perangkat sonar yang diketahui mengusung jenis perangat sonar pencari Thales UMS 4132 Kingklip medium frequency active/passive ASW (Anti Submarine Warfare) juga ditingkatkan kemampuannya. Diantara yang mendapatkan upgrade adalah modernisasi konsol operator, sistem pemrosesan sinyal dan teknologi perangkat keras. Korvet dengan bobot 1.700 ton tersebut kini memiliki kemampuan komunikasi antara pengawak dan mesin melalui human machine interface (HMI), sistem yang sebelumnya sudah terpasang pada PKR (Perusak Kawal Rudal) RE Martadinata Class.
Sonar dengan desain hull mounted terletak di bawah lambung kapal dan dilindungi oleh dome (kubah). Secara umum, hull mounted sonar dirancang untuk mendeteksi keberadaan kapal selam lawan, dan menteksi ancaman yang berasal dari torpedo dan ranjau laut. .."
Cukup tebarkan ranjau laut, maka ADA class a.k.a LeMeS-2 malon, menjadi tak ADA lagi ...
BalasHapusπ€£π€£π€£π€£π€£π€£
LOA = NO CONTRACT LMS
BalasHapusTHEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
πππππππππππ
LOA = NO CONTRACT LMS
BalasHapusTHEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
πKAPAL GHOIB DOWNGRADE = MEMBUALπ
LOA = NO CONTRACT LMS
BalasHapusTHEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
πKAPAL GHOIB DOWNGRADE = MEMBUALπ
Tukang Dongan25 Juni 2024 pukul 13.21
BalasHapusMEMBUAL RADAR CENK 400 km ,....
Ternyata mau pakai CENK S yang merupakan versi donwngrade dari CENK 400N yang dipakai Turki
π€£π€£π€£π€£π€£π€£π€£π€£
LOA = NO CONTRACT LMS
BalasHapusTHEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πKAPAL GHOIB = DOWNGRADE NGAKAKKKKπ
BalasHapusSemua kapal dibina serentak mengikut tahap PEMBINAAN... πππ²πΎπ²πΎ
status kemajuan LCS yang lain iaitu LCS1 sebanyak 75%, LCS2 sebanyak 64.66%, LCS 3 sebanyak 56.58%, LCS 4 sebanyak 51.10% dan LCS 5 adalah sebanyak 42.33%.
Menjelang 2027, selain daripada memiliki 2 buah LCS yang telah siap dibina, kita juga akan memiliki 3 buah Littoral Mission Ship ( LMS) Batch 2 yang sedang dibina di Republik Turkiye, bagi mengukuhkan lagi kesiagaan TLDM kita.
KAPAL GHOIB DOWNGRADE =
Hapus------------------------------------------
LOA = NO CONTRACT LMS
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πππππππππππππππ
KAPAL GHOIB DOWNGRADE =
BalasHapus------------------------------------------
LOA = NO CONTRACT LMS
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πKAPAL GHOIB = DOWNGRADE NGAKAKKKKπ
TIDAK PERLU BANYAK BUAl CUKUP BILANG =
BalasHapusKAPAL GHOIB DOWNGRADE NO CONTRACT
------------------------------------------
LOA = NO CONTRACT LMS
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πππππππππππππππ
Sudah di air miring gak Pork LCS nya,,nanti ditarik ke darat mangkrak lagi.bikin malu
BalasHapusPsstttt... LMS CENK AESA RADAR ye.... ππ
BalasHapusAnother notable difference in the mockup is the air surveillance radar. While MILGEM corvettes serving in the Turkish Navy are equipped with the Smart-S Mk 2 air surveillance radar, the radar featured on the LMS model is the Aselsan CENK-S AESA, which was installed on the TCG Istanbul, the first I-class frigate of the Turkish Navy.
