11 Februari 2025

Gagal Selesaikan Kapal OPV 2 dan OPV 3, Malaysia Putuskan Kontrak dengan Galangan

11 Februari 2025

OPV 1 KM Tun Fatimah (photo: APMM)

Gagal siap kapal peronda pesisir APMM, kontrak pembina ditamatkan
Farhana Farush – Kuala Lumpur

Tanda tanya mengenai status semasa pembinaan dua lagi kapal peronda luar pesisir (OPV) Agensi Penguatkuasa Maritim Malaysia (APMM) terjawab selepas kerajaan menamatkan kontrak dengan THHE Destini Sdn Bhd (TDSB) setelah ia gagal menyiapkan projek berkenaan.

Menteri Dalam Negeri Saifuddin Nasution Ismail berkata susulan penamatan yang ditandatangani pada 31 Disember lalu, syarikat itu dikenakan kadar denda dan ganti rugi ditetapkan (LAD) sebanyak RM12.49 juta [AS$2.82 juta] di atas kelewatan menyiapkan kapal OPV 2 dan OPV 3.

Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan. 


“Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.

Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.

Kerajaan memeterai kontrak perolehan tiga OPV bernilai RM738.9 juta [AS$166.82 juta] dengan TDSB pada Januari 2017 dan projek tersebut sepatutnya siap sepenuhnya pada Julai 2020.

Selepas beberapa kali tertangguh, TDSB hanya berjaya menyerahkan OPV 1 yang dinamakan KM Tun Fatimah pada Januari tahun lalu.

179 komentar:

  1. Balasan
    1. Berat sebelah nya malassia.. alias korup !!! LCS bahkan tidak pernah oleh boustead menyerahkan perahu buatannya, masih mending destini ini.

      Hapus
  2. Akhirrnyaaaa TAMAT haha!❌️❌️❌️

    BalasHapus
    Balasan
    1. Thanks min, sudah kasih bantingan sadis untok geng MALAYDESH....

      😂😂🤣🤣🤣🤣

      Hapus
    2. nyoiihh 4 hari ditunggu nongol jugak haha!🤭🤭🤭

      Hapus
  3. Ini yang bilang bukan orang awam ataupun wartawan pengamat yaah...

    Ini kata Menteri Dalam Negeri Saifuddin Nasution Ismail...

    😂😂🤣🤣🤣😛😛

    BalasHapus
  4. Singkatnya Menteri Dalam Negeri Saifuddin Nasution Ismail kata : GAGAL

    🤣🤣😂😂🤪🤪🤪🤪

    BalasHapus
  5. Putus lagi..putus lagiiii..putusss lagii
    Sekarang Putussss...besok kensel lagiii...Assooyy haha!🤣🤣🤣

    BalasHapus
  6. Heli sewa, GAGAL
    OPV Mangkrak, GAGAL

    Hahahahqhahaaaa...😂😂🤣🤣🤪😛

    BalasHapus
  7. Maaf ya itu Pembatalan Kontrak untuk pembina asal...bukan 2 OPV DIBATAL 🤣🤣🤣

    2 buah OPV akan di Teruskan dengan firma lain ya untuk menyiapkannya.. 😎😎... ORANG KAYA.. KALIS NGUTANG LENDER.. 🤣🤣

    BalasHapus
    Balasan
    1. Banyak alasan... gagal ya gagal saja

      Hapus
    2. Admin kejam angkat berita tentang Malon kok gak ada yg bermutu. Cuma bikin gelak kawasan tapi gpp kan Gempurwaria masih tetap bual dan lawak di DS. Itu yg ditunggu warga DS. Ngamuknya beruk Gempork.parah.

      Hapus
    3. Orang kaya banyak gagalnya dan uang kopi untuk aset mangkrak yah Pork.lawak kau.

      Hapus
    4. NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
      NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
      NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -------------------
      OPV 2 DAN OPV 3 = TAMAT
      OPV 2 DAN OPV 3 = TAMAT
      OPV 2 DAN OPV 3 = TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
      ===============
      PROBLEMS SHIPYARD
      PROBLEMS SHIPYARD
      PROBLEMS SHIPYARD
      Local shipyards have poor record building big ships. LCS is one, Kedah is the first. The MMEA OPV is the other one. No need to be a cheerleader about it and trying to play it safe. It’s bad then it’s bad. Can blame the system, blame the politicians, blame the lack of controls, blame the people, the fact remains the local shipyards failed to deliver, and it has cost RMN. Less we forget, BNS (from the days of PSC-ND) had more than 20+ years to learn building complex ships. Also, the shipbuilding pipeline is too limited to support a local industry, meaning there is no learning possible – BNS (and its predecessor PSC-ND) only had contract to build 12 warships in its existence. In fact, come 2030, after 30 years, if we’re lucky the shipyard would still only have built 11 ships. In contrast ST Engineering had more than 40 ships over 28 years and have confirmed 6 new ships out to 2030. Learning is one thing, tolerating “still learning” after 20 plus years is not good enough. Not recognising learning is not possible because of limited pipeline is another. Local shipyards have proven capable of building certain type of ships because of good pipeline, so good for them that they win those contract – they can learn over time to build bigger ships. But for now, no need to be a cheerleader for local shipyards pitching to win big ships for RMN and MMEA

      Hapus
  8. Projek 2 kapal OPV APMM yang tertangguh akan disambung semula

    https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/

    BalasHapus
    Balasan
    1. NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
      NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
      NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -------------------
      OPV 2 DAN OPV 3 = TAMAT
      OPV 2 DAN OPV 3 = TAMAT
      OPV 2 DAN OPV 3 = TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
      ===============
      PROBLEMS SHIPYARD
      PROBLEMS SHIPYARD
      PROBLEMS SHIPYARD
      Local shipyards have poor record building big ships. LCS is one, Kedah is the first. The MMEA OPV is the other one. No need to be a cheerleader about it and trying to play it safe. It’s bad then it’s bad. Can blame the system, blame the politicians, blame the lack of controls, blame the people, the fact remains the local shipyards failed to deliver, and it has cost RMN. Less we forget, BNS (from the days of PSC-ND) had more than 20+ years to learn building complex ships. Also, the shipbuilding pipeline is too limited to support a local industry, meaning there is no learning possible – BNS (and its predecessor PSC-ND) only had contract to build 12 warships in its existence. In fact, come 2030, after 30 years, if we’re lucky the shipyard would still only have built 11 ships. In contrast ST Engineering had more than 40 ships over 28 years and have confirmed 6 new ships out to 2030. Learning is one thing, tolerating “still learning” after 20 plus years is not good enough. Not recognising learning is not possible because of limited pipeline is another. Local shipyards have proven capable of building certain type of ships because of good pipeline, so good for them that they win those contract – they can learn over time to build bigger ships. But for now, no need to be a cheerleader for local shipyards pitching to win big ships for RMN and MMEA

      Hapus
    2. SHARE BERITA NOVEMBER 2024
      OPV 2 DAN OPV 3 = TAMAT DESEMBER 2024
      -------------
      BERUKWARIA 11 Februari 2025 pukul 11.28
      OPV 1 dan 2 JALAN TERUSSSS... 😎😎🇲🇾🇲🇾
      tps://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/
      -------------
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      ---
      KONTRAK 2017
      TH Heavy Engineering Berhad (THHE) and Destini Berhad (Destini) announced today that they have secured a contract worth RM738.9 million (inclusive of 6% GST) for the supply, delivery, testing and commissioning of three units of Offshore Patrol Vessels (OPV) for the Malonn Maritime Enforcement Agency (MMEA)
      ---
      DIJANGKA 2020
      Kontrak Damen 1800 OPV diberikan kepada perusahaan lokal THHE-Destini pada awal tahun 2017. Kontrak kapal bernilai RM738,9 juta dan konstruksi dimulai pada Desember 2017. Kapal pertama akan selesai pada pertengahan tahun 2020
      --
      MIRING KABEL PUTUS
      THHE general manager Azizul Hanafee Zain explained that the ship tilted to one side after one of the steel cables attached to the supporting structure underneath the ship was cut.
      ---
      DISUNTIK HUTANG
      government is injecting RM152.6 million to ensure that the first Offshore Patrol Vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA)
      ---
      OPV DIAMBIL MOF 2023
      The government will inject RM152.6 million to ensure that the first offshore patrol vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA) will be completed this year, Prime Minister Anwar Ibrahim said today.
      He said the finance ministry (MoF) had taken over the OPV project from Tabung Haji (TH) subsidiary, Destini Sdn Bhd, after it was found to be facing major problems.
      ---
      THHE BANGKRUT 2023 = THHE TUTUP
      Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
      The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.

      Hapus
  9. Projek 2 kapal OPV APMM yang tertangguh akan disambung semula.

    https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/

    BalasHapus
    Balasan
    1. Malonn's defense policy faces a number of challenges, including:
      • Corruption
      The military has been accused of corruption in defense procurement. The government's Integrity Plan addresses corruption, but it's not a strategic document.
      • Recruitment
      The military has difficulty recruiting and retaining qualified personnel. This is partly due to poor service conditions.
      • Infrastructure
      The defense infrastructure needs to be fixed, but the government is prioritizing other needs.
      • Ethnic composition
      The armed forces are overrepresented by Indigenous Malonnns (Bumiputeras) and underrepresented by ethnic Chinese Malonnns.
      • Budget
      Malonn has consistently underspent on defense needs.
      • Defense industry
      The defense industry has challenges with research and development, technology transfer, and job creation.
      • Territorial disputes
      Malonn has territorial disputes and intrusions in its Exclusive Economic Zone (EEZ).
      • Transboundary haze
      Transboundary haze has had a negative impact on Malonn's economy and social activities.
      • Maritime defense
      The Strait of Singapore is critical for Malonn's maritime defense, but it's also important for international commerce.
      Some of the challenges have been addressed by the Anwar government, which has implemented plans to attract more non-Bumiputeras to the military.
      ===========
      Some factors that contribute to the Malonn Army's perceived weakness include:
      • Political instability: Frequent government changes since 2018 have made it difficult for the Malonn Armed Forces (MAF) to receive the support it needs.
      • Corruption: The MAF has been plagued by corruption.
      • Poor planning: The MAF has been criticized for poor planning.
      • Political interference: Political leaders have interfered in the MAF's procurement process.
      • Outdated equipment: Much of the MAF's equipment was purchased between the 1970s and 1990s, and the government has been unable to provide modern equipment.
      Lack of military knowledge: Military personnel have struggled with decision-making and problem-solving during military operations

      Hapus
    2. LEASE 28 HELI = 119 HELI BARU :
      LEASE 28 HELI RM 16.8BN = USD 3.7BN/USD 3.700 JT DOLAR
      •HARGA HELI AW149 = USD 31 JUTA
      •28 UNITK X $ 31 JT= USD 857 JUTA
      •$ 3.700JT ÷ $ 31 JT = 119 HELI BARU
      ----
      4x LEBIH MAHAL LEASE DARIPADA BELI BARU =
      LEASE 15 TAHUN = RM16.8 BILION
      BELI BARU = RM3.954 BILION
      LEASEan selama 15 tahun dianggarkan mencecah RM16.8 bilion, jauh lebih tinggi berbanding kos pembelian helikopter serupa yang dianggarkan sekitar RM3.954 bilion.Malon (ATM).
      ==============
      Malonn's armed forces procurement faces several weaknesses, including:
      1. Corruption
      The defense sector is at high risk of corruption, and procurement is vulnerable to powerful interests. The Malonn Anti-Corruption Commission (MACC) received the highest number of corruption complaints for procurement activities in 2013 and 2018.
      2. Political influence
      Decisions are often driven by vendors and against strategic interests. For example, Malonn has sometimes exchanged hardware for palm oil, which exposes the procurement process to political influence.
      Weak parliamentary oversight
      Parliamentary oversight is weak, and audit bodies can only provide ex-post scrutiny.
      3. Limited financial scrutiny
      Financial scrutiny is limited by excessive secrecy.
      4. Violation of procedures
      Procedures are regularly circumvented through political influence. For example, the purchase of military helicopters in 2015 violated the Ministry of Finance's procedures
      ==============
      MALONNN ARMED FORCES LOGISTIC MANAGEMENT PROBLEM
      Most of the assets bought by the Malonnn government in solidify the country’s defence were used and outdated. This creates various problems; and the used and outdated airforce assets will expose to the air threat from the enemy [5]. This is because most of the Malonnn Army (MA), Royal Malonnn Navy (RMN) and Royal Malonnn Air Force (RMAF) equipments were bought between 1970s to the end of 1990s and still in MAF main inventory [6]. Other than that, lack of modern and latest military assets faced by MAF, will expose it to the internal threat and especially external threat that is escalating with the uncontrollable situation in the southern Philippines and China’s aggressive stand in the island conflict issue in the South China Sea [7]. Besides, the government is incapable to provide and equip modern and latest defence assets to MAF. Moreover, KD Rahman submarine issue (Scorpene) that cannot submerge in the demersal because of technical problem in 2010. It was a conventional submarine that can hold 10 torpedo and 30 mine destructors, was able to observe the country’s waters between 100 to 200 meters in depth. This also shows that the defence asset is outdated and cannot function well [8]. With various reports on pirates’ attacks and abductions in Sabah waters, terrorists attack in Lahad Datu in February 2013 and recently the missing RMN boat KD Perdana on 22 May 2017 for a few days due to communication problem. This scenario creates concern towards MAF logistics to ensure and guarantee the country’s security. With many series of RMAF training and fighter aircrafts crashes and accidents involving MA and vehicles damages that happen quite often, raise questions to the government policy that still maintain the outdated vehicles for country’s defence. Therefore, this study examines the problem in MAF logistic aspect and the effect towards the country’s security.....

      Hapus
  10. Malaydesh kata Ompong lah, Ngutang lah, Gagal lah..blah..blah..blah...

    Ternyata aset depan hidung MALAYDESH sendiri GAGAL

    🤣🤣😂😂😂🤣🤣🤣

    BalasHapus
  11. Sejak 2017 tak selesai..
    Blue print dibuatkan Damen, tinggal bikin..masih saja Mangkrak, lalu...GAGAL


    😂🤣😂😂😂😛🤪🤪🤪

    BODOH...😛

    BalasHapus
  12. OPV 1 dan 2 JALAN TERUSSSS... 😎😎🇲🇾🇲🇾

    Menurut beliau, ini bagi menyiapkan pembinaan kedua-dua kapal yang mana status OPV 2 sudah 76% siap manakala OPV 3 pula 57%.

    Fasa seterusnya ialah mengenal pasti syarikat yang berkelayakan untuk dipertimbangkan bagi meneruskan projek berkenaan.

    “Terdapat 12 buah limbungan kapal telah mengemukakan cadangan (RFI) untuk meneruskan pembinaan 2 buah OPV tersebut.

    https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/

    BalasHapus
    Balasan
    1. LEASE 28 HELI = 119 HELI BARU :
      LEASE 28 HELI RM 16.8BN = USD 3.7BN/USD 3.700 JT DOLAR
      •HARGA HELI AW149 = USD 31 JUTA
      •28 UNITK X $ 31 JT= USD 857 JUTA
      •$ 3.700JT ÷ $ 31 JT = 119 HELI BARU
      ----
      4x LEBIH MAHAL LEASE DARIPADA BELI BARU =
      LEASE 15 TAHUN = RM16.8 BILION
      BELI BARU = RM3.954 BILION
      LEASEan selama 15 tahun dianggarkan mencecah RM16.8 bilion, jauh lebih tinggi berbanding kos pembelian helikopter serupa yang dianggarkan sekitar RM3.954 bilion.Malon (ATM).
      ==============
      Malonn's armed forces procurement faces several weaknesses, including:
      1. Corruption
      The defense sector is at high risk of corruption, and procurement is vulnerable to powerful interests. The Malonn Anti-Corruption Commission (MACC) received the highest number of corruption complaints for procurement activities in 2013 and 2018.
      2. Political influence
      Decisions are often driven by vendors and against strategic interests. For example, Malonn has sometimes exchanged hardware for palm oil, which exposes the procurement process to political influence.
      Weak parliamentary oversight
      Parliamentary oversight is weak, and audit bodies can only provide ex-post scrutiny.
      3. Limited financial scrutiny
      Financial scrutiny is limited by excessive secrecy.
      4. Violation of procedures
      Procedures are regularly circumvented through political influence. For example, the purchase of military helicopters in 2015 violated the Ministry of Finance's procedures
      ==============
      MALONNN ARMED FORCES LOGISTIC MANAGEMENT PROBLEM
      Most of the assets bought by the Malonnn government in solidify the country’s defence were used and outdated. This creates various problems; and the used and outdated airforce assets will expose to the air threat from the enemy [5]. This is because most of the Malonnn Army (MA), Royal Malonnn Navy (RMN) and Royal Malonnn Air Force (RMAF) equipments were bought between 1970s to the end of 1990s and still in MAF main inventory [6]. Other than that, lack of modern and latest military assets faced by MAF, will expose it to the internal threat and especially external threat that is escalating with the uncontrollable situation in the southern Philippines and China’s aggressive stand in the island conflict issue in the South China Sea [7]. Besides, the government is incapable to provide and equip modern and latest defence assets to MAF. Moreover, KD Rahman submarine issue (Scorpene) that cannot submerge in the demersal because of technical problem in 2010. It was a conventional submarine that can hold 10 torpedo and 30 mine destructors, was able to observe the country’s waters between 100 to 200 meters in depth. This also shows that the defence asset is outdated and cannot function well [8]. With various reports on pirates’ attacks and abductions in Sabah waters, terrorists attack in Lahad Datu in February 2013 and recently the missing RMN boat KD Perdana on 22 May 2017 for a few days due to communication problem. This scenario creates concern towards MAF logistics to ensure and guarantee the country’s security. With many series of RMAF training and fighter aircrafts crashes and accidents involving MA and vehicles damages that happen quite often, raise questions to the government policy that still maintain the outdated vehicles for country’s defence. Therefore, this study examines the problem in MAF logistic aspect and the effect towards the country’s security.....

      Hapus
    2. Malonn's military has faced delays due to fiscal limitations and a lack of willingness to reduce government spending.
      Explanation
      • Defense budget
      Malonnn governments have been reluctant to cut government spending to fund defense. This has led to delays in the military's ability to procure new equipment and maintain existing assets.
      • Military size
      Malonnn governments have been reluctant to reduce the size of the armed forces by reducing manpower and equipment.
      • Military spending
      Malonn has been increasing its military spending, but the country's defense budget is still limited by fiscal constraints
      =============
      Malonn's defense policy faces a number of challenges, including:
      • Corruption
      The military has been accused of corruption in defense procurement. The government's Integrity Plan addresses corruption, but it's not a strategic document.
      • Recruitment
      The military has difficulty recruiting and retaining qualified personnel. This is partly due to poor service conditions.
      • Infrastructure
      The defense infrastructure needs to be fixed, but the government is prioritizing other needs.
      • Ethnic composition
      The armed forces are overrepresented by Indigenous Malonnns (Bumiputeras) and underrepresented by ethnic Chinese Malonnns.
      • Budget
      Malonn has consistently underspent on defense needs.
      • Defense industry
      The defense industry has challenges with research and development, technology transfer, and job creation.
      • Territorial disputes
      Malonn has territorial disputes and intrusions in its Exclusive Economic Zone (EEZ).
      • Transboundary haze
      Transboundary haze has had a negative impact on Malonn's economy and social activities.
      • Maritime defense
      The Strait of Singapore is critical for Malonn's maritime defense, but it's also important for international commerce.
      Some of the challenges have been addressed by the Anwar government, which has implemented plans to attract more non-Bumiputeras to the military.

      Hapus
  13. OPV versi "Tanda tanya"

    😂😂🤣🤣🤪🤪😛😛😛

    BalasHapus
  14. OPV 1 dan 2 JALAN TERUSSSS... 😎😎🇲🇾🇲🇾

    Menurut beliau, ini bagi menyiapkan pembinaan kedua-dua kapal yang mana status OPV 2 sudah 76% siap manakala OPV 3 pula 57%.

    Fasa seterusnya ialah mengenal pasti syarikat yang berkelayakan untuk dipertimbangkan bagi meneruskan projek berkenaan.

    “Terdapat 12 buah limbungan kapal telah mengemukakan cadangan (RFI) untuk meneruskan pembinaan 2 buah OPV tersebut.

    https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/

    BalasHapus
    Balasan
    1. DESEMBER 2024 OPV TAMAT
      DESEMBER 2024 OPV TAMAT
      DESEMBER 2024 OPV TAMAT
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam..
      -----
      OPV 2025-2017 = 9 TAHUN
      9 TAHUN MANGKRAK
      9 TAHUN MANGKRAK
      OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up NOtice dated Sept 13.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      ==================
      ==================
      1. real contract and delivery five units C130J Hercules
      2. real contract and delivery two unit Frankethal class Countermine vessels (Pulau Fani class)
      3. real contract and delivery four units KCR 60 Fast missiles boats PT PAL
      4. real contract and delivery 9 units Bell 412 EPI
      5. real contract and delivery 8 additional H225 M
      6. real contract and delivery 2 units Bell 429 Global Ranger
      7. real contract and delivery 18 Medium weight tank Harimau
      8. real contract and delivery 22 Pandur II IFV
      9. real contract and delivery two unit Hospital Ships
      10. real contract and delivery one unit Command and control variant C295
      11. real contract and delivery one unit CN235 MPA
      12. real contract and delivery 7 Badak FSV, 26 ANOa apc and 10 additional Komodo recce vehicles in 2022
      13. real contract and delivery 4 AS 550 Fennec and 8 AS565 MBE, in 2024
      14. real contract and delivery five NC212i in 2023
      15. real contract and delivery one Leonardo RAT 31 DL/M
      16. real contract and delivery five C130H ordered from Australia in 2013 (finished in 2020) after received Grant of 4 C130H
      17. real contract and delivery 9 Teluk Bintuni class LST
      18. real contract and delivery six CH4B UCAV ordered in 2019
      19. real contract t and process building of Abeking & Rasmussen design ocean Hydrography ship
      20. real contract and process building two AH140 AAW Frigate
      21. real contract and process building two OPV 90 ASW patrol vessels
      22. real contract and process building 42 Dassault Rafale F4 fighter
      23. real contract and process building two A400M heavy cargo aircraft
      24. real contract and delivery M3 Amphibious bridging system
      25. real contract and delivery 3 KT1 Wong Bee ordered in 2018 along with radar and spares for T/A50
      26. real contract and process building 13 GM 403 GCI radar from Thales
      27. real contract and process building 12 ANKA S UCAV
      28. real contract and process building additional CH4B UCAV
      29. real contract and delivery Slingshot Satcom system
      30. real contract and delivery Falcon 8X aircraft
      31. real contract and process Thales Alenia earth observation satelite
      32. real contract and process 22 S70M Blackhawk
      33. real contract and process 6 N219 aircraft
      34. real contract and process 3 CN235 for Army
      35. real contract and process 2 PPA patrol Frigate
      36. real contract and process 2 Scorpene Subs
      37. real contract and process Khan Short Range ballistic missiles from Turki
      38. real contract and process Trisula Air defense system
      39. real contract and process 6 T50i aircraft
      40. real contract and delivery Oiler and replenishment ship
      41. real contract and delivery several Tug Harbor ships
      42. real contract and process Submarine rescue vessels and system
      43. real contract and delivery two Large LCU for army
      44. real contract and process 45 Atmaca

      Hapus
    2. Gagal m aning gagal m aning kepriwe koe son.Kasihan beruk nangis bombay.

      Hapus
    3. Malonn's military has faced delays due to fiscal limitations and a lack of willingness to reduce government spending.
      Explanation
      • Defense budget
      Malonnn governments have been reluctant to cut government spending to fund defense. This has led to delays in the military's ability to procure new equipment and maintain existing assets.
      • Military size
      Malonnn governments have been reluctant to reduce the size of the armed forces by reducing manpower and equipment.
      • Military spending
      Malonn has been increasing its military spending, but the country's defense budget is still limited by fiscal constraints
      =============
      Malonn's defense policy faces a number of challenges, including:
      • Corruption
      The military has been accused of corruption in defense procurement. The government's Integrity Plan addresses corruption, but it's not a strategic document.
      • Recruitment
      The military has difficulty recruiting and retaining qualified personnel. This is partly due to poor service conditions.
      • Infrastructure
      The defense infrastructure needs to be fixed, but the government is prioritizing other needs.
      • Ethnic composition
      The armed forces are overrepresented by Indigenous Malonnns (Bumiputeras) and underrepresented by ethnic Chinese Malonnns.
      • Budget
      Malonn has consistently underspent on defense needs.
      • Defense industry
      The defense industry has challenges with research and development, technology transfer, and job creation.
      • Territorial disputes
      Malonn has territorial disputes and intrusions in its Exclusive Economic Zone (EEZ).
      • Transboundary haze
      Transboundary haze has had a negative impact on Malonn's economy and social activities.
      • Maritime defense
      The Strait of Singapore is critical for Malonn's maritime defense, but it's also important for international commerce.
      Some of the challenges have been addressed by the Anwar government, which has implemented plans to attract more non-Bumiputeras to the military.

      Hapus
    4. The Malonnn Armed Forces (MAF) has faced a number of weaknesses, including corruption, outdated equipment, and a lack of authority.
      Corruption
      • The MAF has been plagued by corruption, which has undermined its combat readiness.
      • The MAF's Integrity Plan addresses corruption, but it's not a strategic document and doesn't provide comprehensive guidelines.
      • Commanders don't receive training on corruption issues before deployments.
      Outdated equipment
      • Most of the MAF's equipment was purchased between the 1970s and the 1990s.
      • The MAF's equipment is outdated and behind that of neighboring countries.
      • The government has been unable to provide the MAF with modern defense assets.
      Lack of authority
      • The MAF has limited authority, especially when it comes to non-traditional security challenges.
      • The MAF's role is generally to assist other authorities, such as the police.
      Other weaknesses
      • Political interference has undermined the MAF's combat readiness.
      • The MAF has faced budgetary constraints.
      =========
      The Malonnn Armed Forces (MAF) has faced a number of weaknesses, including outdated equipment, corruption, and political interference.
      Outdated equipment
      • The MAF's equipment is outdated and lacks modern military assets.
      • The MAF's equipment was purchased between the 1970s and 1990s.
      • The MAF's KD Rahman submarine was unable to submerge due to technical problems in 2010.
      Corruption
      • Political interference and corruption have undermined the MAF's combat readiness.
      • The MAF has been plagued by corruption.
      Budgetary constraints
      • The MAF's procurement has been held back by budgetary constraints.
      • The MAF's budget is limited to 1.4% of Malonn's GDP.
      Non-traditional security threats
      • The MAF faces non-traditional security threats, such as territory disputes with neighboring countries.
      • The MAF faces non-conventional threats, such as those that are transboundary in nature.
      Regional strategic environment
      • The MAF needs to consider the regional strategic environment when developing its strategic perspective.

      Hapus
    5. The The Malonn Armed Forces (MAF) face a number of challenges, including:
      Limited funding: The government has been unwilling to reduce spending elsewhere or cut the size of the armed forces.
      Outdated equipment: The MAF's equipment is outdated and behind that of neighboring countries.
      Logistics problems: The MAF's logistics system may not be able to support combat operations.
      Political interference: Political interference and corruption may undermine the MAF's combat readiness.
      Lack of government guidance: The government may not have a clear strategic direction for the defense industry. Malonn Armed Forces (MAF) face a number of challenges, including:
      Limited funding: The government has been unwilling to reduce spending elsewhere or cut the size of the armed forces.
      Outdated equipment: The MAF's equipment is outdated and behind that of neighboring countries.
      Logistics problems: The MAF's logistics system may not be able to support combat operations.
      Political interference: Political interference and corruption may undermine the MAF's combat readiness.
      Lack of government guidance: The government may not have a clear strategic direction for the defense industry.
      ============
      The Royal Malonnn Navy (RMN) has faced several problems, including delayed replacements for its aging fleet and a failed Littoral Combat Ship (LCS) program. These issues have made it difficult for the RMN to patrol its vast maritime domain.
      Delayed replacements
      • A government audit found that the RMN's plans to replace its aging fleet have stalled due to mismanagement.
      • The RMN has only received four of its planned 18 new vessels.
      • Over half of the RMN's fleet is past its prime.
      Failed LCS program
      • The LCS was not suitable for fighting peer competitors like China.
      • The LCS lacked the lethality and survivability needed in a high-end fight.
      • The LCS had low endurance and lacked significant air and surface warfare capabilities

      Hapus
  15. 😂😂🤣🤣🤪😛😛

    Gagal siap kapal peronda pesisir APMM, kontrak pembina ditamatkan

    BalasHapus
  16. Jelas diberita tu adalah PEMBATALAN FIRMA asal yang membina kapal OPV.... 🤣🤣🤣🤣

    GORILLA klaim pula konon kapal OPV DIBATALKAN.. BODOH... 🤣🤣

    BalasHapus
    Balasan
    1. Banyak alasan, banyak cakap.
      Gagal ya gagal aja.
      Emang bodoh kenyataannya

      Hapus
    2. Tololnya kok gak habis habis? LCS mangkrak OPV gagal. Cuma satu yg berhasil ngamuk dan bualnya Gempork yg berhasil membuat gelak di DS.

      Hapus
    3. The Malonnn Armed Forces (MAF) faces a number of challenges, including:
      • Logistics
      A study noted that the MAF's rapid development has raised questions about its readiness to face threats.
      • Budgeting
      Malonn's defense budget and spending has been limited by fiscal constraints. The government has been unwilling to cut spending elsewhere or reduce the size of the armed forces.
      • Personnel
      The MA has identified that military personnel struggle with thinking skills, decision-making, and problem-solving during military operations.
      • Procurement
      The Malonnn procurement system needs reform. The LCS program has been delayed and reduced in scope.
      • Political interference
      Political interference and corruption are undermining combat readiness.
      • Territorial disputes
      Malonn faces territorial disputes and intrusions in its Exclusive Economic Zone (EEZ).
      • Transboundary haze
      Transboundary haze has had a grave impact on economic and social activities in MalonnThe Royal Malonnn Air Force (RMAF) faces several problems, including:
      • Fleet sustainment
      The RMAF has faced challenges maintaining its fleet of aircraft. For example, in 2018, only four of the RMAF's 18 Sukhoi Su-30MKM aircraft were able to fly due to maintenance issues and a lack of spare parts.
      • Technological obsolescence
      Some aircraft in the RMAF's fleet are reaching technological obsolescence. For example, the Kuwaiti HORNET MALONNs are an earlier block of the HORNET MALONN, which may cause compatibility issues with spare parts.
      • Modernization
      The RMAF has ambitious plans to modernize its air capabilities to address current and future threats. However, the government's defense modernization budget is limited
      ==============
      The Sukhoi Su-30MKM has some weaknesses, including engine problems, integration with Western systems, and fatigue failure.
      Engine problems
      • In 2018, Malonn grounded 14 out of 18 Su-30MKM aircraft due to engine problems and a lack of spare parts.
      • The AL-31FP engine in the Su-30MKA has experienced numerous failures, including bearing failures due to metal fatigue and low oil pressure.
      Integration with Western systems
      • The Su-30MKM's Russian origin may limit its integration with Western systems.
      • This could make it difficult to fully integrate with NATO standards, such as Link 16, which is important for modern network-centric warfare.
      Fatigue failure
      • Aircraft structures and components are prone to fatigue failure due to fluctuating stress.
      • Fatigue failure is a gradual form of local damage that can lead to defects or cracks.
      Other considerations
      • The Su-30MKM is a larger aircraft, which means it may be seen earlier by radar and visual combat.

      Hapus
    4. The Royal Malonnn Navy (RMN) faces a number of challenges, including a fleet that is aging, delays in acquiring new ships, and corruption.
      Aging fleet
      • Half of the RMN's fleet of 49 ships are past their serviceable lifespan.
      • The fleet is largely past its prime, making it difficult to monitor the country's extensive maritime domain.
      Delays in acquiring new ships
      • The RMN has experienced delays in acquiring new ships, which has contributed to the use of ships that are beyond their useful life.
      • The RMN has canceled plans to add new batches of Lekiu frigates.
      Corruption
      • Some of the RMN's modernization efforts have been linked to corruption.
      • The Public Accounts Committee (PAC) found that BNS subsidiaries did not use all of the government's payments for the RM9 billion warship procurement.
      Other challenges
      • Maritime boundary disputes with other countries, including China, Indonesia, and the Philippines
      • Sea robbery, smuggling, and illegal sand mining
      • Maritime piracy, which can also be used by terrorists to raise funds
      China's assertiveness in the South China Sea
      ============
      The Malonnn Armed Forces (ATM) face several readiness issues, including a lack of funding, outdated technology, and morale issues. These issues can affect the ATM's combat readiness and strategic deterrence capability.
      Lack of funding
      • Inadequate funding can affect the ATM's training, technology, and morale.
      • The government may not be able to provide the ATM with the latest defense assets.
      Outdated technology
      • The ATM may lack modern military assets, which can expose it to internal and external threats.
      • For example, the KD Rahman submarine had technical issues in 2010 that prevented it from submerging.

      Hapus
  17. TAMAT, GAGAL, END.....🤣🤣😂🤪

    ===
    kerajaan menamatkan kontrak dengan THHE Destini Sdn Bhd (TDSB) setelah ia gagal menyiapkan projek berkenaan.

    BalasHapus
  18. Jelas diberita tu adalah PEMBATALAN FIRMA asal yang membina kapal OPV.... 🤣🤣🤣🤣

    GORILLA klaim pula konon kapal OPV DIBATALKAN.. BODOH... 🤣🤣

    BalasHapus
    Balasan
    1. DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      ---
      KONTRAK 2017
      TH Heavy Engineering Berhad (THHE) and Destini Berhad (Destini) announced today that they have secured a contract worth RM738.9 million (inclusive of 6% GST) for the supply, delivery, testing and commissioning of three units of Offshore Patrol Vessels (OPV) for the Malonn Maritime Enforcement Agency (MMEA)
      ---
      DIJANGKA 2020
      Kontrak Damen 1800 OPV diberikan kepada perusahaan lokal THHE-Destini pada awal tahun 2017. Kontrak kapal bernilai RM738,9 juta dan konstruksi dimulai pada Desember 2017. Kapal pertama akan selesai pada pertengahan tahun 2020
      --
      MIRING KABEL PUTUS
      THHE general manager Azizul Hanafee Zain explained that the ship tilted to one side after one of the steel cables attached to the supporting structure underneath the ship was cut.
      ---
      DISUNTIK HUTANG
      government is injecting RM152.6 million to ensure that the first Offshore Patrol Vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA)
      ---
      OPV DIAMBIL MOF 2023
      The government will inject RM152.6 million to ensure that the first offshore patrol vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA) will be completed this year, Prime Minister Anwar Ibrahim said today.
      He said the finance ministry (MoF) had taken over the OPV project from Tabung Haji (TH) subsidiary, Destini Sdn Bhd, after it was found to be facing major problems.
      ---
      THHE BANGKRUT 2023 = THHE TUTUP
      Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
      The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.

      Hapus
    2. GOODBYE 2024 OPV 2 DAN 3 = TAMAT
      GOODBYE 2024 OPV 2 DAN 3 = TAMAT
      GOODBYE 2024 OPV 2 DAN 3 = TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
      ============
      GOODBYE 2023 THHE DELISTED = BURSA MALONN
      GOODBYE 2023 THHE DELISTED = BURSA MALONN
      GOODBYE 2023 THHE DELISTED = BURSA MALONN
      Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
      The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
      The winding-up notice also stated that a meeting of creditors is scheduled for Oct 4 at 3pm.
      THHE is controlled by the Ministry of Finance-owned (MoF) unit Urusharta Jamaah Sdn Bhd, which holds a 64.45% stake in the company prior to its delisting on Sept 5, 2022
      TH Heavy was delisted from Bursa Malonn in September 2022, after failing to come up with a restructuring exercise despite being given eight extensions by the exchange since first entering Practice Note 17 status in April 2018.
      The decision to wind up came after THHE filed an ex-parte originating summons in July to call for a creditors’ meeting to propose a scheme of arrangement for the company.
      Global Mariner Offshore Services, Blackstone Technology Sdn Bhd and Dynac Sdn Bhd have reportedly filed applications to intervene in THHE’s ex-parte application.
      THHE had a joint venture partnership with Global Mariner, but a legal dispute arose between the two companies. The High Court ordered THHE to pay Global Mariner approximately RM288.72 million in damages.

      Hapus
    3. Jelas ditulis GAGAL bisa baca kan pork?

      Hapus
    4. The Malonnn Armed Forces (MAF) faces a number of challenges, including:
      • Logistics
      A study noted that the MAF's rapid development has raised questions about its readiness to face threats.
      • Budgeting
      Malonn's defense budget and spending has been limited by fiscal constraints. The government has been unwilling to cut spending elsewhere or reduce the size of the armed forces.
      • Personnel
      The MA has identified that military personnel struggle with thinking skills, decision-making, and problem-solving during military operations.
      • Procurement
      The Malonnn procurement system needs reform. The LCS program has been delayed and reduced in scope.
      • Political interference
      Political interference and corruption are undermining combat readiness.
      • Territorial disputes
      Malonn faces territorial disputes and intrusions in its Exclusive Economic Zone (EEZ).
      • Transboundary haze
      Transboundary haze has had a grave impact on economic and social activities in MalonnThe Royal Malonnn Air Force (RMAF) faces several problems, including:
      • Fleet sustainment
      The RMAF has faced challenges maintaining its fleet of aircraft. For example, in 2018, only four of the RMAF's 18 Sukhoi Su-30MKM aircraft were able to fly due to maintenance issues and a lack of spare parts.
      • Technological obsolescence
      Some aircraft in the RMAF's fleet are reaching technological obsolescence. For example, the Kuwaiti HORNET MALONNs are an earlier block of the HORNET MALONN, which may cause compatibility issues with spare parts.
      • Modernization
      The RMAF has ambitious plans to modernize its air capabilities to address current and future threats. However, the government's defense modernization budget is limited
      ==============
      The Sukhoi Su-30MKM has some weaknesses, including engine problems, integration with Western systems, and fatigue failure.
      Engine problems
      • In 2018, Malonn grounded 14 out of 18 Su-30MKM aircraft due to engine problems and a lack of spare parts.
      • The AL-31FP engine in the Su-30MKA has experienced numerous failures, including bearing failures due to metal fatigue and low oil pressure.
      Integration with Western systems
      • The Su-30MKM's Russian origin may limit its integration with Western systems.
      • This could make it difficult to fully integrate with NATO standards, such as Link 16, which is important for modern network-centric warfare.
      Fatigue failure
      • Aircraft structures and components are prone to fatigue failure due to fluctuating stress.
      • Fatigue failure is a gradual form of local damage that can lead to defects or cracks.
      Other considerations
      • The Su-30MKM is a larger aircraft, which means it may be seen earlier by radar and visual combat.

      Hapus
    5. Malonn's military has faced delays due to fiscal limitations and a lack of willingness to reduce government spending.
      Explanation
      • Defense budget
      Malonnn governments have been reluctant to cut government spending to fund defense. This has led to delays in the military's ability to procure new equipment and maintain existing assets.
      • Military size
      Malonnn governments have been reluctant to reduce the size of the armed forces by reducing manpower and equipment.
      • Military spending
      Malonn has been increasing its military spending, but the country's defense budget is still limited by fiscal constraints
      =============
      Malonn's defense policy faces a number of challenges, including:
      • Corruption
      The military has been accused of corruption in defense procurement. The government's Integrity Plan addresses corruption, but it's not a strategic document.
      • Recruitment
      The military has difficulty recruiting and retaining qualified personnel. This is partly due to poor service conditions.
      • Infrastructure
      The defense infrastructure needs to be fixed, but the government is prioritizing other needs.
      • Ethnic composition
      The armed forces are overrepresented by Indigenous Malonnns (Bumiputeras) and underrepresented by ethnic Chinese Malonnns.
      • Budget
      Malonn has consistently underspent on defense needs.
      • Defense industry
      The defense industry has challenges with research and development, technology transfer, and job creation.
      • Territorial disputes
      Malonn has territorial disputes and intrusions in its Exclusive Economic Zone (EEZ).
      • Transboundary haze
      Transboundary haze has had a negative impact on Malonn's economy and social activities.
      • Maritime defense
      The Strait of Singapore is critical for Malonn's maritime defense, but it's also important for international commerce.
      Some of the challenges have been addressed by the Anwar government, which has implemented plans to attract more non-Bumiputeras to the military.

      Hapus
    6. The Malonnn Armed Forces (MAF) has many outdated assets, including ships, helicopters, and spare parts. The MAF has acknowledged the need to replace these assets.
      Ships
      • The Royal Malonnn Navy's (RMN) Fast Attack Craft (FAC) is over 50 years old
      • The RMN has many vessels that are past their optimal lifespan
      • The RMN's age limit for submarines is 35 years, and 30 years for frigates, corvettes, and other ships
      • The RMN's smaller vessels, like fast patrol boats, have an age limit of 24 years
      Helicopters
      • Some helicopters in the MAF were commissioned in the 1960s
      Spare parts
      • The MAF has lost money due to spare parts that are no longer compatible with its fleet
      ===========
      • The Malonn Armed Forces (MAF) face a number of equipment challenges, including:
      Aging aircraft
      The RMAF's main fighter fleet includes the Su-30MKMs and Boeing F/A-18 Hornets, which are becoming technologically obsolete. Maintaining a large fleet of aging aircraft can be expensive.
      Limited defense budget
      The government's defense modernization budget is limited, making it difficult to afford new equipment.
      Local content
      Most MAF equipment is sourced from outside the country, and there is a lack of research and development (R&D) activities.
      Local company capabilities
      Local companies may not have the necessary capabilities to produce the equipment the MAF needs.
      OEM reluctance
      Original equipment manufacturers (OEMs) may be reluctant to share their technology for fear of competition.
      Defense infrastructure
      The condition of some military living quarters and defense infrastructure is poor

      Hapus
    7. Malonn armed forces have faced challenges due to limited funding, which has hindered their ability to modernize and respond to threats.
      Factors
      Fiscal constraints: The government has been unwilling to cut spending elsewhere to fund defense.
      Maintenance and repair: A significant portion of the defense budget goes toward maintenance and repair, leaving little for new assets.
      Political uncertainty: Political uncertainty has limited defense spending.
      Aging aircraft: The air force has a large fleet of aging aircraft that are expensive to maintain.
      Diversified acquisitions: The country has acquired advanced weapon systems from different countries, which can lead to technical and logistical problems.
      Poor governance: Poor governance has undermined the effectiveness of outsourcing programs.
      ==================
      The Malonnn Armed Forces (MAF) face several problems, including:
      • Budgetary constraints
      The Malonnn government has been unwilling to cut spending elsewhere or reduce the size of the armed forces.
      • Poor service conditions
      The MAF has difficulty recruiting and retaining high-caliber personnel due to poor conditions of service.
      • Outdated equipment
      The MAF lacks modern military assets, which puts it at risk from internal and external threats.
      • Political interference
      Political interference and corruption undermine the MAF's combat readiness.
      • Logistics issues
      The MAF faces problems with logistics that impact the country's National Defence Policy.
      • Rapid military development
      The rapid development of the military has raised questions about the MAF's readiness to face threats.
      Other issues include:
      • The government's inability to provide and equip the MAF with modern defense assets
      • The MAF's difficulty in fixing defense infrastructure
      • The MAF's difficulty in ensuring air superiority at all times

      Hapus
    8. The Royal Malonnn Air Force (RMAF) faces several problems with its aircraft, including an aging fleet, limited funding, and a lack of responsiveness in its logistics system.
      Aging fleet
      • The RMAF has a large fleet of aging aircraft that are difficult to maintain.
      • The RMAF's aircraft include the Mikoyan MiG-29, Boeing F/A-18 Hornet, and BAE Hawk.
      Limited funding
      • The government's defense modernization budget is limited.
      • The government is also dealing with the fiscal costs of the COVID-19 pandemic.
      • The government has many other priorities, including revitalizing the economy and reducing the national deficit.
      Logistics system
      • The RMAF's logistics system has problems with readiness and responsiveness.
      • Readiness is the ability to provide the minimum supply and service needed to start a combat operation.
      • Responsiveness is the ability to provide accurate support at the right time and place.
      Government change
      • Frequent changes in government since 2018 have hindered Malonn defense development
      ============
      Malonn armed forces have faced challenges due to limited funding, which has hindered their ability to modernize and respond to threats.
      Factors
      Fiscal constraints: The government has been unwilling to cut spending elsewhere to fund defense.
      Maintenance and repair: A significant portion of the defense budget goes toward maintenance and repair, leaving little for new assets.
      Political uncertainty: Political uncertainty has limited defense spending.
      Aging aircraft: The air force has a large fleet of aging aircraft that are expensive to maintain.
      Diversified acquisitions: The country has acquired advanced weapon systems from different countries, which can lead to technical and logistical problems.
      Poor governance: Poor governance has undermined the effectiveness of outsourcing programs.