TIDAK PERLU BANYAK BUAl CUKUP BILANG =
HapusKAPAL GHOIB DOWNGRADE NO CONTRACT
------------------------------------------
LOA = NO CONTRACT LMS
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πππππππππππππππ
Gempork gak bual dan ngamok pasti gak ramai komen di DS, Cuma komen dan bualan gempork bahan lawak sekawasan.
BalasHapusPsssst biarkan gempirk terus ngamok dan membual di DS bahan buat lawan sekawasan. yg jelas diayamkan sekawasan. Sepi berita dan kalus shopping.
BalasHapusBUKTI BELUM KONTRAK
BalasHapusSTM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
BUKTI LOA = NO CONTRACT LMS
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πππππππππππππππ
BUKTI BELUM KONTRAK
BalasHapusSTM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
BUKTI LOA = NO CONTRACT LMS
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πππππππππππππππ
Lawaknya ada GORILLA disangkanya kapal LCS baru dibina hanya sebuah dan 4 buah lagi belum dibina langsung.. Baca guys... π€£π€£
BalasHapusStatus kemajuan LCS yang lain iaitu LCS1 sebanyak 75%, LCS2 sebanyak 64.66%, LCS 3 sebanyak 56.58%, LCS 4 sebanyak 51.10% dan LCS 5 adalah sebanyak 42.33%.
Menjelang 2027, selain daripada memiliki 2 buah LCS yang telah siap dibina, kita juga akan memiliki 3 buah Littoral Mission Ship ( LMS) Batch 2 yang sedang dibina di Republik Turkiye, bagi mengukuhkan lagi kesiagaan TLDM kita.
BUKTI BELUM KONTRAK LMS
HapusSTM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = GHOIB
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πLMS LCS OPV NGPVs = DRAMAπ
BUKTI BELUM KONTRAK LMS
BalasHapusSTM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = NO CONTRACT LMS
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πππππππππππππππ
BUKTI BELUM KONTRAK LMS
BalasHapusSTM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = NO CONTRACT LMS
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πππππππππππππππ
Ini beerti kapal LMS BATCH 2 sudah mampu deteksi kapal musuh sejauh 400km dengan radar CENK AESA dan musnah kan sasaran menggunakan ATMACA sejauh 220KM... πππ²πΎπ²πΎπ²πΎ
BalasHapusBUKTI BELUM KONTRAK LMS
HapusSTM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = NO CONTRACT LMS
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πππππππππππππππ
Tinggal sebar ranjau laut, selesai..
BalasHapusKarena tak punya Hull sonar
π€£π€£π€£π€£π€£
Maklum downgrade
BUKTI BELUM KONTRAK LMS
BalasHapusSTM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = GHOIB
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πππππππππππππππ
BUKTI BELUM KONTRAK LMS
BalasHapusSTM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = GHOIB
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
2017 SULTAN DITIPU FAKE PSIM = Jika pada peluncurannya tahun 2017 lalu kapal ini terlihat telah dilengkapi dengan modul PSIM, maka itu adalah modul PSIM palsu/fake yang dipasang untuk upacara peluncuran sebagaimana disampaikan dalam sidang PAC (Public Account Committe). Modul PSIM palsu ini kemudian dilepas saat kapal ini dipasangi hanggar.
πππππππππππππππ
Radar & rudal bisa lawan kapal selam kee...?
BalasHapusπ€£π€£π€£π€£π€£π€£
Perbandingan sistem pertahanan udara... π€£π€£π€£
BalasHapusLMS BATCH 2.. πππ²πΎπ²πΎ
Misil SAM K SAAM - 20KM
-----------------------------
KRI DIPONEGORO...