      Hapus
  19. Blah...blah...blah

    GAGAL
    😂🤣🤣😛😛😛

    BalasHapus
  20. ada warganyet negeri🎰kasino genting tak terima...
    silakan bicara pada TEMBOK haha!🗿🗿🗿

    BalasHapus
  21. DESEMBER 2024 OPV 2 dan 3 = TAMAT
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    Tanda tanya mengenai status semasa pembinaan dua lagi kapal peronda luar pesisir (OPV) Agensi Penguatkuasa Maritim Malonn (APMM) terjawab selepas kerajaan menamatkan kontrak dengan THHE Destini Sdn Bhd (TDSB) setelah ia gagal menyiapkan projek berkenaan.
    Menteri Dalam Negeri Saifuddin Nasution Ismail berkata susulan penamatan yang ditandatangani pada 31 Disember lalu, syarikat itu dikenakan kadar denda dan ganti rugi ditetapkan (LAD) sebanyak RM12.49 juta [AS$2.82 juta] di atas kelewatan menyiapkan kapal OPV 2 dan OPV 3.
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
    -----
    LCS 2025-2011 = 15 TAHUN
    15 TAHUN MANGKRAK
    15 TAHUN MANGKRAK
    LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
    -----
    2029-2020 : 10 YEARS = OVERLIMIT DEBT
    2029-2020 : 10 YEARS = OVERLIMIT DEBT
    DEBT RATIO TO GDP.......
    2029 = 69,54%
    2028 = 69,34%
    2027 = 68,8%
    2026 = 68,17%
    2025 = 68,07%
    2024 = 68,38%
    2023 = 69,76%
    2022 = 65,5%
    2021 = 69,16%
    2020 = 67,69%
    BY STATISTA ......
    ================
    2025 $1.3 BILLION MINDEF =
    MAINTENANCE
    REPAIRS
    ASSETS.
    (LEASE, LEASE AND LEASE)
    -------------
    In 2025, Malonn Ministry of Defense (MINDEF) was allocated $4.8 billion to protect the country's sovereignty.
    This budget included $1.3 billion for maintenance, repairs, and new military assets..

    BalasHapus
  22. OPV 1 dan 2 JALAN TERUSSSS... 😎😎🇲🇾🇲🇾

    Menurut beliau, ini bagi menyiapkan pembinaan kedua-dua kapal yang mana status OPV 2 sudah 76% siap manakala OPV 3 pula 57%.

    Fasa seterusnya ialah mengenal pasti syarikat yang berkelayakan untuk dipertimbangkan bagi meneruskan projek berkenaan.

    “Terdapat 12 buah limbungan kapal telah mengemukakan cadangan (RFI) untuk meneruskan pembinaan 2 buah OPV tersebut.

    https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/

    BalasHapus
    Balasan
    1. DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      Tanda tanya mengenai status semasa pembinaan dua lagi kapal peronda luar pesisir (OPV) Agensi Penguatkuasa Maritim Malonn (APMM) terjawab selepas kerajaan menamatkan kontrak dengan THHE Destini Sdn Bhd (TDSB) setelah ia gagal menyiapkan projek berkenaan.
      Menteri Dalam Negeri Saifuddin Nasution Ismail berkata susulan penamatan yang ditandatangani pada 31 Disember lalu, syarikat itu dikenakan kadar denda dan ganti rugi ditetapkan (LAD) sebanyak RM12.49 juta [AS$2.82 juta] di atas kelewatan menyiapkan kapal OPV 2 dan OPV 3.
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      NGPVs 2024-1996 = 28 TAHUN
      28 TAHUN MANGKRAK
      28 TAHUN MANGKRAK
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT FINANCE HOUSE (Malonn) Bhd.

      Hapus
    2. DESEMBER 2024 OPV TAMAT
      DESEMBER 2024 OPV TAMAT
      DESEMBER 2024 OPV TAMAT
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam...
      -----
      LEASE FAST INTERCEPTOR BOAT
      LEASE UTILITY BOAT
      LEASE RIGID HULL FENDER BOAT
      LEASE ROVER FIBER GLASS
      LEASE EC120B
      LEASE FLIGHT SIMULATION TRAINING DEVICE
      Mungkin ada yang tertanya-tanya, namun kaedah penyewaan ini bukanlah kali pertama dilakukan. Kerajaan sebelum ini pernah menyewa Helikopter Latihan Airbus EC120B dan Flight Simulation Training Device (FSTD) Untuk Kegunaan Kursus Asas Juruterbang Helikopter TUDM.
      Selain itu, kerajaan turut pernah menyewa 5 unit Helikopter EC120B; 1 unit Sistem Simulator dan LEASEan Bot Op Pasir merangkumi 10 unit Fast Interceptor Boat (FIB); 10 unit Utility Boat; 10 unit Rigid Hull Fender Boat (RHFB); 10 unit Rover Fiber Glass (Rover).
      -----
      LEASE KAPAL HIDROLOGI
      LEASE KAPAL HIDROLOGI
      LEASE KAPAL HIDROLOGI
      Panglima TLDM Laksamana Tan Sri Ahmad Kamarulzaman Ahmad Badaruddin berkata Aishah Aims 4 diperoleh melalui kontrak LEASEan bagi menggantikan dua kapal hidrografi sedia ada milik TLDM iaitu KD Mutiara dan KD Perantau yang akan melalui proses lucut tauliah secara berperingkat.
      ===================
      LEASE VSHORAD
      LEASE TRUK CINA 3 TON
      Three weeks ago, the Madani government announced that it had struck a deal with China to lease 62 new train sets for KTM Bhd. The estimated cost for the deal is RM10.7 billion and it will be covered in installments over a 30-year lease period. The approved leasing deal for KTMB may tip the scale in favour of the truck and VSHORAD proposals.
      LEASE PESAWAT
      ITTC is currently providing Fighter Lead-In Training (FLIT) to the Royal Malonn Air Force in London, Ontario. ITTC operates a fleet of Aero Vodochody L-39 featuring upgraded avionics for the FLIT programme
      LEASE SIMULATOR MKM TAHUN
      Five-year contract for Sukhoi’s simulators. Publicly listed HeiTech Padu Bhd has announced that it had been awarded a RM67 million, five-year contract to operate and maintain the Su-30MKM flight simulators at the RMAF airbase in Gong Kedak
      LEASE HELI LEASE SIMULATOR
      Kerajaan sebelum ini pernah menyewa Helikopter Latihan Airbus EC120B dan Flight Simulation Training Device (FSTD) Untuk Kegunaan Kursus Asas Juruterbang Helikopter TUDM. Selain itu, kerajaan turut pernah menyewa 5 unit Helikopter EC120B; 1 unit Sistem Simulator
      LEASE HELI
      4 buah Helikopter Leonardo AW 139 yang diperolehi secara LEASEan ini adalah untuk kegunaan Tentera Udara Diraja Malon (TUDM) yang akan ditempatkan di NO.3 Skuadron, Pangkalan Udara Butterworth
      LEASE BOAT
      LEASEan Bot Op Pasir merangkumi 10 unit Fast Interceptor Boat (FIB); 10 unit Utility Boat; 10 unit Rigid Hull Fender Boat (RHFB); 10 unit Rover Fiber Glass (Rover).
      LEASE HIDROGRAFI
      tugas pemetaan data batimetri bagi kawasan perairan negara akan dilakukan oleh sebuah kapal hidrografi moden, MV Aishah AIM 4, yang diperoleh menerusi kontrak LEASEan dari syarikat Breitlink Engineering Services Sdn Bhd (BESSB)
      LEASE 4x4
      Pejabat perusahaan mengatakan kepada Janes di pameran bahwa Angkatan Bersenjata Malon sedang mencari untuk menyewa Tarantula
      LEASE MOTOR
      The Royal Military Police Corp (KPTD) celebrated the lease of 40 brand-new BMW R1250RT Superbikes for the Enforcement Motorcycle Squad on December 22nd, 2022
      LEASE PATROL BOATS : LEASE OUTBOARD MOTORS : LEASE TRAILERS
      Meanwhile, the division also published a tender for eleven glass reinforced plastic patrol boats together outboard motors, trailers and associated equipment. The tender was published on February 28 and closes on March 29. The estimated cost of the tender is RM4.6 million..
      LEASE 28 HELI
      The government signed an agreement with Weststar Aviation Sdn Bhd to lease 28 helicopters for use by ministries and other government agencies

      Hapus
    3. DESEMBER 2024 OPV TAMAT
      DESEMBER 2024 OPV TAMAT
      DESEMBER 2024 OPV TAMAT
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam..
      -----
      OPV 2025-2017 = 9 TAHUN
      9 TAHUN MANGKRAK
      9 TAHUN MANGKRAK
      OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up NOtice dated Sept 13.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      ==================
      ==================
      1. real contract and delivery five units C130J Hercules
      2. real contract and delivery two unit Frankethal class Countermine vessels (Pulau Fani class)
      3. real contract and delivery four units KCR 60 Fast missiles boats PT PAL
      4. real contract and delivery 9 units Bell 412 EPI
      5. real contract and delivery 8 additional H225 M
      6. real contract and delivery 2 units Bell 429 Global Ranger
      7. real contract and delivery 18 Medium weight tank Harimau
      8. real contract and delivery 22 Pandur II IFV
      9. real contract and delivery two unit Hospital Ships
      10. real contract and delivery one unit Command and control variant C295
      11. real contract and delivery one unit CN235 MPA
      12. real contract and delivery 7 Badak FSV, 26 ANOa apc and 10 additional Komodo recce vehicles in 2022
      13. real contract and delivery 4 AS 550 Fennec and 8 AS565 MBE, in 2024
      14. real contract and delivery five NC212i in 2023
      15. real contract and delivery one Leonardo RAT 31 DL/M
      16. real contract and delivery five C130H ordered from Australia in 2013 (finished in 2020) after received Grant of 4 C130H
      17. real contract and delivery 9 Teluk Bintuni class LST
      18. real contract and delivery six CH4B UCAV ordered in 2019
      19. real contract t and process building of Abeking & Rasmussen design ocean Hydrography ship
      20. real contract and process building two AH140 AAW Frigate
      21. real contract and process building two OPV 90 ASW patrol vessels
      22. real contract and process building 42 Dassault Rafale F4 fighter
      23. real contract and process building two A400M heavy cargo aircraft
      24. real contract and delivery M3 Amphibious bridging system
      25. real contract and delivery 3 KT1 Wong Bee ordered in 2018 along with radar and spares for T/A50
      26. real contract and process building 13 GM 403 GCI radar from Thales
      27. real contract and process building 12 ANKA S UCAV
      28. real contract and process building additional CH4B UCAV
      29. real contract and delivery Slingshot Satcom system
      30. real contract and delivery Falcon 8X aircraft
      31. real contract and process Thales Alenia earth observation satelite
      32. real contract and process 22 S70M Blackhawk
      33. real contract and process 6 N219 aircraft
      34. real contract and process 3 CN235 for Army
      35. real contract and process 2 PPA patrol Frigate
      36. real contract and process 2 Scorpene Subs
      37. real contract and process Khan Short Range ballistic missiles from Turki
      38. real contract and process Trisula Air defense system
      39. real contract and process 6 T50i aircraft
      40. real contract and delivery Oiler and replenishment ship
      41. real contract and delivery several Tug Harbor ships
      42. real contract and process Submarine rescue vessels and system
      43. real contract and delivery two Large LCU for army
      44. real contract and process 45 Atmaca

      Hapus
    4. Gagal terus sampai muntaber : Mundur teratur tanpa berita. Kasihan bikin malu.

      Hapus
  23. DESEMBER 2024 OPV 2 dan 3 = TAMAT
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    Tanda tanya mengenai status semasa pembinaan dua lagi kapal peronda luar pesisir (OPV) Agensi Penguatkuasa Maritim Malonn (APMM) terjawab selepas kerajaan menamatkan kontrak dengan THHE Destini Sdn Bhd (TDSB) setelah ia gagal menyiapkan projek berkenaan.
    Menteri Dalam Negeri Saifuddin Nasution Ismail berkata susulan penamatan yang ditandatangani pada 31 Disember lalu, syarikat itu dikenakan kadar denda dan ganti rugi ditetapkan (LAD) sebanyak RM12.49 juta [AS$2.82 juta] di atas kelewatan menyiapkan kapal OPV 2 dan OPV 3.
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
    -----
    LCS 2025-2011 = 15 TAHUN
    15 TAHUN MANGKRAK
    15 TAHUN MANGKRAK
    LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
    -----
    2029-2020 : 10 YEARS = OVERLIMIT DEBT
    2029-2020 : 10 YEARS = OVERLIMIT DEBT
    DEBT RATIO TO GDP.......
    2029 = 69,54%
    2028 = 69,34%
    2027 = 68,8%
    2026 = 68,17%
    2025 = 68,07%
    2024 = 68,38%
    2023 = 69,76%
    2022 = 65,5%
    2021 = 69,16%
    2020 = 67,69%
    BY STATISTA ......
    ================
    2025 $1.3 BILLION MINDEF =
    MAINTENANCE
    REPAIRS
    ASSETS.
    (LEASE, LEASE AND LEASE)
    -------------
    In 2025, Malonn Ministry of Defense (MINDEF) was allocated $4.8 billion to protect the country's sovereignty.
    This budget included $1.3 billion for maintenance, repairs, and new military assets..

    BalasHapus
  24. DESEMBER 2024 OPV TAMAT
    DESEMBER 2024 OPV TAMAT
    DESEMBER 2024 OPV TAMAT
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    -----
    OPV 2025-2017 = 9 TAHUN
    9 TAHUN MANGKRAK
    9 TAHUN MANGKRAK
    OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up NOtice dated Sept 13.
    -----
    LCS 2025-2011 = 15 TAHUN
    15 TAHUN MANGKRAK
    15 TAHUN MANGKRAK
    LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
    -----
    NGPVs 2024-1996 = 28 TAHUN
    28 TAHUN MANGKRAK
    28 TAHUN MANGKRAK
    NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
    -----
    NGPVs BAYAR HUTANG LCS = seperti didedahkan Jawatankuasa Kira-kira Wang Negara (PAC) dan CEO LTAT, syarikat BNS menggunakan RM400 juta daripada bayaran pendahuluan bagi projek LCS untuk menjelaskan hutang lapuk bagi projek NGPV," syarikat PSC-Naval Dockyard pada Disember 2005 sebelum dijenamakan semula menjadi syarikat Boustead Naval Dockyard Sdn Bhd
    -----
    17 KREDITUR LCS
    17 KREDITUR LCS
    17 KREDITUR LCS
    Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT FINANCE HOUSE (Malonn) Bhd.
    ===================
    The Malonnn Armed Forces (MAF) has faced challenges in modernizing its missile capabilities due to budgetary constraints, political interference, and a lack of modern assets.
    Budgetary constraints
    • The 1997 Asian financial crisis limited the MAF's ability to procure new weapons.
    • Malonn's defense budget is limited, which can affect the pace of acquisitions and upgrades.
    Political interference
    • Political leaders have been accused of interfering in procurement.
    Lack of modern assets
    • The MAF has aging military assets, including most of the navy's fleet and helicopters commissioned in the 1960s.
    • The MAF has experienced issues with the maintenance and spare parts for its aircraft.
    Other challenges the MAF has faced include: Poor planning, Personnel issues, and Critical problems with the PT-91M main battle tank.

    BalasHapus
  25. 2029-2020 : 10 YEARS = OVERLIMIT DEBT
    2029-2020 : 10 YEARS = OVERLIMIT DEBT
    DEBT RATIO TO GDP.......
    2029 = 69,54%
    2028 = 69,34%
    2027 = 68,8%
    2026 = 68,17%
    2025 = 68,07%
    2024 = 68,38%
    2023 = 69,76%
    2022 = 65,5%
    2021 = 69,16%
    2020 = 67,69%
    BY STATISTA ......
    -------------
    2025 $1.3 BILLION MINDEF =
    MAINTENANCE
    REPAIRS
    ASSETS.
    (LEASE, LEASE AND LEASE)
    -------------
    In 2025, Malonn Ministry of Defense (MINDEF) was allocated $4.8 billion to protect the country's sovereignty.
    This budget included $1.3 billion for maintenance, repairs, and new military assets..
    -------------
    2024 RASIO HUTANG 84,2% DARI GDP
    HUTANG 2023 = RM 1.53 TRILLION
    HUTANG 2022 = RM 1.45 TRILLION
    HUTANG 2021 = RM 1.38 TRILLION
    HUTANG 2020 = RM 1.32 TRILLIONd
    HUTANG 2019 = RM 1.25 TRILLION
    HUTANG 2018 = RM 1.19 TRILLION
    The Finance Ministry stated that the aggregate national household debt stood at RM1.53 trillion between 2018 and 2023. In aggregate, it said the household debt for 2022 was RM1.45 trillion, followed by RM1.38 trillion (2021,) RM1.32 trillion (2020), RM1.25 trillion (2019) and RM1.19 trillion (2018). “The ratio of household debt to gross domestic product (GDP) at the end of 2023 also slightly increased to 84.2% compared with 82% in 2018,” it said.
    ==================
    ==================
    1. real contract and delivery five units C130J Hercules
    2. real contract and delivery two unit Frankethal class Countermine vessels (Pulau Fani class)
    3. real contract and delivery four units KCR 60 Fast missiles boats PT PAL
    4. real contract and delivery 9 units Bell 412 EPI
    5. real contract and delivery 8 additional H225 M
    6. real contract and delivery 2 units Bell 429 Global Ranger
    7. real contract and delivery 18 Medium weight tank Harimau
    8. real contract and delivery 22 Pandur II IFV
    9. real contract and delivery two unit Hospital Ships
    10. real contract and delivery one unit Command and control variant C295
    11. real contract and delivery one unit CN235 MPA
    12. real contract and delivery 7 Badak FSV, 26 ANOa apc and 10 additional Komodo recce vehicles in 2022
    13. real contract and delivery 4 AS 550 Fennec and 8 AS565 MBE, in 2024
    14. real contract and delivery five NC212i in 2023
    15. real contract and delivery one Leonardo RAT 31 DL/M
    16. real contract and delivery five C130H ordered from Australia in 2013 (finished in 2020) after received Grant of 4 C130H
    17. real contract and delivery 9 Teluk Bintuni class LST
    18. real contract and delivery six CH4B UCAV ordered in 2019
    19. real contract t and process building of Abeking & Rasmussen design ocean Hydrography ship
    20. real contract and process building two AH140 AAW Frigate
    21. real contract and process building two OPV 90 ASW patrol vessels
    22. real contract and process building 42 Dassault Rafale F4 fighter
    23. real contract and process building two A400M heavy cargo aircraft
    24. real contract and delivery M3 Amphibious bridging system
    25. real contract and delivery 3 KT1 Wong Bee ordered in 2018 along with radar and spares for T/A50
    26. real contract and process building 13 GM 403 GCI radar from Thales
    27. real contract and process building 12 ANKA S UCAV
    28. real contract and process building additional CH4B UCAV
    29. real contract and delivery Slingshot Satcom system
    30. real contract and delivery Falcon 8X aircraft
    31. real contract and process Thales Alenia earth observation satelite
    32. real contract and process 22 S70M Blackhawk
    33. real contract and process 6 N219 aircraft
    34. real contract and process 3 CN235 for Army
    35. real contract and process 2 PPA patrol Frigate
    36. real contract and process 2 Scorpene Subs
    37. real contract and process Khan Short Range ballistic missiles from Turki
    38. real contract and process Trisula Air defense system
    39. real contract and process 6 T50i aircraft
    40. real contract and delivery Oiler and replenishment ship
    41. real contract and delivery several Tug Harbor ships
    42. real contract and process Submarine rescue vessels and system
    43. real contract and delivery two Large LCU for army
    44. real contract and process 45 Atmaca

    BalasHapus
  26. DESEMBER 2024 OPV 2 dan 3 = TAMAT
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    ---
    KONTRAK 2017
    TH Heavy Engineering Berhad (THHE) and Destini Berhad (Destini) announced today that they have secured a contract worth RM738.9 million (inclusive of 6% GST) for the supply, delivery, testing and commissioning of three units of Offshore Patrol Vessels (OPV) for the Malonn Maritime Enforcement Agency (MMEA)
    ---
    DIJANGKA 2020
    Kontrak Damen 1800 OPV diberikan kepada perusahaan lokal THHE-Destini pada awal tahun 2017. Kontrak kapal bernilai RM738,9 juta dan konstruksi dimulai pada Desember 2017. Kapal pertama akan selesai pada pertengahan tahun 2020
    --
    MIRING KABEL PUTUS
    THHE general manager Azizul Hanafee Zain explained that the ship tilted to one side after one of the steel cables attached to the supporting structure underneath the ship was cut.
    ---
    DISUNTIK HUTANG
    government is injecting RM152.6 million to ensure that the first Offshore Patrol Vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA)
    ---
    OPV DIAMBIL MOF 2023
    The government will inject RM152.6 million to ensure that the first offshore patrol vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA) will be completed this year, Prime Minister Anwar Ibrahim said today.
    He said the finance ministry (MoF) had taken over the OPV project from Tabung Haji (TH) subsidiary, Destini Sdn Bhd, after it was found to be facing major problems.
    ---
    THHE BANGKRUT 2023 = THHE TUTUP
    Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
    The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.

    BalasHapus
  27. Seharusnya 3 diserah 2020, ....ya ampun ini 2025 guys...

    🤣🤣😂😂😂😂😂

    ====
    "...Kerajaan memeterai kontrak perolehan tiga OPV bernilai RM738.9 juta [AS$166.82 juta] dengan TDSB pada Januari 2017 dan projek tersebut sepatutnya siap sepenuhnya pada Julai 2020..."

    BalasHapus
  28. OPV damen miring 2 & 3 RESMI
    ⛔️TAMAT⛔️ warganyet kecewa
    NGAMUK🔥LAGI haha!🤣🤣🤣

    BalasHapus
  29. OPV 1 dan 2 JALAN TERUSSSS... Baca ya.... 😎😎🇲🇾🇲🇾

    Menurut beliau, ini bagi menyiapkan pembinaan kedua-dua kapal yang mana status OPV 2 sudah 76% siap manakala OPV 3 pula 57%.

    Fasa seterusnya ialah mengenal pasti syarikat yang berkelayakan untuk dipertimbangkan bagi meneruskan projek berkenaan.

    “Terdapat 12 buah limbungan kapal telah mengemukakan cadangan (RFI) untuk meneruskan pembinaan 2 buah OPV tersebut.

    https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/

    BalasHapus
    Balasan
    1. BERUK HANTAR BERITA NOVEMBER 2024
      OPV 2 DAN OPV 3 = TAMAT DESEMBER 2024
      -------------
      BERUKWARIA 11 Februari 2025 pukul 11.28
      OPV 1 dan 2 JALAN TERUSSSS... 😎😎🇲🇾🇲🇾
      tps://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/
      -------------
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      ---
      KONTRAK 2017
      TH Heavy Engineering Berhad (THHE) and Destini Berhad (Destini) announced today that they have secured a contract worth RM738.9 million (inclusive of 6% GST) for the supply, delivery, testing and commissioning of three units of Offshore Patrol Vessels (OPV) for the Malonn Maritime Enforcement Agency (MMEA)
      ---
      DIJANGKA 2020
      Kontrak Damen 1800 OPV diberikan kepada perusahaan lokal THHE-Destini pada awal tahun 2017. Kontrak kapal bernilai RM738,9 juta dan konstruksi dimulai pada Desember 2017. Kapal pertama akan selesai pada pertengahan tahun 2020
      --
      MIRING KABEL PUTUS
      THHE general manager Azizul Hanafee Zain explained that the ship tilted to one side after one of the steel cables attached to the supporting structure underneath the ship was cut.
      ---
      DISUNTIK HUTANG
      government is injecting RM152.6 million to ensure that the first Offshore Patrol Vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA)
      ---
      OPV DIAMBIL MOF 2023
      The government will inject RM152.6 million to ensure that the first offshore patrol vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA) will be completed this year, Prime Minister Anwar Ibrahim said today.
      He said the finance ministry (MoF) had taken over the OPV project from Tabung Haji (TH) subsidiary, Destini Sdn Bhd, after it was found to be facing major problems.
      ---
      THHE BANGKRUT 2023 = THHE TUTUP
      Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
      The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.

      Hapus
    2. BERUK HANTAR BERITA NOVEMBER 2024
      OPV 2 DAN OPV 3 = TAMAT DESEMBER 2024
      -------------
      BERUKWARIA 11 Februari 2025 pukul 11.28
      OPV 1 dan 2 JALAN TERUSSSS... 😎😎🇲🇾🇲🇾
      tps://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/
      -------------
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      ---
      KONTRAK 2017
      TH Heavy Engineering Berhad (THHE) and Destini Berhad (Destini) announced today that they have secured a contract worth RM738.9 million (inclusive of 6% GST) for the supply, delivery, testing and commissioning of three units of Offshore Patrol Vessels (OPV) for the Malonn Maritime Enforcement Agency (MMEA)
      ---
      DIJANGKA 2020
      Kontrak Damen 1800 OPV diberikan kepada perusahaan lokal THHE-Destini pada awal tahun 2017. Kontrak kapal bernilai RM738,9 juta dan konstruksi dimulai pada Desember 2017. Kapal pertama akan selesai pada pertengahan tahun 2020
      --
      MIRING KABEL PUTUS
      THHE general manager Azizul Hanafee Zain explained that the ship tilted to one side after one of the steel cables attached to the supporting structure underneath the ship was cut.
      ---
      DISUNTIK HUTANG
      government is injecting RM152.6 million to ensure that the first Offshore Patrol Vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA)
      ---
      OPV DIAMBIL MOF 2023
      The government will inject RM152.6 million to ensure that the first offshore patrol vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA) will be completed this year, Prime Minister Anwar Ibrahim said today.
      He said the finance ministry (MoF) had taken over the OPV project from Tabung Haji (TH) subsidiary, Destini Sdn Bhd, after it was found to be facing major problems.
      ---
      THHE BANGKRUT 2023 = THHE TUTUP
      Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
      The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.

      Hapus
    3. BERUK HANTAR BERITA NOVEMBER 2024
      OPV 2 DAN OPV 3 = TAMAT DESEMBER 2024
      -------------
      BERUKWARIA 11 Februari 2025 pukul 11.28
      OPV 1 dan 2 JALAN TERUSSSS... 😎😎🇲🇾🇲🇾
      tps://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/
      -------------
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      ---
      KONTRAK 2017
      TH Heavy Engineering Berhad (THHE) and Destini Berhad (Destini) announced today that they have secured a contract worth RM738.9 million (inclusive of 6% GST) for the supply, delivery, testing and commissioning of three units of Offshore Patrol Vessels (OPV) for the Malonn Maritime Enforcement Agency (MMEA)
      ---
      DIJANGKA 2020
      Kontrak Damen 1800 OPV diberikan kepada perusahaan lokal THHE-Destini pada awal tahun 2017. Kontrak kapal bernilai RM738,9 juta dan konstruksi dimulai pada Desember 2017. Kapal pertama akan selesai pada pertengahan tahun 2020
      --
      MIRING KABEL PUTUS
      THHE general manager Azizul Hanafee Zain explained that the ship tilted to one side after one of the steel cables attached to the supporting structure underneath the ship was cut.
      ---
      DISUNTIK HUTANG
      government is injecting RM152.6 million to ensure that the first Offshore Patrol Vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA)
      ---
      OPV DIAMBIL MOF 2023
      The government will inject RM152.6 million to ensure that the first offshore patrol vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA) will be completed this year, Prime Minister Anwar Ibrahim said today.
      He said the finance ministry (MoF) had taken over the OPV project from Tabung Haji (TH) subsidiary, Destini Sdn Bhd, after it was found to be facing major problems.
      ---
      THHE BANGKRUT 2023 = THHE TUTUP
      Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
      The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.

      Hapus
    4. SHARE BERITA NOVEMVER
      OPV TAMAT DESEMBER 2024 =
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      -------------------
      BERUK WARIA 9 Februari 2025 pukul 21.38
      OPV TAMAT...? SORRY ya GORILLA.. 🤣🤣🤣

      Projek 2 kapal OPV APMM yang tertangguh akan disambung semula

      https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/
      -------------------
      GOODBYE = 2025 OPV TAMAT
      GOODBYE = 2025 OPV TAMAT
      GOODBYE = 2025 OPV TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      NGPVs 2024-1996 = 28 TAHUN
      28 TAHUN MANGKRAK
      28 TAHUN MANGKRAK
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT FINANCE HOUSE (Malonn) Bhd.

      Hapus
    5. Lebih baik GAGAL dari pada OPV jalanya miring bual begitu Pork?

      Hapus
    6. MKM = PALM OIL
      MKM = PALM OIL
      Malonn has used palm oil to barter for military equipment, including fighter jets. The Malonnn Armed Forces (MAF) is made up of the Royal Malonnn Navy, the Royal Malonnn Air Force, and the Malonnn Army.
      Explanation
      • In 2003, Malonn purchased 18 Flankers from Russia in exchange for palm oil.
      • In 2018, the defense minister revealed that only four of Malonn's 28 Russian jet fighters could fly.
      • The MiG-29N was decommissioned in 2017 due to high maintenance costs.
      The MAF has also used privately funded sea bases to improve response time to threats. For example, Petronas, a Malonnn oil company, donated a decommissioned oil rig to the Royal Malonnn Navy. The rig was converted into a fixed sea base that can launch helicopters and boats.
      ==============
      The Malonnn Armed Forces (MAF) has faced issues with its vessels, including logistics, outdated inventory, and sinking ships. The MAF has also been involved in maritime disputes with China.
      Issues
      Logistics
      There have been studies and writings about the quality of MAF logistics equipment, but there is a lack of information about the government's policy and stand on developing it.
      Outdated inventory
      Outdated inventory can be a stumbling block in operations, especially in hostile environments.
      Sinking ships
      The sinking of an old Malonnn navy vessel has raised questions about defense spending.
      Maritime disputes
      Malonn has faced maritime disputes with China, including Chinese vessels encroaching into Malonnn waters.

      Hapus
  30. Seharusnya 3 diserah 2020, ....ya ampun ini 2025 guys...

    🤣🤣😂😂😂😂😂

    TOLOL....apalagi

    BalasHapus
  31. BERUK HANTAR BERITA NOVEMBER 2024
    OPV 2 DAN OPV 3 = TAMAT DESEMBER 2024
    -------------
    BERUKWARIA 11 Februari 2025 pukul 11.28
    OPV 1 dan 2 JALAN TERUSSSS... 😎😎🇲🇾🇲🇾
    tps://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/
    -------------
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    ---
    KONTRAK 2017
    TH Heavy Engineering Berhad (THHE) and Destini Berhad (Destini) announced today that they have secured a contract worth RM738.9 million (inclusive of 6% GST) for the supply, delivery, testing and commissioning of three units of Offshore Patrol Vessels (OPV) for the Malonn Maritime Enforcement Agency (MMEA)
    ---
    DIJANGKA 2020
    Kontrak Damen 1800 OPV diberikan kepada perusahaan lokal THHE-Destini pada awal tahun 2017. Kontrak kapal bernilai RM738,9 juta dan konstruksi dimulai pada Desember 2017. Kapal pertama akan selesai pada pertengahan tahun 2020
    --
    MIRING KABEL PUTUS
    THHE general manager Azizul Hanafee Zain explained that the ship tilted to one side after one of the steel cables attached to the supporting structure underneath the ship was cut.
    ---
    DISUNTIK HUTANG
    government is injecting RM152.6 million to ensure that the first Offshore Patrol Vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA)
    ---
    OPV DIAMBIL MOF 2023
    The government will inject RM152.6 million to ensure that the first offshore patrol vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA) will be completed this year, Prime Minister Anwar Ibrahim said today.
    He said the finance ministry (MoF) had taken over the OPV project from Tabung Haji (TH) subsidiary, Destini Sdn Bhd, after it was found to be facing major problems.
    ---
    THHE BANGKRUT 2023 = THHE TUTUP
    Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
    The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.

    BalasHapus
  32. BERUK HANTAR BERITA NOVEMBER 2024
    OPV 2 DAN OPV 3 = TAMAT DESEMBER 2024
    -------------
    BERUKWARIA 11 Februari 2025 pukul 11.28
    OPV 1 dan 2 JALAN TERUSSSS... 😎😎🇲🇾🇲🇾
    tps://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/
    -------------
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    ---
    KONTRAK 2017
    TH Heavy Engineering Berhad (THHE) and Destini Berhad (Destini) announced today that they have secured a contract worth RM738.9 million (inclusive of 6% GST) for the supply, delivery, testing and commissioning of three units of Offshore Patrol Vessels (OPV) for the Malonn Maritime Enforcement Agency (MMEA)
    ---
    DIJANGKA 2020
    Kontrak Damen 1800 OPV diberikan kepada perusahaan lokal THHE-Destini pada awal tahun 2017. Kontrak kapal bernilai RM738,9 juta dan konstruksi dimulai pada Desember 2017. Kapal pertama akan selesai pada pertengahan tahun 2020
    --
    MIRING KABEL PUTUS
    THHE general manager Azizul Hanafee Zain explained that the ship tilted to one side after one of the steel cables attached to the supporting structure underneath the ship was cut.
    ---
    DISUNTIK HUTANG
    government is injecting RM152.6 million to ensure that the first Offshore Patrol Vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA)
    ---
    OPV DIAMBIL MOF 2023
    The government will inject RM152.6 million to ensure that the first offshore patrol vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA) will be completed this year, Prime Minister Anwar Ibrahim said today.
    He said the finance ministry (MoF) had taken over the OPV project from Tabung Haji (TH) subsidiary, Destini Sdn Bhd, after it was found to be facing major problems.
    ---
    THHE BANGKRUT 2023 = THHE TUTUP
    Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
    The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.

    BalasHapus
  33. HAHAHAHA.... SALAH POTONG GAGAL TOTAL....😂😂😂😂😂


    MEMALUKAN... HAHAHAHAHA

    BalasHapus
  34. OPV 1 dan 2 JALAN TERUSSSS... Baca ya.... 😎😎🇲🇾🇲🇾

    Menurut beliau, ini bagi menyiapkan pembinaan kedua-dua kapal yang mana status OPV 2 sudah 76% siap manakala OPV 3 pula 57%.

    Fasa seterusnya ialah mengenal pasti syarikat yang berkelayakan untuk dipertimbangkan bagi meneruskan projek berkenaan.

    “Terdapat 12 buah limbungan kapal telah mengemukakan cadangan (RFI) untuk meneruskan pembinaan 2 buah OPV tersebut.

    https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/

    BalasHapus
    Balasan
    1. SHARE BERITA NOVEMVER
      OPV TAMAT DESEMBER 2024 =
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      -------------------
      BERUK WARIA 9 Februari 2025 pukul 21.38
      OPV TAMAT...? SORRY ya GORILLA.. 🤣🤣🤣

      Projek 2 kapal OPV APMM yang tertangguh akan disambung semula

      https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/
      -------------------
      GOODBYE = 2025 OPV TAMAT
      GOODBYE = 2025 OPV TAMAT
      GOODBYE = 2025 OPV TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      NGPVs 2024-1996 = 28 TAHUN
      28 TAHUN MANGKRAK
      28 TAHUN MANGKRAK
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
      =======
      KEYWORDS
      OPV TAMAT
      LCS NEXT TAMAT

      Hapus
    2. SHARE BERITA NOVEMVER
      OPV TAMAT DESEMBER 2024 =
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      -------------------
      BERUK WARIA 9 Februari 2025 pukul 21.38
      OPV TAMAT...? SORRY ya GORILLA.. 🤣🤣🤣

      Projek 2 kapal OPV APMM yang tertangguh akan disambung semula

      https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/
      -------------------
      GOODBYE = 2025 OPV TAMAT
      GOODBYE = 2025 OPV TAMAT
      GOODBYE = 2025 OPV TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      NGPVs 2024-1996 = 28 TAHUN
      28 TAHUN MANGKRAK
      28 TAHUN MANGKRAK
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
      =======
      KEYWORDS
      OPV TAMAT
      LCS NEXT TAMAT

      Hapus
    3. 2029-2020 : 10 YEARS = OVERLIMIT DEBT
      2029-2020 : 10 YEARS = OVERLIMIT DEBT
      DEBT RATIO TO GDP.......
      2029 = 69,54%
      2028 = 69,34%
      2027 = 68,8%
      2026 = 68,17%
      2025 = 68,07%
      2024 = 68,38%
      2023 = 69,76%
      2022 = 65,5%
      2021 = 69,16%
      2020 = 67,69%
      BY STATISTA ......
      ================
      LEASE HONDA CIVIC
      LEASE 40 BMW SUPERBIKES
      Leased BMW superbikes for military police. The Army’s military police – Kor Polis Tentera Di Raja – took delivery of 40 BMW R1250RT super bikes today. The superbikes are under lease from Syarikat Ammo Defence Sdn Bhd under a RM13.7 million Letter of Award.
      As for leasing vehicles, this has been common practise by government departments for the decade or so as it is supposed to be cheaper overall. The MPs had also taken delivery of Honda Civics under a leasing programme,
      -----
      LEASE FAST INTERCEPTOR BOAT
      LEASE UTILITY BOAT
      LEASE RIGID HULL FENDER BOAT
      LEASE ROVER FIBER GLASS
      LEASE EC120B
      LEASE FLIGHT SIMULATION TRAINING DEVICE
      Mungkin ada yang tertanya-tanya, namun kaedah penyewaan ini bukanlah kali pertama dilakukan. Kerajaan sebelum ini pernah menyewa Helikopter Latihan Airbus EC120B dan Flight Simulation Training Device (FSTD) Untuk Kegunaan Kursus Asas Juruterbang Helikopter TUDM.
      Selain itu, kerajaan turut pernah menyewa 5 unit Helikopter EC120B; 1 unit Sistem Simulator dan LEASEan Bot Op Pasir merangkumi 10 unit Fast Interceptor Boat (FIB); 10 unit Utility Boat; 10 unit Rigid Hull Fender Boat (RHFB); 10 unit Rover Fiber Glass (Rover).
      -----
      LEASE KAPAL HIDROLOGI
      LEASE KAPAL HIDROLOGI
      LEASE KAPAL HIDROLOGI
      Panglima TLDM Laksamana Tan Sri Ahmad Kamarulzaman Ahmad Badaruddin berkata Aishah Aims 4 diperoleh melalui kontrak LEASEan bagi menggantikan dua kapal hidrografi sedia ada milik TLDM iaitu KD Mutiara dan KD Perantau yang akan melalui proses lucut tauliah secara berperingkat.
      ===================
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT FINANCE HOUSE (Malonn) Bhd.

      Hapus
    4. Goblok masih bual dan gak punya malu yah?

      Hapus
  35. GOODBYE 2024 OPV 2 DAN 3 = TAMAT
    GOODBYE 2024 OPV 2 DAN 3 = TAMAT
    GOODBYE 2024 OPV 2 DAN 3 = TAMAT
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
    ============
    GOODBYE 2023 THHE DELISTED = BURSA MALONN
    GOODBYE 2023 THHE DELISTED = BURSA MALONN
    GOODBYE 2023 THHE DELISTED = BURSA MALONN
    Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
    The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
    The winding-up notice also stated that a meeting of creditors is scheduled for Oct 4 at 3pm.
    THHE is controlled by the Ministry of Finance-owned (MoF) unit Urusharta Jamaah Sdn Bhd, which holds a 64.45% stake in the company prior to its delisting on Sept 5, 2022
    TH Heavy was delisted from Bursa Malonn in September 2022, after failing to come up with a restructuring exercise despite being given eight extensions by the exchange since first entering Practice Note 17 status in April 2018.
    The decision to wind up came after THHE filed an ex-parte originating summons in July to call for a creditors’ meeting to propose a scheme of arrangement for the company.
    Global Mariner Offshore Services, Blackstone Technology Sdn Bhd and Dynac Sdn Bhd have reportedly filed applications to intervene in THHE’s ex-parte application.
    THHE had a joint venture partnership with Global Mariner, but a legal dispute arose between the two companies. The High Court ordered THHE to pay Global Mariner approximately RM288.72 million in damages.
    =======
    KEYWORDS
    OPV TAMAT
    LCS NEXT TAMAT

    BalasHapus
  36. Kasihan MALAYDESH... 😂😂😂😂

    Jadi Kapal OPV 1 KM Tun Fatimah yang SALAH POTONG dan JALAN MIRING di paksakan untuk di terima yang ternyata produk GAGAL dan KUALITAS RENDAH....

    Sehingga kapal OPV 2 dan OPV 3 yang produk RENDAHAN pun GAGAL TOTAL dan TENGGELAM ke ALAM GHOIB... Hahahahahaha😂😂😂😂😂


    MEMALUKAN dan MENYEDIHKAN...hahahahahaha

    BalasHapus
  37. Kasihan MALAYDESH... 😂😂😂😂

    Jadi Kapal OPV 1 KM Tun Fatimah yang SALAH POTONG dan JALAN MIRING di paksakan untuk di terima yang ternyata produk GAGAL dan KUALITAS RENDAH....

    Sehingga kapal OPV 2 dan OPV 3 yang produk RENDAHAN pun GAGAL TOTAL dan TENGGELAM ke ALAM GHOIB... Hahahahahaha😂😂😂😂😂


    MEMALUKAN dan MENYEDIHKAN...hahahahahaha

    BalasHapus
  38. SHARE BERITA NOVEMVER
    OPV TAMAT DESEMBER 2024 =
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    -------------------
    BERUK WARIA 9 Februari 2025 pukul 21.38
    OPV TAMAT...? SORRY ya GORILLA.. 🤣🤣🤣

    Projek 2 kapal OPV APMM yang tertangguh akan disambung semula

    https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/
    -------------------
    GOODBYE = 2025 OPV TAMAT
    GOODBYE = 2025 OPV TAMAT
    GOODBYE = 2025 OPV TAMAT
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
    -----
    LCS 2025-2011 = 15 TAHUN
    15 TAHUN MANGKRAK
    15 TAHUN MANGKRAK
    LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
    -----
    NGPVs 2024-1996 = 28 TAHUN
    28 TAHUN MANGKRAK
    28 TAHUN MANGKRAK
    NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
    -----
    17 KREDITUR LCS
    17 KREDITUR LCS
    17 KREDITUR LCS
    Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
    =======
    KEYWORDS
    OPV TAMAT
    LCS NEXT TAMAT

    BalasHapus
  39. Kasihan MALAYDESH... 😂😂😂😂

    Jadi Kapal OPV 1 KM Tun Fatimah yang SALAH POTONG dan JALAN MIRING di paksakan untuk di terima yang ternyata produk GAGAL dan KUALITAS RENDAH....