MISTRAL SAM - 6KM
BUKTI BELUM KONTRAK LMS
HapusSTM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = GHOIB
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
NGPV DIBAYAR 27 JADI NOL = Najib berkata, Limbungan TLDM dikorporatkan kerajaan pada 1991 sebelum dijual kepada syarikat swasta Penang Shipbuilding & Construction Corporation(PSC) untuk menjadi syarikat PSC-Naval Dockyard pada 1995. Pada tahun 1998, kerajaan memberi kontrak pembinaan untuk 27 kapal NGPV dengan anggaran bajet RM30 bilion kepada syarikat swasta itu. Fasa pertama membabitkan pembinaan enam kapal pertama dengan kos RM6 bilion. "Namun kontrak ini gagal dan tiada satu kapal pun diserahkan oleh PSC-Naval Dockyard
---
LCS BAYAR HUTANG LAPUK NGPV = seperti didedahkan Jawatankuasa Kira-kira Wang Negara (PAC) dan CEO LTAT, syarikat BNS menggunakan RM400 juta daripada bayaran pendahuluan bagi projek LCS untuk menjelaskan hutang lapuk bagi projek NGPV,"
syarikat PSC-Naval Dockyard pada Disember 2005 sebelum dijenamakan semula menjadi syarikat Boustead Naval Dockyard Sdn Bhd
πLMS LCS OPV NGPVs = DRAMAπ
BUKTI BELUM KONTRAK LMS
BalasHapusSTM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = GHOIB
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
NGPV DIBAYAR 27 JADI NOL = Najib berkata, Limbungan TLDM dikorporatkan kerajaan pada 1991 sebelum dijual kepada syarikat swasta Penang Shipbuilding & Construction Corporation(PSC) untuk menjadi syarikat PSC-Naval Dockyard pada 1995. Pada tahun 1998, kerajaan memberi kontrak pembinaan untuk 27 kapal NGPV dengan anggaran bajet RM30 bilion kepada syarikat swasta itu. Fasa pertama membabitkan pembinaan enam kapal pertama dengan kos RM6 bilion. "Namun kontrak ini gagal dan tiada satu kapal pun diserahkan oleh PSC-Naval Dockyard
---
LCS BAYAR HUTANG LAPUK NGPV = seperti didedahkan Jawatankuasa Kira-kira Wang Negara (PAC) dan CEO LTAT, syarikat BNS menggunakan RM400 juta daripada bayaran pendahuluan bagi projek LCS untuk menjelaskan hutang lapuk bagi projek NGPV,"
syarikat PSC-Naval Dockyard pada Disember 2005 sebelum dijenamakan semula menjadi syarikat Boustead Naval Dockyard Sdn Bhd
πLMS LCS OPV NGPVs = DRAMAπ
BUKTI BELUM KONTRAK LMS
BalasHapusSTM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = GHOIB
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
NGPV DIBAYAR 27 JADI NOL = Najib berkata, Limbungan TLDM dikorporatkan kerajaan pada 1991 sebelum dijual kepada syarikat swasta Penang Shipbuilding & Construction Corporation(PSC) untuk menjadi syarikat PSC-Naval Dockyard pada 1995. Pada tahun 1998, kerajaan memberi kontrak pembinaan untuk 27 kapal NGPV dengan anggaran bajet RM30 bilion kepada syarikat swasta itu. Fasa pertama membabitkan pembinaan enam kapal pertama dengan kos RM6 bilion. "Namun kontrak ini gagal dan tiada satu kapal pun diserahkan oleh PSC-Naval Dockyard
---
LCS BAYAR HUTANG LAPUK NGPV = seperti didedahkan Jawatankuasa Kira-kira Wang Negara (PAC) dan CEO LTAT, syarikat BNS menggunakan RM400 juta daripada bayaran pendahuluan bagi projek LCS untuk menjelaskan hutang lapuk bagi projek NGPV,"
syarikat PSC-Naval Dockyard pada Disember 2005 sebelum dijenamakan semula menjadi syarikat Boustead Naval Dockyard Sdn Bhd
πLMS LCS OPV NGPVs = DRAMA KOMEDIπ
Maknanya kapal lawan yang radarnya hanya sejauh 150KM tidak tahu.. Kapal nya sudah di deteksi dengan radar sejauh 400KM...