    Sehingga kapal OPV 2 dan OPV 3 yang produk RENDAHAN pun GAGAL TOTAL dan TENGGELAM ke ALAM GHOIB... Hahahahahaha😂😂😂😂😂


    MEMALUKAN dan MENYEDIHKAN...hahahahahaha

    BalasHapus
  40. Hahahahah.... SALAH POTONG jalan terus hingga GAGAL TOTAL...


    Hahahahahaha....😂😂😂😂😂😂

    BalasHapus
  41. Pembinaan 2 kapal OPV APMM akan disambung, 12 limbungan tawar siapkan projek

    https://www.dagangnews.com/index.php/article/terkini/pembinaan-2-kapal-opv-apmm-akan-disambung-12-limbungan-tawar-siapkan-projek-44854

    BalasHapus
    Balasan
    1. 2029-2020 : 10 YEARS = OVERLIMIT DEBT
      2029-2020 : 10 YEARS = OVERLIMIT DEBT
      DEBT RATIO TO GDP.......
      2029 = 69,54%
      2028 = 69,34%
      2027 = 68,8%
      2026 = 68,17%
      2025 = 68,07%
      2024 = 68,38%
      2023 = 69,76%
      2022 = 65,5%
      2021 = 69,16%
      2020 = 67,69%
      BY STATISTA ......
      ================
      OPV 2 DAN OPV 3 TAMAT = DESEMBER 2024
      OPV 2 DAN OPV 3 TAMAT = DESEMBER 2024
      OPV 2 DAN OPV 3 TAMAT = DESEMBER 2024
      Menteri Dalam Negeri Saifuddin Nasution Ismail berkata susulan penamatan yang ditandatangani pada 31 Disember lalu, syarikat itu dikenakan kadar denda dan ganti rugi ditetapkan (LAD) sebanyak RM12.49 juta [AS$2.82 juta] di atas kelewatan menyiapkan kapal OPV 2 dan OPV 3.
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      NGPVs 2024-1996 = 28 TAHUN
      28 TAHUN MANGKRAK
      28 TAHUN MANGKRAK
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
      =======
      KEYWORDS
      OPV TAMAT
      LCS NEXT TAMAT

      Hapus
    2. SHARE BERITA NOVEMVER
      OPV TAMAT DESEMBER 2024 =
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      -------------------
      BERUK WARIA 9 Februari 2025 pukul 21.38
      OPV TAMAT...? SORRY ya GORILLA.. 🤣🤣🤣

      Projek 2 kapal OPV APMM yang tertangguh akan disambung semula

      https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/
      -------------------
      GOODBYE = 2025 OPV TAMAT
      GOODBYE = 2025 OPV TAMAT
      GOODBYE = 2025 OPV TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      NGPVs 2024-1996 = 28 TAHUN
      28 TAHUN MANGKRAK
      28 TAHUN MANGKRAK
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
      =======
      KEYWORDS
      OPV TAMAT
      LCS NEXT TAMAT

      Hapus
    3. DELAYED LCS ...........
      PROGRESS 70.1% (2025-2011 = 15 YEARS)
      PROGRESS 70.1% (2025-2011 = 15 YEARS)
      PROGRESS 70.1% (2025-2011 = 15 YEARS)
      Deputy Defence Minister Adly Zahari said on Thursday that the overall progress of the long-delayed littoral combat ships (LCS) project had reached 70.1% as of Oct 25 this year.
      =============
      SLOWLY...........
      70.1% : 15 YEARS = 4.6% PER YEARS
      70.1% : 15 YEARS = 4.6% PER YEARS
      70.1% : 15 YEARS = 4.6% PER YEARS
      The progress — which includes design, construction, equipping, and testing — is slightly behind schedule by 0.59%, as the planned progress was 70.69%, according to the contract’s timeline.
      On the first LCS (LCS 1), the construction is in its final phase and is expected to be completed by the end of this year, Adly noted.
      =============
      GOODBYE 2025 OPV 2 DAN 3 = TAMAT
      GOODBYE 2025 OPV 2 DAN 3 = TAMAT
      GOODBYE 2025 OPV 2 DAN 3 = TAMAT
      Tanda tanya mengenai status semasa pembinaan dua lagi kapal peronda luar pesisir (OPV) Agensi Penguatkuasa Maritim Malonn (APMM) terjawab selepas kerajaan menamatkan kontrak dengan THHE Destini Sdn Bhd (TDSB) setelah ia gagal menyiapkan projek berkenaan.
      Menteri Dalam Negeri Saifuddin Nasution Ismail berkata susulan penamatan yang ditandatangani pada 31 Disember lalu, syarikat itu dikenakan kadar denda dan ganti rugi ditetapkan (LAD) sebanyak RM12.49 juta [AS$2.82 juta] di atas kelewatan menyiapkan kapal OPV 2 dan OPV 3.
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.

      Hapus
    4. LCS = FFBNW STALLED 15 YEARS
      LCS USD 4,74 BILLION/5 UNIT = USD 948 MILLION/UNIT ]
      • USD 948 JUTA (WITHOUT AMMO) = FFBNW = DELAYED
      -NO NSM.
      -NO VL MICA.
      -NO TORPEDO RINGAN.
      -NO SECONDARY GUNS.
      -NO BOFORS MK3.
      -------------
      LMS B2 = FFBNW DOWNGRADE HISAR OPV NO ASW
      1. ADA CLASS PAKISTAN USD 1 MILYAR/4 = USD 250 JUTA PER UNIT
      -
      2. ADA CLASS UKRAINE USD 1 MILYAR/2 = USD 250 JUTA PER UNIT + UCAV SENILAI USD 500 JUTA
      -
      3. HISAR OPV CLASS (LMS B2) MALON USD 530 JUTA /3 = USD 176,7 JUTA PER UNIT
      -------------
      KEDAH = FFBNW NO MISSILE SINCE 2025=2009 : 17 YAERS GUNBOAT
      In June 2006, after a total of 18 months of delays, the Royal Malonnn Navy commissioned KD Kedah, followed by a second hull, KD Pahang in August of the same year, and a third hull, KD Perak on 12 November 2007. By July 2009, six vessels had been launched.
      -------------
      LMS B1 = GUNBOAT NO MISSILE
      LEKIU = EXO B2 EXPIRED
      KASTURI = EXO B2 EXPIRED
      LAKSAMANA = GUNBOAT NO MISSILE
      KEDAH = GUNBOAT NO MISSILE
      PERDANA = GUNBOAT NO MISSILE
      HANDALAN = GUNBOAT NO MISSILE
      JERUNG = GUNBOAT NO MISSILE
      PERDANA MENTERI = DEFACT KILL PREGNANT WOMEN
      =============
      The Malonnn Armed Forces' (MAF) Littoral Combat Ships (LCS) have faced several issues, including delays, design flaws, and a lack of air and surface warfare capabilities.
      Delays
      • The first LCS was delayed by six years, from its scheduled delivery date.
      • The LCS program has been plagued by delays due to a number of factors.
      Design flaws
      • The LCS hull, or sea frame, had issues with cracking.
      • The propulsion plant design had issues from the start.
      • Some mission module components were immature.
      Lack of air and surface warfare capabilities
      • Some say the LCS lacks significant air and surface warfare capabilities.
      Other issues
      • The LCS has faced issues with survivability in contested waters.
      • The LCS has had limited flight deck and berthing space.
      • The LCS has had command and control limitations.
      • The LCS program has been plagued by allegations of corruption and political interference.
      The MAF has also faced other challenges, including underfunding and an aging fleet.
      =============
      The Malonnn Armed Forces (MAF) face a number of challenges, including limited funding, aging equipment, and a lack of modern assets.
      Funding
      • Small procurement budgets: The MAF has had small procurement budgets over the past 25 years.
      • Fiscal limitations: The government has been unwilling to cut spending elsewhere or reduce the size of the armed forces.
      Aging equipment
      • Outdated assets: The MAF's equipment is aging, and the government has been unable to provide modern assets.
      • Withdrawal of MiG-29 Fulcrum fighter aircraft: The MAF withdrew its MiG-29 Fulcrum fighter aircraft from service in 2017.
      • Su-30MKM Flanker fighter aircraft: The MAF is struggling to keep its Su-30MKM Flanker fighter ground-attack aircraft operational.
      Other challenges
      Internal and external threats: The MAF faces threats from within and outside the country, including territorial incursions, radicalization, and violent extremism

      Hapus
  42. MEMALUKAN... Guys.... HAHAHAHAH😂😂😂😂😂😂

    BalasHapus
  43. Kasihan Damen....kena PRANK Malaydesh...😆 🤣

    BalasHapus
  44. Memang hebat geng MALAYDESH nih.. Suka buat dunia TERTAWA... HAHAHAHAH


    SALAH POTONG kapal OPV 2 dan 3 TENGGELAM ke ALAM GHOIB... Hahahahahaha

    BalasHapus
  45. MEMALUKAN... bukan lagi miring.... Tapi TENGGELAM... 🤣🤣🤣

    Duh, Kapal Baru Bakamla Ini Nyaris Tenggelam

    https://news.detik.com/foto-news/d-4442174/duh-kapal-baru-bakamla-ini-nyaris-tenggelam

    BalasHapus
    Balasan
    1. 2029-2020 : 10 YEARS = OVERLIMIT DEBT
      2029-2020 : 10 YEARS = OVERLIMIT DEBT
      DEBT RATIO TO GDP.......
      2029 = 69,54%
      2028 = 69,34%
      2027 = 68,8%
      2026 = 68,17%
      2025 = 68,07%
      2024 = 68,38%
      2023 = 69,76%
      2022 = 65,5%
      2021 = 69,16%
      2020 = 67,69%
      BY STATISTA ......
      ================
      OPV 2 DAN OPV 3 TAMAT = DESEMBER 2024
      OPV 2 DAN OPV 3 TAMAT = DESEMBER 2024
      OPV 2 DAN OPV 3 TAMAT = DESEMBER 2024
      Menteri Dalam Negeri Saifuddin Nasution Ismail berkata susulan penamatan yang ditandatangani pada 31 Disember lalu, syarikat itu dikenakan kadar denda dan ganti rugi ditetapkan (LAD) sebanyak RM12.49 juta [AS$2.82 juta] di atas kelewatan menyiapkan kapal OPV 2 dan OPV 3.
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      NGPVs 2024-1996 = 28 TAHUN
      28 TAHUN MANGKRAK
      28 TAHUN MANGKRAK
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
      =======
      KEYWORDS
      OPV TAMAT
      LCS NEXT TAMAT

      Hapus
    2. DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      ---
      KONTRAK 2017
      TH Heavy Engineering Berhad (THHE) and Destini Berhad (Destini) announced today that they have secured a contract worth RM738.9 million (inclusive of 6% GST) for the supply, delivery, testing and commissioning of three units of Offshore Patrol Vessels (OPV) for the Malonn Maritime Enforcement Agency (MMEA)
      ---
      DIJANGKA 2020
      Kontrak Damen 1800 OPV diberikan kepada perusahaan lokal THHE-Destini pada awal tahun 2017. Kontrak kapal bernilai RM738,9 juta dan konstruksi dimulai pada Desember 2017. Kapal pertama akan selesai pada pertengahan tahun 2020
      --
      MIRING KABEL PUTUS
      THHE general manager Azizul Hanafee Zain explained that the ship tilted to one side after one of the steel cables attached to the supporting structure underneath the ship was cut.
      ---
      DISUNTIK HUTANG
      government is injecting RM152.6 million to ensure that the first Offshore Patrol Vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA)
      ---
      OPV DIAMBIL MOF 2023
      The government will inject RM152.6 million to ensure that the first offshore patrol vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA) will be completed this year, Prime Minister Anwar Ibrahim said today.
      He said the finance ministry (MoF) had taken over the OPV project from Tabung Haji (TH) subsidiary, Destini Sdn Bhd, after it was found to be facing major problems.
      ---
      THHE BANGKRUT 2023 = THHE TUTUP
      Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
      The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.

      Hapus
    3. GOODBYE 2024 OPV 2 DAN 3 = TAMAT
      GOODBYE 2024 OPV 2 DAN 3 = TAMAT
      GOODBYE 2024 OPV 2 DAN 3 = TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
      ============
      GOODBYE 2023 THHE DELISTED = BURSA MALONN
      GOODBYE 2023 THHE DELISTED = BURSA MALONN
      GOODBYE 2023 THHE DELISTED = BURSA MALONN
      Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
      The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
      The winding-up notice also stated that a meeting of creditors is scheduled for Oct 4 at 3pm.
      THHE is controlled by the Ministry of Finance-owned (MoF) unit Urusharta Jamaah Sdn Bhd, which holds a 64.45% stake in the company prior to its delisting on Sept 5, 2022
      TH Heavy was delisted from Bursa Malonn in September 2022, after failing to come up with a restructuring exercise despite being given eight extensions by the exchange since first entering Practice Note 17 status in April 2018.
      The decision to wind up came after THHE filed an ex-parte originating summons in July to call for a creditors’ meeting to propose a scheme of arrangement for the company.
      Global Mariner Offshore Services, Blackstone Technology Sdn Bhd and Dynac Sdn Bhd have reportedly filed applications to intervene in THHE’s ex-parte application.
      THHE had a joint venture partnership with Global Mariner, but a legal dispute arose between the two companies. The High Court ordered THHE to pay Global Mariner approximately RM288.72 million in damages.
      =======
      KEYWORDS
      OPV TAMAT
      LCS NEXT TAMAT

      Hapus
    4. DESEMBER 2024 OPV TAMAT
      DESEMBER 2024 OPV TAMAT
      DESEMBER 2024 OPV TAMAT
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      -----
      OPV 2025-2017 = 9 TAHUN
      9 TAHUN MANGKRAK
      9 TAHUN MANGKRAK
      OPV DIBAYAR 3 JADI 1 = THHE BANGKRUT : Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn. The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up NOtice dated Sept 13.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      NGPVs 2024-1996 = 28 TAHUN
      28 TAHUN MANGKRAK
      28 TAHUN MANGKRAK
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -----
      NGPVs BAYAR HUTANG LCS = seperti didedahkan Jawatankuasa Kira-kira Wang Negara (PAC) dan CEO LTAT, syarikat BNS menggunakan RM400 juta daripada bayaran pendahuluan bagi projek LCS untuk menjelaskan hutang lapuk bagi projek NGPV," syarikat PSC-Naval Dockyard pada Disember 2005 sebelum dijenamakan semula menjadi syarikat Boustead Naval Dockyard Sdn Bhd
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT FINANCE HOUSE (Malonn) Bhd.
      ===================
      The Malonnn Armed Forces (MAF) has faced challenges in modernizing its missile capabilities due to budgetary constraints, political interference, and a lack of modern assets.
      Budgetary constraints
      • The 1997 Asian financial crisis limited the MAF's ability to procure new weapons.
      • Malonn's defense budget is limited, which can affect the pace of acquisitions and upgrades.
      Political interference
      • Political leaders have been accused of interfering in procurement.
      Lack of modern assets
      • The MAF has aging military assets, including most of the navy's fleet and helicopters commissioned in the 1960s.
      • The MAF has experienced issues with the maintenance and spare parts for its aircraft.
      Other challenges the MAF has faced include: Poor planning, Personnel issues, and Critical problems with the PT-91M main battle tank.

      Hapus
    5. Yg betul miring Tuh si Fatimah. tolol kok dipelihara dan dibanggakan.paham.

      Hapus
  46. MEMALUKAN... bukan lagi miring.... Tapi TENGGELAM... 🤣🤣🤣

    Duh, Kapal Baru Bakamla Ini Nyaris Tenggelam

    https://news.detik.com/foto-news/d-4442174/duh-kapal-baru-bakamla-ini-nyaris-tenggelam

    BalasHapus
    Balasan
    1. 2029-2020 : 10 YEARS = OVERLIMIT DEBT
      2029-2020 : 10 YEARS = OVERLIMIT DEBT
      DEBT RATIO TO GDP.......
      2029 = 69,54%
      2028 = 69,34%
      2027 = 68,8%
      2026 = 68,17%
      2025 = 68,07%
      2024 = 68,38%
      2023 = 69,76%
      2022 = 65,5%
      2021 = 69,16%
      2020 = 67,69%
      BY STATISTA ......
      ================
      OPV 2 DAN OPV 3 TAMAT = DESEMBER 2024
      OPV 2 DAN OPV 3 TAMAT = DESEMBER 2024
      OPV 2 DAN OPV 3 TAMAT = DESEMBER 2024
      Menteri Dalam Negeri Saifuddin Nasution Ismail berkata susulan penamatan yang ditandatangani pada 31 Disember lalu, syarikat itu dikenakan kadar denda dan ganti rugi ditetapkan (LAD) sebanyak RM12.49 juta [AS$2.82 juta] di atas kelewatan menyiapkan kapal OPV 2 dan OPV 3.
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      NGPVs 2024-1996 = 28 TAHUN
      28 TAHUN MANGKRAK
      28 TAHUN MANGKRAK
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
      =======
      KEYWORDS
      OPV TAMAT
      LCS NEXT TAMAT

      Hapus
    2. DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      DESEMBER 2024 OPV 2 dan 3 = TAMAT
      Tanda tanya mengenai status semasa pembinaan dua lagi kapal peronda luar pesisir (OPV) Agensi Penguatkuasa Maritim Malonn (APMM) terjawab selepas kerajaan menamatkan kontrak dengan THHE Destini Sdn Bhd (TDSB) setelah ia gagal menyiapkan projek berkenaan.
      Menteri Dalam Negeri Saifuddin Nasution Ismail berkata susulan penamatan yang ditandatangani pada 31 Disember lalu, syarikat itu dikenakan kadar denda dan ganti rugi ditetapkan (LAD) sebanyak RM12.49 juta [AS$2.82 juta] di atas kelewatan menyiapkan kapal OPV 2 dan OPV 3.
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      NGPVs 2024-1996 = 28 TAHUN
      28 TAHUN MANGKRAK
      28 TAHUN MANGKRAK
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT FINANCE HOUSE (Malonn) Bhd.

      Hapus
    3. NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
      NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
      NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -------------------
      OPV 2 DAN OPV 3 = TAMAT
      OPV 2 DAN OPV 3 = TAMAT
      OPV 2 DAN OPV 3 = TAMAT
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
      Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
      ===============
      PROBLEMS SHIPYARD
      PROBLEMS SHIPYARD
      PROBLEMS SHIPYARD
      Local shipyards have poor record building big ships. LCS is one, Kedah is the first. The MMEA OPV is the other one. No need to be a cheerleader about it and trying to play it safe. It’s bad then it’s bad. Can blame the system, blame the politicians, blame the lack of controls, blame the people, the fact remains the local shipyards failed to deliver, and it has cost RMN. Less we forget, BNS (from the days of PSC-ND) had more than 20+ years to learn building complex ships. Also, the shipbuilding pipeline is too limited to support a local industry, meaning there is no learning possible – BNS (and its predecessor PSC-ND) only had contract to build 12 warships in its existence. In fact, come 2030, after 30 years, if we’re lucky the shipyard would still only have built 11 ships. In contrast ST Engineering had more than 40 ships over 28 years and have confirmed 6 new ships out to 2030. Learning is one thing, tolerating “still learning” after 20 plus years is not good enough. Not recognising learning is not possible because of limited pipeline is another. Local shipyards have proven capable of building certain type of ships because of good pipeline, so good for them that they win those contract – they can learn over time to build bigger ships. But for now, no need to be a cheerleader for local shipyards pitching to win big ships for RMN and MMEA

      Hapus
    4. Memalukan kapal usang tenggelam kok masih diangkat bukan buat rumpon. MKM Malon Ketahuan Miskin.