BalasHapusdan dalam jarak 220KM BOOOMMMMM di hancur kan dengan misil ATMACA... πππ
Bot kecil AYAM KFC....lagi KESIAN... π€£π€£π€£
BalasHapusTIADA TORPEDO
TIADA RADAR
TIADA MISIL SAM
HANYA 4 MISIL ANTI KAPAL
HANYA KETAHANAN BELAYAR 5 HARI DI LAUT
GHOIB GHOIB GHOIB
HapusBUKTI BELUM KONTRAK LMS
STM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
GHOIB GHOIB GHOIB
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = GHOIB
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
NGPV DIBAYAR 27 JADI NOL = Najib berkata, Limbungan TLDM dikorporatkan kerajaan pada 1991 sebelum dijual kepada syarikat swasta Penang Shipbuilding & Construction Corporation(PSC) untuk menjadi syarikat PSC-Naval Dockyard pada 1995. Pada tahun 1998, kerajaan memberi kontrak pembinaan untuk 27 kapal NGPV dengan anggaran bajet RM30 bilion kepada syarikat swasta itu. Fasa pertama membabitkan pembinaan enam kapal pertama dengan kos RM6 bilion. "Namun kontrak ini gagal dan tiada satu kapal pun diserahkan oleh PSC-Naval Dockyard
---
LCS BAYAR HUTANG LAPUK NGPV = seperti didedahkan Jawatankuasa Kira-kira Wang Negara (PAC) dan CEO LTAT, syarikat BNS menggunakan RM400 juta daripada bayaran pendahuluan bagi projek LCS untuk menjelaskan hutang lapuk bagi projek NGPV,"
syarikat PSC-Naval Dockyard pada Disember 2005 sebelum dijenamakan semula menjadi syarikat Boustead Naval Dockyard Sdn Bhd
πLMS LCS OPV NGPVs = DRAMA KOMEDIπ
Kasihan.... Levelnya masih jauh dibawah KRI Diponegoro. Ya maklum.lah..... beruk lagi miskin.
BalasHapushttps://www.zonajakarta.com/nasional/67312979033/dikira-setara-diponegoro-class-korvet-ada-class-pesanan-malaysia-alami-downgrade
Komentar ini telah dihapus oleh pengarang.
BalasHapusADA warganyet tak brani sebut kata
BalasHapus⛔️sonar⛔️torpedo⛔️CIWS fiks Kalah Total haha!πππ
Kapal penakut oom..
HapusTak berani ke laut lepas..
Takut torpedo KS .
π€£π€£π€£π€£π€£
Sesuai dengan doktrin, hanya pantau CCG dari kejauhan
π€£π€£π€£π€£π€£π€£
nyoiihh sambil mancing om pedang haha!π€π€π€
HapusKapal ini tidak punya SAM hanya besar saja 115 m
BalasHapusMana kapalnya puur..msh bentuk brosur yaa....
BalasHapusNo kontrak..BANYAK BUAL
GHOIB GHOIB GHOIB
BalasHapusBUKTI BELUM KONTRAK LMS
STM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
GHOIB GHOIB GHOIB
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = GHOIB
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
OMPONG = ANKA WILL NOT BE EQUIPPED WITH ANY WEAPONRY
Malaysia to use Anka-S for Maritime Surveillance
While the specific equipment configuration of the Ankas is not currently known, they will be operated solely as a maritime surveillance platform in Malaysian service, and will not be equipped with any weaponry. According to European Security & Defence reporting from LIMA 2023, the Malaysian Ankas will have modified wings to improve their endurance.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
NGPV DIBAYAR 27 JADI NOL = Najib berkata, Limbungan TLDM dikorporatkan kerajaan pada 1991 sebelum dijual kepada syarikat swasta Penang Shipbuilding & Construction Corporation(PSC) untuk menjadi syarikat PSC-Naval Dockyard pada 1995. Pada tahun 1998, kerajaan memberi kontrak pembinaan untuk 27 kapal NGPV dengan anggaran bajet RM30 bilion kepada syarikat swasta itu. Fasa pertama membabitkan pembinaan enam kapal pertama dengan kos RM6 bilion. "Namun kontrak ini gagal dan tiada satu kapal pun diserahkan oleh PSC-Naval Dockyard
---
LCS BAYAR HUTANG LAPUK NGPV = seperti didedahkan Jawatankuasa Kira-kira Wang Negara (PAC) dan CEO LTAT, syarikat BNS menggunakan RM400 juta daripada bayaran pendahuluan bagi projek LCS untuk menjelaskan hutang lapuk bagi projek NGPV,"
syarikat PSC-Naval Dockyard pada Disember 2005 sebelum dijenamakan semula menjadi syarikat Boustead Naval Dockyard Sdn Bhd
πLMS LCS OPV NGPVs = DRAMA GHOIBBBπ
"..Kata Menhan Malaysia: “Kami Tidak Tertarik Akuisisi Frigat HMAS ANZAC Australia”
BalasHapusindomiliter | 25/06/2024
π€£π€£π€£π€£π€£π€£
(Kalo free maintenance + free ongkir maka kami mahu)
π€£π€£π€£π€£π€£π€£
Lagian siapa yang mau jual, Aussy masih pakai untok ambil parts Anzac class yang masih oprasional lon...
BalasHapusLalu di scrap total...π€£π€£π€£π€£
Yaaah...
Jiwa miskin dan KLAIM malon menggelora
Macam KLAIM Hornet Kuwait
π€£π€£π€£π€£π€£
Ini June hampir habis, klaim nego Hornet Kuwait tak terbukti
BalasHapusBukti MEMBUAL lagi
π€£π€£π€£π€£π€£π€£π€£
"..ada kabar datang dari neger jiran yang diam-diam sempat menganalisa untuk mengakuisisi HMAS ANZAC...
BalasHapusAustralia tidak berencana untuk menjual frigat HMAS ANZAC. “HMAS ANZAC tidak layak untuk dijual, sebagain atau mayoritas suku cadang dari frigat ini akan ditambahkan ke rantai pasokan untuk mendukung platform yang tersisa di kelas tersebut,” menurut pernyataan dari juru bicara Kementerian Pertahanan Australia pada 30 Mei 2024..."
====
Tak dijual, namun direka-reka untok dibeli
π€£π€£π€£π€£π€£π€£π€£π€£
Anzac yang tidak dijual lagaknya dianalisis
BalasHapusSementara Type 23 yang jelas ditawarkan oleh tuannya, tapi malon nii pura pura tak dengar
Lawak...
π€£π€£π€£π€£π€£π€£π€£π€£
Inggris Tawarkan Malaysia Sepasang Frigat Type 23 Duke Class, Spesifikasi Menarik Tapi ‘Tiada Wang’
BalasHapusindomiliter | 11/05/2024 |
π€£π€£π€£π€£π€£π€£π€£
SEA to Provide KraitSense ASW System for OPV Programme
BalasHapusSEA has been awarded a contract to supply two of its innovative ASW systems, KraitSense, to a South-East Asian Navy for a new offshore patrol vessel (OPV) programme.
Anti-Submarine Warfare (ASW) capability is one of the most important aspects for a modern combat vessel or a warship, especially the one with medium to large tonnage such as destroyer, frigate, or corvette. The capability of doing Anti-Submarine Warfare is of course important for a surface naval ship, enable them to locate enemy submarine position, then tracking the submarine and attack it with the right weapon system, such as anti-submarine torpedo and anti-submarine rocket. Sonar plays a very important role for a ship ASW capability. Sonar can search, track and identify any objects that lay beneath the ocean, not just enemy submarine. It makes sonar so important for any combat vessel, including the one with small tonnage, such as PC-40 class patrol ship and KCR-60 class fast attack craft that belongs to Indonesian Navy.