      Hapus
  47. Duh, Kapal Baru Bakamla Ini Nyaris Tenggelam.

    https://news.detik.com/foto-news/d-4442174/duh-kapal-baru-bakamla-ini-nyaris-tenggelam

    BalasHapus
    Balasan
    1. 2029-2020 : 10 YEARS = OVERLIMIT DEBT
      2029-2020 : 10 YEARS = OVERLIMIT DEBT
      DEBT RATIO TO GDP.......
      2029 = 69,54%
      2028 = 69,34%
      2027 = 68,8%
      2026 = 68,17%
      2025 = 68,07%
      2024 = 68,38%
      2023 = 69,76%
      2022 = 65,5%
      2021 = 69,16%
      2020 = 67,69%
      BY STATISTA ......
      ================
      OPV 2 DAN OPV 3 TAMAT = DESEMBER 2024
      OPV 2 DAN OPV 3 TAMAT = DESEMBER 2024
      OPV 2 DAN OPV 3 TAMAT = DESEMBER 2024
      Menteri Dalam Negeri Saifuddin Nasution Ismail berkata susulan penamatan yang ditandatangani pada 31 Disember lalu, syarikat itu dikenakan kadar denda dan ganti rugi ditetapkan (LAD) sebanyak RM12.49 juta [AS$2.82 juta] di atas kelewatan menyiapkan kapal OPV 2 dan OPV 3.
      Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
      -----
      LCS 2025-2011 = 15 TAHUN
      15 TAHUN MANGKRAK
      15 TAHUN MANGKRAK
      LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
      -----
      NGPVs 2024-1996 = 28 TAHUN
      28 TAHUN MANGKRAK
      28 TAHUN MANGKRAK
      NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
      -----
      17 KREDITUR LCS
      17 KREDITUR LCS
      17 KREDITUR LCS
      Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
      =======
      KEYWORDS
      OPV TAMAT
      LCS NEXT TAMAT

      Hapus
    2. DESEMBER 2024 OPV TAMAT
      DESEMBER 2024 OPV TAMAT
      DESEMBER 2024 OPV TAMAT
      “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam...
      -----
      LEASE FAST INTERCEPTOR BOAT
      LEASE UTILITY BOAT
      LEASE RIGID HULL FENDER BOAT
      LEASE ROVER FIBER GLASS
      LEASE EC120B
      LEASE FLIGHT SIMULATION TRAINING DEVICE
      Mungkin ada yang tertanya-tanya, namun kaedah penyewaan ini bukanlah kali pertama dilakukan. Kerajaan sebelum ini pernah menyewa Helikopter Latihan Airbus EC120B dan Flight Simulation Training Device (FSTD) Untuk Kegunaan Kursus Asas Juruterbang Helikopter TUDM.
      Selain itu, kerajaan turut pernah menyewa 5 unit Helikopter EC120B; 1 unit Sistem Simulator dan LEASEan Bot Op Pasir merangkumi 10 unit Fast Interceptor Boat (FIB); 10 unit Utility Boat; 10 unit Rigid Hull Fender Boat (RHFB); 10 unit Rover Fiber Glass (Rover).
      -----
      LEASE KAPAL HIDROLOGI
      LEASE KAPAL HIDROLOGI
      LEASE KAPAL HIDROLOGI
      Panglima TLDM Laksamana Tan Sri Ahmad Kamarulzaman Ahmad Badaruddin berkata Aishah Aims 4 diperoleh melalui kontrak LEASEan bagi menggantikan dua kapal hidrografi sedia ada milik TLDM iaitu KD Mutiara dan KD Perantau yang akan melalui proses lucut tauliah secara berperingkat.
      ===================
      LEASE VSHORAD
      LEASE TRUK CINA 3 TON
      Three weeks ago, the Madani government announced that it had struck a deal with China to lease 62 new train sets for KTM Bhd. The estimated cost for the deal is RM10.7 billion and it will be covered in installments over a 30-year lease period. The approved leasing deal for KTMB may tip the scale in favour of the truck and VSHORAD proposals.
      LEASE PESAWAT
      ITTC is currently providing Fighter Lead-In Training (FLIT) to the Royal Malonn Air Force in London, Ontario. ITTC operates a fleet of Aero Vodochody L-39 featuring upgraded avionics for the FLIT programme
      LEASE SIMULATOR MKM TAHUN
      Five-year contract for Sukhoi’s simulators. Publicly listed HeiTech Padu Bhd has announced that it had been awarded a RM67 million, five-year contract to operate and maintain the Su-30MKM flight simulators at the RMAF airbase in Gong Kedak
      LEASE HELI LEASE SIMULATOR
      Kerajaan sebelum ini pernah menyewa Helikopter Latihan Airbus EC120B dan Flight Simulation Training Device (FSTD) Untuk Kegunaan Kursus Asas Juruterbang Helikopter TUDM. Selain itu, kerajaan turut pernah menyewa 5 unit Helikopter EC120B; 1 unit Sistem Simulator
      LEASE HELI
      4 buah Helikopter Leonardo AW 139 yang diperolehi secara LEASEan ini adalah untuk kegunaan Tentera Udara Diraja Malon (TUDM) yang akan ditempatkan di NO.3 Skuadron, Pangkalan Udara Butterworth
      LEASE BOAT
      LEASEan Bot Op Pasir merangkumi 10 unit Fast Interceptor Boat (FIB); 10 unit Utility Boat; 10 unit Rigid Hull Fender Boat (RHFB); 10 unit Rover Fiber Glass (Rover).
      LEASE HIDROGRAFI
      tugas pemetaan data batimetri bagi kawasan perairan negara akan dilakukan oleh sebuah kapal hidrografi moden, MV Aishah AIM 4, yang diperoleh menerusi kontrak LEASEan dari syarikat Breitlink Engineering Services Sdn Bhd (BESSB)
      LEASE 4x4
      Pejabat perusahaan mengatakan kepada Janes di pameran bahwa Angkatan Bersenjata Malon sedang mencari untuk menyewa Tarantula
      LEASE MOTOR
      The Royal Military Police Corp (KPTD) celebrated the lease of 40 brand-new BMW R1250RT Superbikes for the Enforcement Motorcycle Squad on December 22nd, 2022
      LEASE PATROL BOATS : LEASE OUTBOARD MOTORS : LEASE TRAILERS
      Meanwhile, the division also published a tender for eleven glass reinforced plastic patrol boats together outboard motors, trailers and associated equipment. The tender was published on February 28 and closes on March 29. The estimated cost of the tender is RM4.6 million..
      LEASE 28 HELI
      The government signed an agreement with Weststar Aviation Sdn Bhd to lease 28 helicopters for use by ministries and other government agencies

      Hapus
    3. RENAME = COPY PASTE = STALLED 15 YEARS .....
      PSC = 1995
      PSC > BNS = 2005
      BNC > LUNAS = 2024
      PSC-Naval Dockyard founded 1995. In 2005, Public Accounts Committee (PAC) unveiled serious corruption in the PCS-ND and caused solemn concern from the public. Under pressure of the public, Malonnn government enforced a reorganize result the PCS-ND to be taken over by Boustead Heavy Industries Corporation and renamed as Boustead Naval Shipyard Sdn Bhd. Boustead Heavy Industries Corporation (BHIC) was listed on Bursa Malonn in 2007 and the parent company is Boustead Holdings. BHIC was known for its subsidiary Boustead Naval Shipyard (BNS) which is specialised in naval shipbuilding and ship repair.[5] BNS now had taken over by Government and renamed as Lumut Naval Shipyard (LUNAS) 2024
      ===================
      NEVER BUILT ANYTHING BUT = TRAWLERS OR POLICE BOATS
      NEVER BUILT ANYTHING BUT = TRAWLERS OR POLICE BOATS
      NEVER BUILT ANYTHING BUT = TRAWLERS OR POLICE BOATS
      Despite the auditor-general stating that PSC-Naval Dockyard had never built anything but trawlers or police boats before being given the contract, the company was contracted to deliver six patrol boats for the Malonnn Navy in 2004 and complete the delivery in 2007.
      Those were supposed to be the first of 27 offshore vessels ultimately cost RM24 billion plus the right to maintain and repair all of the country’s naval craft.
      ===================
      Malon's combat equipment has several weaknesses, including:
      • Ageing equipment: The Malonn military's equipment is aging due to small procurement budgets over the past 25 years.
      • Lack of modern assets: The Malonn Armed Forces (MAF) lacks modern military assets, which puts them at risk from both internal and external threats.
      • Russian-made weapons: Malon has been struggling to keep its Russian-made Su-30MKM ground-attack aircraft operational. The country is also wary of Russian-made weapons due to sanctions imposed on Russia after its invasion of Ukraine.
      • Local production: The MAF is reluctant to use locally produced products. Local companies have produced prototypes of pistols and rifles, but none have materialized.
      • Procurement system: The Malonn procurement system needs reform.
      Political interference and corruption: Political interference and corruption are undermining combat readiness.
      ===================
      PROBLEMS SHIPYARD
      PROBLEMS SHIPYARD
      PROBLEMS SHIPYARD
      Local shipyards have poor record building big ships. LCS is one, Kedah is the first. The MMEA OPV is the other one. No need to be a cheerleader about it and trying to play it safe. It’s bad then it’s bad. Can blame the system, blame the politicians, blame the lack of controls, blame the people, the fact remains the local shipyards failed to deliver, and it has cost RMN. Less we forget, BNS (from the days of PSC-ND) had more than 20+ years to learn building complex ships. Also, the shipbuilding pipeline is too limited to support a local industry, meaning there is no learning possible – BNS (and its predecessor PSC-ND) only had contract to build 12 warships in its existence. In fact, come 2030, after 30 years, if we’re lucky the shipyard would still only have built 11 ships. In contrast ST Engineering had more than 40 ships over 28 years and have confirmed 6 new ships out to 2030. Learning is one thing, tolerating “still learning” after 20 plus years is not good enough. Not recognising learning is not possible because of limited pipeline is another. Local shipyards have proven capable of building certain type of ships because of good pipeline, so good for them that they win those contract – they can learn over time to build bigger ships. But for now, no need to be a cheerleader for local shipyards pitching to win big ships for RMN and MMEA.

      Hapus
  48. Kasihan MALAYDESH... 😂😂😂😂

    Jadi Kapal OPV 1 KM Tun Fatimah yang SALAH POTONG dan JALAN MIRING di paksakan untuk di terima yang ternyata produk GAGAL dan KUALITAS RENDAH....

    Sehingga kapal OPV 2 dan OPV 3 yang produk RENDAHAN pun GAGAL TOTAL dan TENGGELAM ke ALAM GHOIB... Hahahahahaha😂😂😂😂😂


    MEMALUKAN dan MENYEDIHKAN...hahahahahaha

    BalasHapus
  49. Galangan Destiny bankrup....hahahaha OPV miring

    BalasHapus
  50. SHARE BERITA NOVEMVER
    OPV TAMAT DESEMBER 2024 =
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    -------------------
    BERUK WARIA 9 Februari 2025 pukul 21.38
    OPV TAMAT...? SORRY ya GORILLA.. 🤣🤣🤣

    Projek 2 kapal OPV APMM yang tertangguh akan disambung semula

    https://www.airtimes.my/2024/11/19/projek-2-kapal-opv-apmm-yang-tertangguh-akan-disambung-semula/
    -------------------
    GOODBYE = 2025 OPV TAMAT
    GOODBYE = 2025 OPV TAMAT
    GOODBYE = 2025 OPV TAMAT
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
    -----
    LCS 2025-2011 = 15 TAHUN
    15 TAHUN MANGKRAK
    15 TAHUN MANGKRAK
    LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
    -----
    NGPVs 2024-1996 = 28 TAHUN
    28 TAHUN MANGKRAK
    28 TAHUN MANGKRAK
    NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
    -----
    17 KREDITUR LCS
    17 KREDITUR LCS
    17 KREDITUR LCS
    Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
    =======
    KEYWORDS
    OPV TAMAT
    LCS NEXT TAMAT

    BalasHapus
  51. Admin tega benar ke geng MALAYDESH... Hahahahahaha


    Di suruh update kecanggihan kapal PPA INDONESIA dia malah update berita KEGAGALAN kapal MINYAK SAWIT... Hahahahahaha😂😂😂😂😂

    BalasHapus
  52. DESEMBER 2024 OPV 2 dan 3 = TAMAT
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    DESEMBER 2024 OPV 2 dan 3 = TAMAT
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    ---
    KONTRAK 2017
    TH Heavy Engineering Berhad (THHE) and Destini Berhad (Destini) announced today that they have secured a contract worth RM738.9 million (inclusive of 6% GST) for the supply, delivery, testing and commissioning of three units of Offshore Patrol Vessels (OPV) for the Malonn Maritime Enforcement Agency (MMEA)
    ---
    DIJANGKA 2020
    Kontrak Damen 1800 OPV diberikan kepada perusahaan lokal THHE-Destini pada awal tahun 2017. Kontrak kapal bernilai RM738,9 juta dan konstruksi dimulai pada Desember 2017. Kapal pertama akan selesai pada pertengahan tahun 2020
    --
    MIRING KABEL PUTUS
    THHE general manager Azizul Hanafee Zain explained that the ship tilted to one side after one of the steel cables attached to the supporting structure underneath the ship was cut.
    ---
    DISUNTIK HUTANG
    government is injecting RM152.6 million to ensure that the first Offshore Patrol Vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA)
    ---
    OPV DIAMBIL MOF 2023
    The government will inject RM152.6 million to ensure that the first offshore patrol vessel (OPV 1) project belonging to the Malonnn Maritime Enforcement Agency (MMEA) will be completed this year, Prime Minister Anwar Ibrahim said today.
    He said the finance ministry (MoF) had taken over the OPV project from Tabung Haji (TH) subsidiary, Destini Sdn Bhd, after it was found to be facing major problems.
    ---
    THHE BANGKRUT 2023 = THHE TUTUP
    Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
    The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.

    BalasHapus
  53. GOODBYE 2024 OPV 2 DAN 3 = TAMAT
    GOODBYE 2024 OPV 2 DAN 3 = TAMAT
    GOODBYE 2024 OPV 2 DAN 3 = TAMAT
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
    ============
    GOODBYE 2023 THHE DELISTED = BURSA MALONN
    GOODBYE 2023 THHE DELISTED = BURSA MALONN
    GOODBYE 2023 THHE DELISTED = BURSA MALONN
    Offshore fabricator and shipbuilder TH Heavy Engineering Bhd (THHE) is undertaking a voluntary winding-up, a year after it was delisted from Bursa Malonn.
    The company resolved to undertake voluntary winding-up as it is unable to continue its operations due to liabilities, it said in a winding-up notice dated Sept 13.
    The winding-up notice also stated that a meeting of creditors is scheduled for Oct 4 at 3pm.
    THHE is controlled by the Ministry of Finance-owned (MoF) unit Urusharta Jamaah Sdn Bhd, which holds a 64.45% stake in the company prior to its delisting on Sept 5, 2022
    TH Heavy was delisted from Bursa Malonn in September 2022, after failing to come up with a restructuring exercise despite being given eight extensions by the exchange since first entering Practice Note 17 status in April 2018.
    The decision to wind up came after THHE filed an ex-parte originating summons in July to call for a creditors’ meeting to propose a scheme of arrangement for the company.
    Global Mariner Offshore Services, Blackstone Technology Sdn Bhd and Dynac Sdn Bhd have reportedly filed applications to intervene in THHE’s ex-parte application.
    THHE had a joint venture partnership with Global Mariner, but a legal dispute arose between the two companies. The High Court ordered THHE to pay Global Mariner approximately RM288.72 million in damages.
    =======
    KEYWORDS
    OPV TAMAT
    LCS NEXT TAMAT

    BalasHapus
  54. Jadi selama ini memang benar kapal OPV 1 tenyata kualitas RENDAH dan PRODUK GAGAL namun di paksakan untik di serahkan... HAHAHAHA


    OPV 2dan 3 begabung dengan kapal lcs ke 6 di ALAM GHOIB... Hahahahaha

    LUAR BIASA MALON... HAHAHAHA😜😜😜😜😜😂😂😂

    BalasHapus
  55. DELAYED LCS ...........
    PROGRESS 70.1% (2025-2011 = 15 YEARS)
    PROGRESS 70.1% (2025-2011 = 15 YEARS)
    PROGRESS 70.1% (2025-2011 = 15 YEARS)
    Deputy Defence Minister Adly Zahari said on Thursday that the overall progress of the long-delayed littoral combat ships (LCS) project had reached 70.1% as of Oct 25 this year.
    =============
    SLOWLY...........
    70.1% : 15 YEARS = 4.6% PER YEARS
    70.1% : 15 YEARS = 4.6% PER YEARS
    70.1% : 15 YEARS = 4.6% PER YEARS
    The progress — which includes design, construction, equipping, and testing — is slightly behind schedule by 0.59%, as the planned progress was 70.69%, according to the contract’s timeline.
    On the first LCS (LCS 1), the construction is in its final phase and is expected to be completed by the end of this year, Adly noted.
    =============
    GOODBYE 2025 OPV 2 DAN 3 = TAMAT
    GOODBYE 2025 OPV 2 DAN 3 = TAMAT
    GOODBYE 2025 OPV 2 DAN 3 = TAMAT
    Tanda tanya mengenai status semasa pembinaan dua lagi kapal peronda luar pesisir (OPV) Agensi Penguatkuasa Maritim Malonn (APMM) terjawab selepas kerajaan menamatkan kontrak dengan THHE Destini Sdn Bhd (TDSB) setelah ia gagal menyiapkan projek berkenaan.
    Menteri Dalam Negeri Saifuddin Nasution Ismail berkata susulan penamatan yang ditandatangani pada 31 Disember lalu, syarikat itu dikenakan kadar denda dan ganti rugi ditetapkan (LAD) sebanyak RM12.49 juta [AS$2.82 juta] di atas kelewatan menyiapkan kapal OPV 2 dan OPV 3.
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.

    BalasHapus
  56. RENAME = COPY PASTE = STALLED 15 YEARS .....
    PSC = 1995
    PSC > BNS = 2005
    BNC > LUNAS = 2024
    PSC-Naval Dockyard founded 1995. In 2005, Public Accounts Committee (PAC) unveiled serious corruption in the PCS-ND and caused solemn concern from the public. Under pressure of the public, Malonnn government enforced a reorganize result the PCS-ND to be taken over by Boustead Heavy Industries Corporation and renamed as Boustead Naval Shipyard Sdn Bhd. Boustead Heavy Industries Corporation (BHIC) was listed on Bursa Malonn in 2007 and the parent company is Boustead Holdings. BHIC was known for its subsidiary Boustead Naval Shipyard (BNS) which is specialised in naval shipbuilding and ship repair.[5] BNS now had taken over by Government and renamed as Lumut Naval Shipyard (LUNAS) 2024
    ===================
    NEVER BUILT ANYTHING BUT = TRAWLERS OR POLICE BOATS
    NEVER BUILT ANYTHING BUT = TRAWLERS OR POLICE BOATS
    NEVER BUILT ANYTHING BUT = TRAWLERS OR POLICE BOATS
    Despite the auditor-general stating that PSC-Naval Dockyard had never built anything but trawlers or police boats before being given the contract, the company was contracted to deliver six patrol boats for the Malonnn Navy in 2004 and complete the delivery in 2007.
    Those were supposed to be the first of 27 offshore vessels ultimately cost RM24 billion plus the right to maintain and repair all of the country’s naval craft.
    ===================
    Malon's combat equipment has several weaknesses, including:
    • Ageing equipment: The Malonn military's equipment is aging due to small procurement budgets over the past 25 years.
    • Lack of modern assets: The Malonn Armed Forces (MAF) lacks modern military assets, which puts them at risk from both internal and external threats.
    • Russian-made weapons: Malon has been struggling to keep its Russian-made Su-30MKM ground-attack aircraft operational. The country is also wary of Russian-made weapons due to sanctions imposed on Russia after its invasion of Ukraine.
    • Local production: The MAF is reluctant to use locally produced products. Local companies have produced prototypes of pistols and rifles, but none have materialized.
    • Procurement system: The Malonn procurement system needs reform.
    Political interference and corruption: Political interference and corruption are undermining combat readiness.
    ===================
    PROBLEMS SHIPYARD
    PROBLEMS SHIPYARD
    PROBLEMS SHIPYARD
    Local shipyards have poor record building big ships. LCS is one, Kedah is the first. The MMEA OPV is the other one. No need to be a cheerleader about it and trying to play it safe. It’s bad then it’s bad. Can blame the system, blame the politicians, blame the lack of controls, blame the people, the fact remains the local shipyards failed to deliver, and it has cost RMN. Less we forget, BNS (from the days of PSC-ND) had more than 20+ years to learn building complex ships. Also, the shipbuilding pipeline is too limited to support a local industry, meaning there is no learning possible – BNS (and its predecessor PSC-ND) only had contract to build 12 warships in its existence. In fact, come 2030, after 30 years, if we’re lucky the shipyard would still only have built 11 ships. In contrast ST Engineering had more than 40 ships over 28 years and have confirmed 6 new ships out to 2030. Learning is one thing, tolerating “still learning” after 20 plus years is not good enough. Not recognising learning is not possible because of limited pipeline is another. Local shipyards have proven capable of building certain type of ships because of good pipeline, so good for them that they win those contract – they can learn over time to build bigger ships. But for now, no need to be a cheerleader for local shipyards pitching to win big ships for RMN and MMEA.

    BalasHapus
  57. INDONESIA nih guys....😎😎👍👍

    PRESTASI membanggakan disuguhkan PT Daya Radar Utama (DRU). Perusahaan yang berbasis di Lampung tersebut sukses meluncurkan dua kapal Offshore Patrol Vessel (OPV) 90M dan OPV dalam tempo dua hari, yakni pada Rabu (18/09/2024) dan Jumat (20/09/2024).


    Berbanding terbalik dengan 2 OPV geng MALAYDESH belum BERPERANG sudah GAGAL TOTAL... HAHAHAHAHA

    Salam SALAH POTONG... Hahaha😂😂😂

    BalasHapus
  58. It is interesting to note that 70 per cent of the materials for the OPV is sourced from overseas and most of it come from China – most likely the steel or aluminium
    -----

    jiaahh besi baja tipis dari Elder Brader
    Low Kualiti, ktemu CCG sungkem haha!🤣🤣🤣
    Murah aja Ngutang sampe minta suntik RM 152 juta haha!🥶🤥🥶

    BalasHapus
  59. INDONESIA nih guys....😎😎👍👍

    PRESTASI membanggakan disuguhkan PT Daya Radar Utama (DRU). Perusahaan yang berbasis di Lampung tersebut sukses meluncurkan dua kapal Offshore Patrol Vessel (OPV) 90M dan OPV dalam tempo dua hari, yakni pada Rabu (18/09/2024) dan Jumat (20/09/2024).


    Berbanding terbalik dengan 2 OPV geng MALAYDESH belum BERPERANG sudah GAGAL TOTAL... HAHAHAHAHA

    Salam SALAH POTONG... Hahaha😂😂😂

    BalasHapus
  60. INDONESIA nih guys....😎😎👍👍

    PRESTASI membanggakan disuguhkan PT Daya Radar Utama (DRU). Perusahaan yang berbasis di Lampung tersebut sukses meluncurkan dua kapal Offshore Patrol Vessel (OPV) 90M dan OPV dalam tempo dua hari, yakni pada Rabu (18/09/2024) dan Jumat (20/09/2024).