https://defense-studies.blogspot.com/2023/06/sea-to-provide-kraitsense-asw-system.html?m=1
-------
OPV 98meter Terbaruw kita pun dilengkapi Sonar tarik buat ASW,
makin mabteb bisa tembak torpedo haha!πππ
ingat 2 kaprang OPV ini pake cms havelsan dan rudal Atmaca semua dari Turkiye
bisa buat kcr 40/60 wah manteb
lah seblah KOSONG haha!πππ
masa korvet KALAH TOTAL ama OPV haha!π€π€π€
Litoral Mission Ship oom..
HapusMisi tengok tengok dari jauh
π€£π€£π€£π€£
GHOIB GHOIB GHOIB
BalasHapusBUKTI BELUM KONTRAK LMS
STM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
GHOIB GHOIB GHOIB
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = GHOIB
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
NGPV DIBAYAR 27 JADI NOL = Najib berkata, Limbungan TLDM dikorporatkan kerajaan pada 1991 sebelum dijual kepada syarikat swasta Penang Shipbuilding & Construction Corporation(PSC) untuk menjadi syarikat PSC-Naval Dockyard pada 1995. Pada tahun 1998, kerajaan memberi kontrak pembinaan untuk 27 kapal NGPV dengan anggaran bajet RM30 bilion kepada syarikat swasta itu. Fasa pertama membabitkan pembinaan enam kapal pertama dengan kos RM6 bilion. "Namun kontrak ini gagal dan tiada satu kapal pun diserahkan oleh PSC-Naval Dockyard
---
LCS BAYAR HUTANG LAPUK NGPV = seperti didedahkan Jawatankuasa Kira-kira Wang Negara (PAC) dan CEO LTAT, syarikat BNS menggunakan RM400 juta daripada bayaran pendahuluan bagi projek LCS untuk menjelaskan hutang lapuk bagi projek NGPV,"
syarikat PSC-Naval Dockyard pada Disember 2005 sebelum dijenamakan semula menjadi syarikat Boustead Naval Dockyard Sdn Bhd
πLMS LCS OPV NGPVs = DRAMA GHOIBBBπ
https://www.zonajakarta.com/nasional/67312979033/dikira-setara-diponegoro-class-korvet-ada-class-pesanan-malaysia-alami-downgrade
BalasHapusTAK PERLU BANYAK BUAL☝️☝️☝️FAKTA
ππ€£ππ€£ππ€£
calon ADA kl hanya mampu utk 3Dimensi,
BalasHapusNO⛔️CIWS, NO⛔️SONAR, NO⛔️TORPEDO
ini ADA paling LeMaH yang perna dibuat turkiye haha!πππ
masa kalah ama OPV apalagi KCR/KCT 60 meter kita, ada Torpedo dan rudal Panjang haja!πππ
Anggaran militer malasya lebih kecil dibanding Singapura, Vietnam dan Filipina, tapi ada netizen Jiran membual kalau semua peralatannya dibeli cash π, logikanya dengan anggaran sekecil itu dibagi beberapa Matra, berapa besar yang tersisa untuk pembelanjaan alutsista π,
BalasHapusApalagi rasio hutang pemerintah Malaysia sudah melewati batas aman π
Sebentar lagi ada netizen Jiran yang Denial fakta tersebut π€§
Malon anggaran MEMBUALNYA yang besarππ€£ππ€£ππ€£
HapusKapal ini akan dipersenjatai dengan satu Meriam Leonardo 40 mm, dua Senapan Mesin Berat 20 mm, dan dua Peluncur Rudal Permukaan ke Udara. Bung Karno akan dilengkapi dengan terpedo dan sonar, serta dirancang mampu membawa helikopter Panther dan memiliki helly deck yang mirip dengan korvet kelas Bung Tomo.
BalasHapus-----
korvet VVIP kita pun punyak Torpedo dan Sonar...mantabbb haha!πππ
aman dari kasel dan ranjau
calon ADA kl hanya mampu utk 3Dimensi,
BalasHapusNO⛔️CIWS, NO⛔️SONAR, NO⛔️TORPEDO
ini ADA paling LeMaH yang perna dibuat turkiye....MURAH BANGET haha!πππ
apalagi kapal darat, bisanya Ngambang gealo geol..tak bisa berlayar haha!πππ
kapal darat kapal KOSONG haha!πππ
BalasHapussi LeMeS NO⛔️Sonar, NO⛔️Torpedo, NO⛔️CIWS tamat lagiiiii haha!πππ
Nasib LeMeS selalu kalah oom
HapusLeMeS-1 kalah ama spek Bangla
LeMeS-2 kalah ama spek Pakistan
π€£π€£π€£π€£π€£π€£
LCS, LeMeS semuanya kalah spek ama korvet filipin om pedang haha!πππ
HapusGHOIB GHOIB GHOIB
BalasHapusBUKTI BELUM KONTRAK LMS
STM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
GHOIB GHOIB GHOIB
BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
BUKTI CUMA LOA = GHOIB
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
---
LCS DIBAYAR 6 JADI NOL = The cost of the LCS project is now RM11.2 billion. It must be noted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And not a single ship has been delivered yet.
---
OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malaysia. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
---
NGPV DIBAYAR 27 JADI NOL = Najib berkata, Limbungan TLDM dikorporatkan kerajaan pada 1991 sebelum dijual kepada syarikat swasta Penang Shipbuilding & Construction Corporation(PSC) untuk menjadi syarikat PSC-Naval Dockyard pada 1995. Pada tahun 1998, kerajaan memberi kontrak pembinaan untuk 27 kapal NGPV dengan anggaran bajet RM30 bilion kepada syarikat swasta itu. Fasa pertama membabitkan pembinaan enam kapal pertama dengan kos RM6 bilion. "Namun kontrak ini gagal dan tiada satu kapal pun diserahkan oleh PSC-Naval Dockyard
---
LCS BAYAR HUTANG LAPUK NGPV = seperti didedahkan Jawatankuasa Kira-kira Wang Negara (PAC) dan CEO LTAT, syarikat BNS menggunakan RM400 juta daripada bayaran pendahuluan bagi projek LCS untuk menjelaskan hutang lapuk bagi projek NGPV,"
syarikat PSC-Naval Dockyard pada Disember 2005 sebelum dijenamakan semula menjadi syarikat Boustead Naval Dockyard Sdn Bhd
πLMS LCS OPV NGPVs = DRAMA GHOIBBBπ
BalasHapus"Selaras dengan perkara itu kerajaan telah membayar RM7.15 bilion iaitu bersamaan 63.69 peratus, berbanding perancangan asal pembayaran iaitu 68.43 peratus berdasarkan kontrak mengikut kemajuan semasa perolehan LCS kelima-lima kapal secara keseluruhannya,” katanya.
-----
lah ternyata baruw RM7.15,
kata warganyet bayar cash, lah ini dipirit2
catat Angsuran=NGUTANG haha!π π π
total RM 9 milyar untuk 6 kapal lcs
katanya cukup 5..RM 6 bn ajah bayarnya, tambah biaya penalti delay
kenapa bayar lagi, klo sampe rm 9 bn ato lebih
fiks gomen kena prenk BNS eh blom lunas haha!πππ
Lunas Ta'i!!ππ€£πππππ€π
BalasHapus5 Kapal Salah Fotong.....cost termahal.didunia...wkwkwkwk
BalasHapusPULLED OUT (DIKELUARKAN) = Armidale class is a class of patrol boats built for the Royal Australian Navy (RAN). Planning for a class of vessels to replace the fifteen Fremantle-class patrol boats began in 1993 as a joint project with the Royal Malaysian Navy, but was cancelled when Malaysia pulled out of the process. The project was reopened in 1999 under the designation SEA 1444, with the RAN as the sole participant.