    Berbanding terbalik dengan 2 OPV geng MALAYDESH belum BERPERANG sudah GAGAL TOTAL... HAHAHAHAHA

    Salam SALAH POTONG... Hahaha😂😂😂

    BalasHapus
  61. Warga DS itu sungguh TERLALU.
    Kenapa harus dibuli???? Kasihan MALON, bagi mereka GAGAL itu ON TRACK
    🤣🤣🤣🤣🤣🤣

    BalasHapus
  62. ❌opv kontrak 3 kapal rm.738.9 mil
    tambah utang RM152.6 jt hasil 1,
    sisa 2 mangkrak haha!🤣🤣🤣

    ❌LCS kontrak 6 kapal rm.9 b hasil K⛔️SONG
    kasian warganyet kl, KENA Songlap lagiiiii haha!😂😂😂

    BalasHapus
  63. MENGAPA MASIH BUTUH OPV KAN SELEPAS HARI RAYA BANYAK ULTRAMAN² MELAYU ? ,
    YANG SAAT INI MASIH REBUTAN UNTUK DAPATKAN BAJU ULTRAMAN UNTUK HARI RAYA.

    BalasHapus
  64. Hanya bina kapal OPV saiz kecil saja hingga SALAH POTONG dan GAGAL TOTAL itu namanya....... TOLOL... HAHAHAHAHAHAHA



    MENANGIS lah geng MALON di kaki inggris ... HAHAHAHA😂😂😂😂

    BalasHapus
  65. Denda hanya segitu untuk kerugian yang berlipat2 .....
    Kasihan MALON
    🤣🤣🤣🤣🤣🤣

    BalasHapus
  66. 🤣🤣🤣.... TENGGELAM guys....

    Duh, Kapal Baru Bakamla Ini Nyaris Tenggelam

    https://news.detik.com/foto-news/d-4442174/duh-kapal-baru-bakamla-ini-nyaris-tenggelam

    BalasHapus
    Balasan
    1. KAPAL 1978
      PENDEKAR BOCOR TENGGELAM
      Kuala Lumpur: Tentera Laut Diraja Malon (TLDM) mengesahkan Kapal Diraja (KD) Pendekar mengalami kebocoran dan kebanjiran besar di dua batu nautika Tenggara Tanjung Penyusop, Johor ketika sedang melaksanakan penugasan operasi.
      -
      READINESS 58.6%
      Panglima Tentera Laut, Laksamana Tan Sri Abdul Rahman Ayob hari ini menyatakan tahap kesiagaan armada Tentera Laut Diraja Malon (TLDM) adalah di bawah sasaran.
      Perkara tersebut dinyatakan oleh beliau semasa menyampaikan Perutusan Tahun Baharu 2024 dan Setahun Pemerintahan Panglima Tentera Laut di Wisma Pertahanan.
      “Kesiagaan TLDM masih berada di bawah sasaran iaitu 58.6% berbanding sasaran 75%,
      -
      OBSOLETE ....
      PM Anwar said he had been astonished to see a navy frigate dating from the 1970s on display at the recent LIMA maritime and aerospace expo in Langkawi. “I want to salute these ships but I don’t know where to put my face. The last frigate (on display at LIMA) was from 1998,” he said
      -
      ASET USANG
      masalah penggunaan aset usang ini bukan hanya membabitkan pelbagai ketumbukan dalam Angkatan Tentera Malon (ATM), malah Polis Diraja Malon (PDRM), Agensi Penguatkuasaan Maritim Malon (Maritim Malon) dan pasukan keselamatan lain sebagai sebahagian daripada barisan pertahanan negara.
      -
      RONGSOK KAPAL 1967 = The post stated that among his achievements in the MMEA were that he was the team leader for a suitability study on absorbing the US Coast Guard cutter – USCG Decisive. Checks on the US Coast Guard website showed that Decisive– a Reliance class cutter – was laid in 1967 and commissioned in 1968
      -
      RONGSOK KAPAL SELAM BEKAS 1970 = In 2002, Malon signed a contract with France for acquisition of two Scorpène-class diesel-electric submarines.3 As part of the submarine induction process, Malon also negotiated for an ex-French Agosta 70-class submarine – Quessant – to be based in Toulon for RMN crew training and instruction
      -
      RONGSOK KAPAL 1980 = KM Perwira, one of the two Bay class patrol boats donated to MMEA by Australia. It is likely that the Bay class was the design proposed for the tri-nation VLPV project in the late 80s.
      -
      RONGSOK KAPAL 1989 DAN 1991 = Jepang menghibahkan dua kapal kelas 90m masing-masing PL-01 Ojima dan PL-02 Erimo, kedua kapal ini masuk dinas di JCG pada tahun 1989 dan 1991.
      -
      RONGSOK KAPAL 1990–1991 = KM Pekan is an Ojika-class offshore patrol vessel operated by the Malonn Coast Guard. This ship, together with KM Arau and KM Marlin was transferred from the Japan Coast Guard to Malon in order to strengthen the relations between the two countries. The ship was built as the Ojika for the Japanese Coast Guard in 1990–1991
      -
      RONGSOK KAPAL 1989 = KM Arau is an offshore patrol vessel operated by the Malonn Coast Guard. She was the second ship transferred from the Japan Coast Guard together with KM Pekan and KM Marlin. KM Arau was formerly kNOwn as Oki (PL-01) in the Japan Coast Guard.
      -
      RONGSOK 1960 BEKAS MARINE POLICE BEKAS MMEA = RMN informed us that they are getting a new boat – albeit a third hand one – courtesy of the MMEA. MMEA received from the Marine police back in 2011.
      -
      RONGSOK BEKAS MMEA = RMN has taken delivery of ex-Sundang on October 23 after the patrol craft completed its refit. She is the first of two ex-MMEA PC
      ===========================
      2024 OVER LIMIT DEBT 65,6%
      2024 OVER LIMIT DEBT 65,6%
      2024 OVER LIMIT DEBT 65,6%
      Malon Government debt accounted for 65.6 % of the country's Nominal GDP in Mar 2024, compared with the ratio of 64.3 % in the previous quarter. Malon government debt to GDP ratio data is updated quarterly, available from Dec 2010 to Mar 2024.
      ------------------
      HASIL STUDI = BELANJA PERTAHANAN TERGANTUNG HUTANG
      The results reveal a robust positive association between Public Debt and Defence Spending, substantiated by the significant coefficient of 0.7601 (p < 0.01). This suggests that an increase in Public Debt corresponds to a substantial rise in Defence Spending.

      Hapus
    2. LEASE HONDA CIVIC
      LEASE 40 BMW SUPERBIKES
      Leased BMW superbikes for military police. The Army’s military police – Kor Polis Tentera Di Raja – took delivery of 40 BMW R1250RT super bikes today. As for leasing vehicles, this has been common practise by government departments for the decade or so as it is supposed to be cheaper overall. The MPs had also taken delivery of Honda Civics under a leasing programme,
      -----
      LEASE FAST INTERCEPTOR BOAT
      LEASE UTILITY BOAT
      LEASE RIGID HULL FENDER BOAT
      LEASE ROVER FIBER GLASS
      LEASE EC120B
      LEASE FLIGHT SIMULATION TRAINING DEVICE
      Mungkin ada yang tertanya-tanya, namun kaedah penyewaan ini bukanlah kali pertama dilakukan. Kerajaan sebelum ini pernah menyewa Helikopter Latihan Airbus EC120B dan Flight Simulation Training Device (FSTD) Untuk Kegunaan Kursus Asas Juruterbang Helikopter TUDM.
      Selain itu, kerajaan turut pernah menyewa 5 unit Helikopter EC120B; 1 unit Sistem Simulator dan LEASEan Bot Op Pasir merangkumi 10 unit Fast Interceptor Boat (FIB); 10 unit Utility Boat; 10 unit Rigid Hull Fender Boat (RHFB); 10 unit Rover Fiber Glass (Rover).
      -----
      LEASE KAPAL HIDROLOGI
      LEASE KAPAL HIDROLOGI
      LEASE KAPAL HIDROLOGI
      Panglima TLDM Laksamana Tan Sri Ahmad Kamarulzaman Ahmad Badaruddin berkata Aishah Aims 4 diperoleh melalui kontrak LEASEan bagi menggantikan dua kapal hidrografi sedia ada milik TLDM iaitu KD Mutiara dan KD Perantau yang akan melalui proses lucut tauliah secara berperingkat.
      ===================
      LEASE VSHORAD
      LEASE TRUK CINA 3 TON
      Three weeks ago, the Madani government announced that it had struck a deal with China to lease 62 new train sets for KTM Bhd. The estimated cost for the deal is RM10.7 billion and it will be covered in installments over a 30-year lease period. The approved leasing deal for KTMB may tip the scale in favour of the truck and VSHORAD proposals.
      LEASE PESAWAT
      ITTC is currently providing Fighter Lead-In Training (FLIT) to the Royal Malonn Air Force in London, Ontario. ITTC operates a fleet of Aero Vodochody L-39 featuring upgraded avionics for the FLIT programme
      LEASE SIMULATOR MKM TAHUN
      Five-year contract for Sukhoi’s simulators. Publicly listed HeiTech Padu Bhd has announced that it had been awarded a RM67 million, five-year contract to operate and maintain the Su-30MKM flight simulators at the RMAF airbase in Gong Kedak
      LEASE HELI LEASE SIMULATOR
      Kerajaan sebelum ini pernah menyewa Helikopter Latihan Airbus EC120B dan Flight Simulation Training Device (FSTD) Untuk Kegunaan Kursus Asas Juruterbang Helikopter TUDM. Selain itu, kerajaan turut pernah menyewa 5 unit Helikopter EC120B; 1 unit Sistem Simulator
      LEASE HELI
      4 buah Helikopter Leonardo AW 139 yang diperolehi secara LEASEan ini adalah untuk kegunaan Tentera Udara Diraja Malon (TUDM) yang akan ditempatkan di NO.3 Skuadron, Pangkalan Udara Butterworth
      LEASE BOAT
      LEASEan Bot Op Pasir merangkumi 10 unit Fast Interceptor Boat (FIB); 10 unit Utility Boat; 10 unit Rigid Hull Fender Boat (RHFB); 10 unit Rover Fiber Glass (Rover).
      LEASE HIDROGRAFI
      tugas pemetaan data batimetri bagi kawasan perairan negara akan dilakukan oleh sebuah kapal hidrografi moden, MV Aishah AIM 4, yang diperoleh menerusi kontrak LEASEan dari syarikat Breitlink Engineering Services Sdn Bhd (BESSB)
      LEASE 4x4
      Pejabat perusahaan mengatakan kepada Janes di pameran bahwa Angkatan Bersenjata Malon sedang mencari untuk menyewa Tarantula
      LEASE MOTOR
      The Royal Military Police Corp (KPTD) celebrated the lease of 40 brand-new BMW R1250RT Superbikes for the Enforcement Motorcycle Squad on December 22nd, 2022
      LEASE PATROL BOATS : LEASE OUTBOARD MOTORS : LEASE TRAILERS
      Meanwhile, the division also published a tender for eleven glass reinforced plastic patrol boats together outboard motors, trailers and associated equipment. The tender was published on February 28 and closes on March 29. The estimated cost of the tender is RM4.6 million..
      LEASE 28 HELI
      The government signed an agreement with Weststar Aviation Sdn Bhd to lease 28 helicopters for use by ministries and other government agencies
      ..

      Hapus
    3. Kasihan TLDM di prank kapal miring dan mangkrak. Tapi gpp masih ada beruk Tolol Gempurwaria yg masih menghibur diri di DS.lanjut Pork.

      Hapus
  67. 🤣🤣🤣.... TENGGELAM guys....

    Duh, Kapal Baru Bakamla Ini Nyaris Tenggelam

    https://news.detik.com/foto-news/d-4442174/duh-kapal-baru-bakamla-ini-nyaris-tenggelam

    BalasHapus
    Balasan
    1. KAPAL 1978
      PENDEKAR BOCOR TENGGELAM
      Kuala Lumpur: Tentera Laut Diraja Malon (TLDM) mengesahkan Kapal Diraja (KD) Pendekar mengalami kebocoran dan kebanjiran besar di dua batu nautika Tenggara Tanjung Penyusop, Johor ketika sedang melaksanakan penugasan operasi.
      -
      READINESS 58.6%
      Panglima Tentera Laut, Laksamana Tan Sri Abdul Rahman Ayob hari ini menyatakan tahap kesiagaan armada Tentera Laut Diraja Malon (TLDM) adalah di bawah sasaran.
      Perkara tersebut dinyatakan oleh beliau semasa menyampaikan Perutusan Tahun Baharu 2024 dan Setahun Pemerintahan Panglima Tentera Laut di Wisma Pertahanan.
      “Kesiagaan TLDM masih berada di bawah sasaran iaitu 58.6% berbanding sasaran 75%,
      -
      OBSOLETE ....
      PM Anwar said he had been astonished to see a navy frigate dating from the 1970s on display at the recent LIMA maritime and aerospace expo in Langkawi. “I want to salute these ships but I don’t know where to put my face. The last frigate (on display at LIMA) was from 1998,” he said
      -
      ASET USANG
      masalah penggunaan aset usang ini bukan hanya membabitkan pelbagai ketumbukan dalam Angkatan Tentera Malon (ATM), malah Polis Diraja Malon (PDRM), Agensi Penguatkuasaan Maritim Malon (Maritim Malon) dan pasukan keselamatan lain sebagai sebahagian daripada barisan pertahanan negara.
      -
      RONGSOK KAPAL 1967 = The post stated that among his achievements in the MMEA were that he was the team leader for a suitability study on absorbing the US Coast Guard cutter – USCG Decisive. Checks on the US Coast Guard website showed that Decisive– a Reliance class cutter – was laid in 1967 and commissioned in 1968
      -
      RONGSOK KAPAL SELAM BEKAS 1970 = In 2002, Malon signed a contract with France for acquisition of two Scorpène-class diesel-electric submarines.3 As part of the submarine induction process, Malon also negotiated for an ex-French Agosta 70-class submarine – Quessant – to be based in Toulon for RMN crew training and instruction
      -
      RONGSOK KAPAL 1980 = KM Perwira, one of the two Bay class patrol boats donated to MMEA by Australia. It is likely that the Bay class was the design proposed for the tri-nation VLPV project in the late 80s.
      -
      RONGSOK KAPAL 1989 DAN 1991 = Jepang menghibahkan dua kapal kelas 90m masing-masing PL-01 Ojima dan PL-02 Erimo, kedua kapal ini masuk dinas di JCG pada tahun 1989 dan 1991.
      -
      RONGSOK KAPAL 1990–1991 = KM Pekan is an Ojika-class offshore patrol vessel operated by the Malonn Coast Guard. This ship, together with KM Arau and KM Marlin was transferred from the Japan Coast Guard to Malon in order to strengthen the relations between the two countries. The ship was built as the Ojika for the Japanese Coast Guard in 1990–1991
      -
      RONGSOK KAPAL 1989 = KM Arau is an offshore patrol vessel operated by the Malonn Coast Guard. She was the second ship transferred from the Japan Coast Guard together with KM Pekan and KM Marlin. KM Arau was formerly kNOwn as Oki (PL-01) in the Japan Coast Guard.
      -
      RONGSOK 1960 BEKAS MARINE POLICE BEKAS MMEA = RMN informed us that they are getting a new boat – albeit a third hand one – courtesy of the MMEA. MMEA received from the Marine police back in 2011.
      -
      RONGSOK BEKAS MMEA = RMN has taken delivery of ex-Sundang on October 23 after the patrol craft completed its refit. She is the first of two ex-MMEA PC
      ===========================
      2024 OVER LIMIT DEBT 65,6%
      2024 OVER LIMIT DEBT 65,6%
      2024 OVER LIMIT DEBT 65,6%
      Malon Government debt accounted for 65.6 % of the country's Nominal GDP in Mar 2024, compared with the ratio of 64.3 % in the previous quarter. Malon government debt to GDP ratio data is updated quarterly, available from Dec 2010 to Mar 2024.
      ------------------
      HASIL STUDI = BELANJA PERTAHANAN TERGANTUNG HUTANG
      The results reveal a robust positive association between Public Debt and Defence Spending, substantiated by the significant coefficient of 0.7601 (p < 0.01). This suggests that an increase in Public Debt corresponds to a substantial rise in Defence Spending.

      Hapus
  68. KAPAL 1978
    PENDEKAR BOCOR TENGGELAM
    Kuala Lumpur: Tentera Laut Diraja Malon (TLDM) mengesahkan Kapal Diraja (KD) Pendekar mengalami kebocoran dan kebanjiran besar di dua batu nautika Tenggara Tanjung Penyusop, Johor ketika sedang melaksanakan penugasan operasi.
    -
    READINESS 58.6%
    Panglima Tentera Laut, Laksamana Tan Sri Abdul Rahman Ayob hari ini menyatakan tahap kesiagaan armada Tentera Laut Diraja Malon (TLDM) adalah di bawah sasaran.
    Perkara tersebut dinyatakan oleh beliau semasa menyampaikan Perutusan Tahun Baharu 2024 dan Setahun Pemerintahan Panglima Tentera Laut di Wisma Pertahanan.
    “Kesiagaan TLDM masih berada di bawah sasaran iaitu 58.6% berbanding sasaran 75%,
    -
    OBSOLETE ....
    PM Anwar said he had been astonished to see a navy frigate dating from the 1970s on display at the recent LIMA maritime and aerospace expo in Langkawi. “I want to salute these ships but I don’t know where to put my face. The last frigate (on display at LIMA) was from 1998,” he said
    -
    ASET USANG
    masalah penggunaan aset usang ini bukan hanya membabitkan pelbagai ketumbukan dalam Angkatan Tentera Malon (ATM), malah Polis Diraja Malon (PDRM), Agensi Penguatkuasaan Maritim Malon (Maritim Malon) dan pasukan keselamatan lain sebagai sebahagian daripada barisan pertahanan negara.
    -
    RONGSOK KAPAL 1967 = The post stated that among his achievements in the MMEA were that he was the team leader for a suitability study on absorbing the US Coast Guard cutter – USCG Decisive. Checks on the US Coast Guard website showed that Decisive– a Reliance class cutter – was laid in 1967 and commissioned in 1968
    -
    RONGSOK KAPAL SELAM BEKAS 1970 = In 2002, Malon signed a contract with France for acquisition of two Scorpène-class diesel-electric submarines.3 As part of the submarine induction process, Malon also negotiated for an ex-French Agosta 70-class submarine – Quessant – to be based in Toulon for RMN crew training and instruction
    -
    RONGSOK KAPAL 1980 = KM Perwira, one of the two Bay class patrol boats donated to MMEA by Australia. It is likely that the Bay class was the design proposed for the tri-nation VLPV project in the late 80s.
    -
    RONGSOK KAPAL 1989 DAN 1991 = Jepang menghibahkan dua kapal kelas 90m masing-masing PL-01 Ojima dan PL-02 Erimo, kedua kapal ini masuk dinas di JCG pada tahun 1989 dan 1991.
    -
    RONGSOK KAPAL 1990–1991 = KM Pekan is an Ojika-class offshore patrol vessel operated by the Malonn Coast Guard. This ship, together with KM Arau and KM Marlin was transferred from the Japan Coast Guard to Malon in order to strengthen the relations between the two countries. The ship was built as the Ojika for the Japanese Coast Guard in 1990–1991
    -
    RONGSOK KAPAL 1989 = KM Arau is an offshore patrol vessel operated by the Malonn Coast Guard. She was the second ship transferred from the Japan Coast Guard together with KM Pekan and KM Marlin. KM Arau was formerly kNOwn as Oki (PL-01) in the Japan Coast Guard.
    -
    RONGSOK 1960 BEKAS MARINE POLICE BEKAS MMEA = RMN informed us that they are getting a new boat – albeit a third hand one – courtesy of the MMEA. MMEA received from the Marine police back in 2011.
    -
    RONGSOK BEKAS MMEA = RMN has taken delivery of ex-Sundang on October 23 after the patrol craft completed its refit. She is the first of two ex-MMEA PC
    ===========================
    2024 OVER LIMIT DEBT 65,6%
    2024 OVER LIMIT DEBT 65,6%
    2024 OVER LIMIT DEBT 65,6%
    Malon Government debt accounted for 65.6 % of the country's Nominal GDP in Mar 2024, compared with the ratio of 64.3 % in the previous quarter. Malon government debt to GDP ratio data is updated quarterly, available from Dec 2010 to Mar 2024.
    ------------------
    HASIL STUDI = BELANJA PERTAHANAN TERGANTUNG HUTANG
    The results reveal a robust positive association between Public Debt and Defence Spending, substantiated by the significant coefficient of 0.7601 (p < 0.01). This suggests that an increase in Public Debt corresponds to a substantial rise in Defence Spending.