BalasHapus---
GHOIB = BUKTI BELUM KONTRAK LMS
STM officials, in conversation with Naval News, affirmed that the project remains on schedule, with final contract details under negotiation. Consequently, while the contract wasn’t anticipated to be signed at the DSA 2024 exhibition, it is expected to be finalized in the forthcoming months. However, STM officials refrained from divulging specifics regarding the contract timeline and the potential configuration of the ship
---
GHOIB = BUKTI BELUM KONTRAK ATMACA
While the Malaysian Navy continues to work on the choice of the anti-ship missile system of LMS, Naval News has learned that the Atmaca missile, developed by Roketsan, has emerged as a leading contender. If this trajectory remains unchanged, it is likely that the Atmaca missile, akin to the one installed on the TCG KINALIADA, the Turkish Navy’s 4th Island-class corvette, will be mounted on the LMS.
---
GHOIB = BUKTI CUMA LOA
THEY COULD STILL BE FINALISING THE TECHNICAL DETAILS OF THE SHIPS
Three of the ships will be built in Turkiye under the LOA according to the release though it did not identify the shipyards to build them. Defence Minister DS Khaled Nordin was present at the LOA handing over ceremony so it is likely the ministry will issue – a less detailed press release on it. Do note that even if the LOA is issued, they could still be finalising the technical details of the ships.
---
DOWNGRADE LMS B2
RADAR 3D
MERIAM 30mm
NO TORPEDO
NO SONAR
STM, in its role as main contractor, will turn to the Turkish defence sector for such equipment as the Combat Management System; the Gun Fire Control System, to be supplied by HAVELSAN; and the 3D Search Radar, Fire Control Radar, IFF, 30mm Gun, ESM and Chaff Decoy System, as well as other electronic sensors, to be supplied by ASELSAN. ROKETSAN will be supplying its ATMACA Surface-to-Surface G/M System.
==================
HIBAH KAPAL 1967 = The post stated that among his achievements in the MMEA were that he was the team leader for a suitability study on absorbing the US Coast Guard cutter – USCG Decisive. Checks on the US Coast Guard website showed that Decisive– a Reliance class cutter – was laid in 1967 and commissioned in 1968
-----
HIBAH KAPAL 1980 = KM Perwira, one of the two Bay class patrol boats donated to MMEA by Australia. It is likely that the Bay class was the design proposed for the tri-nation VLPV project in the late 80s.
-----
PERBAIKAN DIBIAYAI JEPANG = Kapal patroli kedua yang disumbangkan oleh Jepang Coast Guard (JCG) untuk APMM/MMEA akan berlayar ke pulang pada akhir Mei, saat ini kapal dengan nama KM Arau ini sedang dalam tahap perbaikan akhir yang dilakukan di Jepang.
-----
HIBAH KAPAL 1989 DAN 1991 = Jepang menghibahkan dua kapal kelas 90m masing-masing PL-01 Ojima dan PL-02 Erimo, kedua kapal ini masuk dinas di JCG pada tahun 1989 dan 1991.
-----
HIBAH KAPAL = KM Pekan is an Ojika-class offshore patrol vessel operated by the Malaysian Coast Guard. This ship, together with KM Arau and KM Marlin was transferred from the Japan Coast Guard to Malaysia in order to strengthen the relations between the two countries. The ship was built as the Ojika for the Japanese Coast Guard in 1990–1991
-----
HIBAH KAPAL 1989 = KM Arau is an offshore patrol vessel operated by the Malaysian Coast Guard. She was the second ship transferred from the Japan Coast Guard together with KM Pekan and KM Marlin. KM Arau was formerly known as Oki (PL-01) in the Japan Coast Guard
Si kaum semburi penyembah h0m0 lesbi kecoh saja, dari loa 2011 sampai ke hari ini kapal ini saja yg dibacotin
BalasHapusDasar kaum semburit