    BalasHapus
  69. Kasihan kerajaan MALON rugi besar proyek opv GAGAL.
    Siap2 keluar duit tambahan lagi bila mau lanjut. Yang jelas duit sisa kontrak plus denda gak bakalan cukup selesaikan 2 kapal opv tersisa

    Kasihan MALON 🤣🤣🤣🤣🤣

    BalasHapus
  70. KAPAL 1978
    PENDEKAR BOCOR TENGGELAM
    Kuala Lumpur: Tentera Laut Diraja Malon (TLDM) mengesahkan Kapal Diraja (KD) Pendekar mengalami kebocoran dan kebanjiran besar di dua batu nautika Tenggara Tanjung Penyusop, Johor ketika sedang melaksanakan penugasan operasi.
    -
    READINESS 58.6%
    Panglima Tentera Laut, Laksamana Tan Sri Abdul Rahman Ayob hari ini menyatakan tahap kesiagaan armada Tentera Laut Diraja Malon (TLDM) adalah di bawah sasaran.
    Perkara tersebut dinyatakan oleh beliau semasa menyampaikan Perutusan Tahun Baharu 2024 dan Setahun Pemerintahan Panglima Tentera Laut di Wisma Pertahanan.
    “Kesiagaan TLDM masih berada di bawah sasaran iaitu 58.6% berbanding sasaran 75%,
    -
    OBSOLETE ....
    PM Anwar said he had been astonished to see a navy frigate dating from the 1970s on display at the recent LIMA maritime and aerospace expo in Langkawi. “I want to salute these ships but I don’t know where to put my face. The last frigate (on display at LIMA) was from 1998,” he said
    -
    ASET USANG
    masalah penggunaan aset usang ini bukan hanya membabitkan pelbagai ketumbukan dalam Angkatan Tentera Malon (ATM), malah Polis Diraja Malon (PDRM), Agensi Penguatkuasaan Maritim Malon (Maritim Malon) dan pasukan keselamatan lain sebagai sebahagian daripada barisan pertahanan negara.
    -
    RONGSOK KAPAL 1967 = The post stated that among his achievements in the MMEA were that he was the team leader for a suitability study on absorbing the US Coast Guard cutter – USCG Decisive. Checks on the US Coast Guard website showed that Decisive– a Reliance class cutter – was laid in 1967 and commissioned in 1968
    -
    RONGSOK KAPAL SELAM BEKAS 1970 = In 2002, Malon signed a contract with France for acquisition of two Scorpène-class diesel-electric submarines.3 As part of the submarine induction process, Malon also negotiated for an ex-French Agosta 70-class submarine – Quessant – to be based in Toulon for RMN crew training and instruction
    -
    RONGSOK KAPAL 1980 = KM Perwira, one of the two Bay class patrol boats donated to MMEA by Australia. It is likely that the Bay class was the design proposed for the tri-nation VLPV project in the late 80s.
    -
    RONGSOK KAPAL 1989 DAN 1991 = Jepang menghibahkan dua kapal kelas 90m masing-masing PL-01 Ojima dan PL-02 Erimo, kedua kapal ini masuk dinas di JCG pada tahun 1989 dan 1991.
    -
    RONGSOK KAPAL 1990–1991 = KM Pekan is an Ojika-class offshore patrol vessel operated by the Malonn Coast Guard. This ship, together with KM Arau and KM Marlin was transferred from the Japan Coast Guard to Malon in order to strengthen the relations between the two countries. The ship was built as the Ojika for the Japanese Coast Guard in 1990–1991
    -
    RONGSOK KAPAL 1989 = KM Arau is an offshore patrol vessel operated by the Malonn Coast Guard. She was the second ship transferred from the Japan Coast Guard together with KM Pekan and KM Marlin. KM Arau was formerly kNOwn as Oki (PL-01) in the Japan Coast Guard.
    -
    RONGSOK 1960 BEKAS MARINE POLICE BEKAS MMEA = RMN informed us that they are getting a new boat – albeit a third hand one – courtesy of the MMEA. MMEA received from the Marine police back in 2011.
    -
    RONGSOK BEKAS MMEA = RMN has taken delivery of ex-Sundang on October 23 after the patrol craft completed its refit. She is the first of two ex-MMEA PC
    ===========================
    2024 OVER LIMIT DEBT 65,6%
    2024 OVER LIMIT DEBT 65,6%
    2024 OVER LIMIT DEBT 65,6%
    Malon Government debt accounted for 65.6 % of the country's Nominal GDP in Mar 2024, compared with the ratio of 64.3 % in the previous quarter. Malon government debt to GDP ratio data is updated quarterly, available from Dec 2010 to Mar 2024.
    ------------------
    HASIL STUDI = BELANJA PERTAHANAN TERGANTUNG HUTANG
    The results reveal a robust positive association between Public Debt and Defence Spending, substantiated by the significant coefficient of 0.7601 (p < 0.01). This suggests that an increase in Public Debt corresponds to a substantial rise in Defence Spending.

    BalasHapus
  71. OPV MALON GAGAL

    KATA MALON MINIM LITERASI MASIH ON TRACK DAN AKAN DILANJUT
    🤣🤣🤣🤣🤣🤣

    BalasHapus
  72. JALAN TERUS vesi MALAYDESH...

    KONTRAK KOSONG ➡ SALAH POTONG➡ MANGKRAK➡ JALAN MIRING➡ DELAL TAHUNAN ➡GAGAL TOTAL... HAHAHAHAHA


    MEMALUKAN... Hahahahah😂😂😂😂

    BalasHapus
  73. JALAN TERUS vesi MALAYDESH...

    KONTRAK KOSONG ➡ SALAH POTONG➡ MANGKRAK➡ JALAN MIRING➡ DELAY TAHUNAN ➡GAGAL TOTAL... HAHAHAHAHA


    MEMALUKAN... Hahahahah😂😂😂😂

    BalasHapus
  74. Kasihan GAGAL TOTAL buat geng MALAYDESH semakin NGAMUK... Hahahahahahaha


    GAGAL LAGI....

    BalasHapus
  75. Satu kata buat pembuatan kapal ini... TOLOL..😂😂😂😂

    Satu kata buat MALAYDESH dan pendukungnya... KASIHAN....😂😂😂😂😂😂


    😂😂😂😂

    BalasHapus
  76. Memang benar geng MALON nih kalau sudah bina kapal tidak jau dari kata..

    KORUPSI.. MANGKRAK.. SALAH POTONG.. MIRING.. GAGAL TOTAL...


    HAHAHAH... 😂😂😂😂

    BalasHapus
  77. Seperti dugaan om palu gada, last last kensel. Keh keh keh

    BalasHapus
  78. Di buat 2017
    Sembang AKAN diserah 2020

    OPV#1 :
    Mangkrak..
    Miring..
    Miring..
    Miring...
    Balik naik dock..
    Akhirnya diserah

    Senyap..senyap..senyap...
    2025 : #2 & #3 GAGAL.

    hahahahahahah

    🤣🤣😂😂🤣🤣

    BalasHapus
  79. Kasih paham sedikit inilah kehebatan galangan kapal kami..

    Bukan GAGAL TOTAL ya guys... Hahahahahaha

    BACA...

    Dua kapal perang baru untuk TNI Angkatan Laut jenis Offshore Patrol Vessel (OPV) 90 meter, resmi diberi nama KRI Raja Haji Fisabilillah (RHF)-391 dan KRI Lukas Rumkorem (LRK)-392.

    Kedua kapal perang tersebut diproduksi PT Daya Radar Utama (DRU) di Lampung dan didesain sebagai kapal kombatan maupun patroli, yang memiliki kecepatan tinggi dan bisa beroperasi di seluruh perairan Indonesia.

    Untuk konstruksi, kapal perang OPV ini menggunakan monohull yang dirancang untuk mendapatkan performa yang baik saat melaju dengan kecepatan tinggi sekitar 28 knot maupun pada kecepatan jelajah sekitar 20 knot.

    Direktur PT DRU, John Wijanarko dalam sambutannya menyatakan, pihaknya merupakan galangan kapal pertama yang diberi kepercayaan oleh Kementerian Pertahanan untuk membangun kapal OPV.

    “Kapal OPV yang kami bangun akan dilengkapi dengan persenjataan peperangan anti serangan udara, permukaan laut, dan bawah air, sehingga kapal OPV yang memiliki fungsi sebagai kapal Patroling Force dapat dioperasikan menjadi kapal Striking Force, untuk menambah kekuatan alutsista TNI Angkatan Laut,” tutur John Wijanarko.

    “Dengan kemampuan yang meliputi anti serangan udara, permukaan laut, dan bawah air, kapal OPV yang kami bangun telah memenuhi syarat sebagai kapal jenis Light Frigate,” tambah John.

    BalasHapus
  80. Dimulai Januari 2017 dan projek tersebut sepatutnya siap sepenuhnya pada Julai 2020...

    ====
    Sekarang tahun 2025, guys itu 8 tahun guys...

    Pikir sendiri kesimpulannya

    Hahahahahahah...😂😂🤣🤣😛😛😛

    BalasHapus
  81. Proyek aset Malaydesh konon tak NGUTANG, tapi selalu Mangkrak & Over price gila...

    Lebih baik mana jika berbanding pakai biaya kredit tapi ontime delivery..?

    Hahahahahahahaa....🤣🤣😂😂😂😂🤣

    BalasHapus
  82. 2029-2020 : 10 YEARS = OVERLIMIT DEBT
    2029-2020 : 10 YEARS = OVERLIMIT DEBT
    DEBT RATIO TO GDP.......
    2029 = 69,54%
    2028 = 69,34%
    2027 = 68,8%
    2026 = 68,17%
    2025 = 68,07%
    2024 = 68,38%
    2023 = 69,76%
    2022 = 65,5%
    2021 = 69,16%
    2020 = 67,69%
    BY STATISTA ......
    ================
    LEASE HONDA CIVIC
    LEASE 40 BMW SUPERBIKES
    Leased BMW superbikes for military police. The Army’s military police – Kor Polis Tentera Di Raja – took delivery of 40 BMW R1250RT super bikes today. The superbikes are under lease from Syarikat Ammo Defence Sdn Bhd under a RM13.7 million Letter of Award.
    As for leasing vehicles, this has been common practise by government departments for the decade or so as it is supposed to be cheaper overall. The MPs had also taken delivery of Honda Civics under a leasing programme,
    -----
    LEASE FAST INTERCEPTOR BOAT
    LEASE UTILITY BOAT
    LEASE RIGID HULL FENDER BOAT
    LEASE ROVER FIBER GLASS
    LEASE EC120B
    LEASE FLIGHT SIMULATION TRAINING DEVICE
    Mungkin ada yang tertanya-tanya, namun kaedah penyewaan ini bukanlah kali pertama dilakukan. Kerajaan sebelum ini pernah menyewa Helikopter Latihan Airbus EC120B dan Flight Simulation Training Device (FSTD) Untuk Kegunaan Kursus Asas Juruterbang Helikopter TUDM.
    Selain itu, kerajaan turut pernah menyewa 5 unit Helikopter EC120B; 1 unit Sistem Simulator dan LEASEan Bot Op Pasir merangkumi 10 unit Fast Interceptor Boat (FIB); 10 unit Utility Boat; 10 unit Rigid Hull Fender Boat (RHFB); 10 unit Rover Fiber Glass (Rover).
    -----
    LEASE KAPAL HIDROLOGI
    LEASE KAPAL HIDROLOGI
    LEASE KAPAL HIDROLOGI
    Panglima TLDM Laksamana Tan Sri Ahmad Kamarulzaman Ahmad Badaruddin berkata Aishah Aims 4 diperoleh melalui kontrak LEASEan bagi menggantikan dua kapal hidrografi sedia ada milik TLDM iaitu KD Mutiara dan KD Perantau yang akan melalui proses lucut tauliah secara berperingkat.
    ===================
    17 KREDITUR LCS
    17 KREDITUR LCS
    17 KREDITUR LCS
    Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT FINANCE HOUSE (Malonn) Bhd.

    BalasHapus
  83. Ampyun deh malon lomlonlon parah banget negara tukang klaim hahaha lonlonlon bidoh miskin

    BalasHapus
  84. NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
    NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
    NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
    NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
    -------------------
    GOODBYE = 2025 OPV TAMAT
    GOODBYE = 2025 OPV TAMAT
    GOODBYE = 2025 OPV TAMAT
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
    -----
    LCS 2025-2011 = 15 TAHUN
    15 TAHUN MANGKRAK
    15 TAHUN MANGKRAK
    LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
    -----
    17 KREDITUR LCS
    17 KREDITUR LCS
    17 KREDITUR LCS
    Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT

    BalasHapus
  85. NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
    NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
    NGPVs PLANNED 27 SHIPS = TAMAT 21 SHIPS
    NGPVs DIBAYAR 27 JADI 6 = The Kedah-class offshore patrol vessels of the Royal Malonnn Navy (RMN) are six ships based on the MEKO 100 design by Blohm + Voss. Originally, a total of 27 ships were planned, but due to programme delays and overruns, only six were eventually ordered. Their construction began in the early 2000s, and by 2009, all six were in active service.
    -------------------
    OPV 2 DAN OPV 3 = TAMAT
    OPV 2 DAN OPV 3 = TAMAT
    OPV 2 DAN OPV 3 = TAMAT
    Beliau berkata keputusan itu dipersetujui oleh Kabinet pada 22 Mac 2024 sebelum ia dilaksanakan.
    “Kementerian Dalam Negeri dibenarkan menamatkan kontrak projek tersebut setelah mendapat pandangan daripada Jabatan Peguam Negara. Sehubungan itu, kerajaan menandatangani perjanjian penamatan bersama pihak syarikat pada 31 Disember 2024,” katanya dalam jawapan bertulis yang dimuat naik dalam laman web Parlimen pada Khamis malam.
    Saifuddin berkata TDSB turut dikenakan LAD di atas kelewatan penyiapan kapal OPV 1 yang berjumlah RM5.58 juta [AS$1.26 juta] dan RM9,600 [AS$2,167] bagi kelewatan pembekalan baki 12 unit General Purpose Machine Gun (GPMG) serta pembekalan Unmanned Aerial Vehicle (UAV) bermula 1 Oktober 2024 hingga tarikh penerimaan oleh kerajaan.
    -----
    LCS 2025-2011 = 15 TAHUN
    15 TAHUN MANGKRAK
    15 TAHUN MANGKRAK
    LCS DIBAYAR 6 RM 11.2 BILLION NOT YET DELIVERED = The cost of the LCS project is NOw RM11.2 billion. It must be NOted from that RM11.2 billion, Lunas or the former BNS used around RM1 billion to pay its debts and to upgrade the facilities for the LCS project. And NOt a single ship has been delivered yet.
    -----
    17 KREDITUR LCS
    17 KREDITUR LCS
    17 KREDITUR LCS
    Besides MTU Services, others include Contraves Sdn Bhd, Axima Concept SA, Contraves Advanced Devices Sdn Bhd, Contraves Electrodynamics Sdn Bhd and Tyco Fire, Security & Services Malonn Sdn Bhd, as well as iXblue SAS, iXblue Sdn Bhd and Protank Mission Systems Sdn Bhd. Also included are Bank Pembangunan Malonn Bhd, AmBank Islamic Bhd, AmBank (M) Bhd, MTU Services, Affin Hwang Investment Bank Bhd, Bank Muamalat Malonn Bhd, Affin Bank Bhd, Bank Kerjasama Rakyat Malonn Bhd, Malayan Banking Bhd (Maybank) and KUWAIT
    ===============
    PROBLEMS SHIPYARD
    PROBLEMS SHIPYARD
    PROBLEMS SHIPYARD
    Local shipyards have poor record building big ships. LCS is one, Kedah is the first. The MMEA OPV is the other one. No need to be a cheerleader about it and trying to play it safe. It’s bad then it’s bad. Can blame the system, blame the politicians, blame the lack of controls, blame the people, the fact remains the local shipyards failed to deliver, and it has cost RMN. Less we forget, BNS (from the days of PSC-ND) had more than 20+ years to learn building complex ships. Also, the shipbuilding pipeline is too limited to support a local industry, meaning there is no learning possible – BNS (and its predecessor PSC-ND) only had contract to build 12 warships in its existence. In fact, come 2030, after 30 years, if we’re lucky the shipyard would still only have built 11 ships. In contrast ST Engineering had more than 40 ships over 28 years and have confirmed 6 new ships out to 2030. Learning is one thing, tolerating “still learning” after 20 plus years is not good enough. Not recognising learning is not possible because of limited pipeline is another. Local shipyards have proven capable of building certain type of ships because of good pipeline, so good for them that they win those contract – they can learn over time to build bigger ships. But for now, no need to be a cheerleader for local shipyards pitching to win big ships for RMN and MMEA

    BalasHapus
  86. Malonn's defense policy faces a number of challenges, including:
    • Corruption
    The military has been accused of corruption in defense procurement. The government's Integrity Plan addresses corruption, but it's not a strategic document.
    • Recruitment
    The military has difficulty recruiting and retaining qualified personnel. This is partly due to poor service conditions.
    • Infrastructure
    The defense infrastructure needs to be fixed, but the government is prioritizing other needs.
    • Ethnic composition
    The armed forces are overrepresented by Indigenous Malonnns (Bumiputeras) and underrepresented by ethnic Chinese Malonnns.
    • Budget
    Malonn has consistently underspent on defense needs.
    • Defense industry
    The defense industry has challenges with research and development, technology transfer, and job creation.
    • Territorial disputes
    Malonn has territorial disputes and intrusions in its Exclusive Economic Zone (EEZ).
    • Transboundary haze
    Transboundary haze has had a negative impact on Malonn's economy and social activities.
    • Maritime defense
    The Strait of Singapore is critical for Malonn's maritime defense, but it's also important for international commerce.
    Some of the challenges have been addressed by the Anwar government, which has implemented plans to attract more non-Bumiputeras to the military.
    ===========
    Some factors that contribute to the Malonn Army's perceived weakness include:
    • Political instability: Frequent government changes since 2018 have made it difficult for the Malonn Armed Forces (MAF) to receive the support it needs.
    • Corruption: The MAF has been plagued by corruption.
    • Poor planning: The MAF has been criticized for poor planning.
    • Political interference: Political leaders have interfered in the MAF's procurement process.
    • Outdated equipment: Much of the MAF's equipment was purchased between the 1970s and 1990s, and the government has been unable to provide modern equipment.
    Lack of military knowledge: Military personnel have struggled with decision-making and problem-solving during military operations

    BalasHapus
  87. Admin kejam up berita MALAYSEWA pasti yg bikin Beruk Gempurwaria ngamuk. Memang gak ada berita yg bermutu tentang Malon Yah?

    BalasHapus
  88. Beruk Malondesh gagal lagi, gagal lagi....

    Beruk Malondesh memang IDIOT !!

    🤣🤣🤣🤣🤣

    BalasHapus
  89. Ketika beruk disuruh bikin kapal... Ya begini jadinya. Serahkan saja ke ahlinya PT PAL

    BalasHapus
  90. SAMPEK KIAMAT GAK AKAN BISA BUAT KAPAL UNTUK PERTAHANAN NEGARA RAKYAT MALAKA..

    ITU SUDAH DARI SANA NYA...
    SEBELUM MOJOPAHIT..
    SUDAH DITAKDIRKAN RAKYAT MALAKA ITU TERBUODOH DI PLANET INI..


    DULU SAYAPUN TAK PERCAYA TAPI BEGITU DISANA DULU SAYA GELENG KEPALA..

    KALAU SAMPAN, PERAHU, BOATLAH BALING BOAT KECIL MEREKA BISA..

    ITU KARENA BUDAYA DAN TRADISI JUGA JIWA MARITIMNYA RAKYAT MALAKA SAMA SEKALI TIDAK ADA DALAM SEJARAH DUNIA..
    💪🇲🇨⚓🔥🔥🔥🔥🔥⚔️

    BalasHapus
  91. Mau ketawa takut dosa 😁😁😁😁😁

    BalasHapus
  92. MALON buat kapal GAGAL terus, padahal sudah beli lisensi dan tot ....
    1. NGPV Kedah class
    2. Kapal latih
    3. LCS
    4. OPV

    Empat galangan kapal dari 4 negara dipermalukan MALON
    🤣🤣🤣🤣🤣

    BalasHapus
  93. It is interesting to note that 70 per cent of the materials for the OPV is sourced from overseas and most of it come from China – most likely the steel or aluminium
    -----

    jiaahh besi baja tipis dari Elder Brader
    Low Kualiti, ktemu CCG sungkem haha!🤣🤣🤣
    Murah aja Ngutang sampe minta suntik RM 152 juta haha!🥶🤥🥶

    BalasHapus
  94. fatime..fatime..ente jaga warung sendiri yak, si fatona ama siti kagak jadi kerja, kaburrrrr haha!🤭🤭🤭

    BalasHapus
  95. Hamiwoww...Hamiwoww...Melambaiii...haha!🤭🍌🤭

    BalasHapus
  96. Sembang kaya , bilang sahaja malaydesh takde duitt

    BalasHapus
  97. Malon bina kapal pasti mangkrak 🤣😁

    BalasHapus
  98. Klaim
    Konon katanya kapal Jong Majapahit adalah buatan beruk Malondesh dengan nama kapal Jong Malaya.

    Bukti klaim beruk Malondesh buat kapal gagal terus .

    Beruk Malondesh hanya kuat bual dan klaim

    🤣🤣🤣🤣

    BalasHapus
  99. Malonn's military has been described as weak due to a number of factors, including corruption, poor planning, and small budgets.
    Small budgets
    • The Malonnn military has had small procurement budgets for the past 25 years.
    • The government has had to focus on other priorities, such as the economy and the COVID-19 pandemic.
    Aging equipment
    • The Malonnn military's equipment is aging. For example, the air force's MiG-29 Fulcrum fighter aircraft were withdrawn from service in 2017.
    Corruption
    • The Malonnn military has been plagued by corruption.
    • Political leaders have interfered with procurement.
    Frequent government changes
    • Malonn has had frequent government changes since 2018.
    • This has made it difficult to develop a consistent defense strategy.
    Influence of British structure
    • The Malonnn military's structure is based on the British model, which was developed for counter-insurgency warfare.
    • This has influenced the military's strategy, training, and development.
    Lowy Institute Asia Power Index
    • The Lowy Institute Asia Power Index ranks Malonn's military capability 16th in the region.

    BalasHapus
  100. Gagaal tamat hahahahhaa

    Malon hanya bisa buat kapal kecik boat nelayan🤭☺😂

    BalasHapus
  101. Lon buat kapal sampan aja dah sana.

    OPV tamat
    LCs bau bau delayy lagi 😂😂😂😂😂

    BalasHapus
  102. Gagal ya hahahha
    Galangan kapal malon musti belajar dri timor leste aja
    Kalis hutang lah,cash lah bual bual sedapkan hati aja
    Nyatanya tidak sesuai dgn berita

    Wkwkwkkw😂😂😂😂

    BalasHapus
  103. Klaim kaya,kalis hutang nyatanya gagal hahahah

    Failed again

    BalasHapus
  104. Udah wahai malon lebih bgus sewa aja

    BalasHapus
  105. Memang gak masuk akal Kapal 3 Kontrak 170 juta dollar. Brarti per unit 52 Juta Dollar US mana ada kapal segitu..belum wang kopi nya . Yaa boncos tuh company....gitulah tak ada kepakaran....🤪🤪🤪🤪🤪

    BalasHapus